Construction Defect Case Not Over, Despite Summary Judgment
November 07, 2012 —
CDJ STAFFThe Supreme Court of Oregon has concluded in an en banc decision that a motion to reconsider a summary judgment is not a motion for a new trial. In coming to their conclusion the court overturned an earlier Oregon Supreme Court case, Carter v. U.S. National Bank. Although the decision does not bear on construction defects, the underlying case did. Due to the decision, these claims can now be evaluated in a trial.
The case, Association of Unit Owners of Timbercrest Condominiums v. Warren, came about after an apartment complex was converted into condominium units. The developers hired Big Al’s Construction for some of the remodeling work. The condominium association later sued the developer and the contractor over claims of construction defects. The defendants filed a motion for summary judgment, which the court granted.
But that wasn’t the end of things. The plaintiff soon filed a “motion to reconsider,” noting that the summary judgment seemed to be in conflict with both law and other recent rulings, and additionally, the grounds for the decision were not in the order. The judge then notified the parties that the court had “pulled the trigger too quickly” and had seven questions for the parties to answer.
The court dismissed all claims against the defendants. The defendants filed their responses, objecting that that “‘there is no such thing’ as a motion for reconsideration.” Further, while “the rules do allow for post-judgment review of pre-judgment rulings through a motion for a new trial,” the plaintiffs had not filed for a new trial. But did they need one? They did file an appeal.
The judge in the case admitted that there was no such thing as a motion to reconsider, and felt bad about prematurely signing the judgment. The case was sent to the Court of Appeals to determine if the motion to reconsider was a request for a new trial. The Court of Appeals concurred.
In reviewing the decision, the Oregon Supreme Court concluded that there were a maximum of three questions to address. Was the motion for reconsideration a motion for a new trial? If so, was the later notice of appeal premature? And if so, was the plaintiff required to file a new appeal? The court determined that the answer to the first question was no.
Prior decisions pointed to the conclusion “that a motion for reconsideration of a summary judgment amounts to a motion for a new trial,” but here the court concluded that “our prior cases erred,” and turned to the summary judgment rule for clarification. The court noted that “the rule contemplates that summary judgment and trial are separate and distinct events.” With this conclusion, the Oregon Supreme Court remanded the case to the Court of Appeals for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
Lien Claimant’s Right to Execute against Bond Upheld in Court of Appeals
February 10, 2012 —
Douglas Reiser, Builders Council BlogStonewood v. Infinity Homes is a simple construction dispute over a matter of about $9,000.00. But sometimes these tiny little disputes turn into expensive legal battles over mere procedural quivering. In Stonewood, a small subcontractor won a big victory yesterday when the Divison 1 Court of Appeals upheld its judgment against a lien release bond posted by an owner.
Infinity Homes contracted with Stonewood Design to lay tile in one of its customer’s homes. Stonewood did the work, but Infinity withheld roughly $9,000.00 of the contract sums for what it alleged were trade damages left on the tile. The two parties were unable to come to an agreement over payment and Stonewood proceeded with a lien under RCW 60.04. It then filed an action to enforce the lien against the homeowner, Infinity and its bonding company.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
General Partner Is Not Additional Insured For Construction Defect Claim
August 26, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court determined that the project owner's general partner was not an additional insured entitled to a defense and indemnity against claims for construction defects. St. Paul Fire & Marine Ins. Co. v,. Cypress Fairway Condo. Ass'n, 2015 U.S. Dist. LEXIS 94012 (M.D. Fla. July 20, 2015).
Construction of the Cypress Fairway Condominium project took place in 1999 and 2000. Cypress Fairway Ltd. ("Cypress") was the owner and Vineland Partners , LLC ("Vineland") was its general partner. The general contractor was Winter Park Construction Company ("WPC"). Water intrusion and property damage occurred, but it was unclear when or whether the damage was known. Cypress' expert indicated that the damage began shortly after the end of construction.
In 2004, the complex was sold to Cypress Madison Ownership Company. In 2010, the Cypress Fairway Condominium Association sued Cypress and Vineland. Count V of the underlying complaint asserted there were construction defects that Cypress and Vineland were responsible for when they owned and managed the project. Count VI alleged that Cypress and Vineland negligently supplied information which the Association relied on for the purchase of the condominiums.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Privette: The “Affirmative Contribution” Exception, How Far Does It Go?
August 10, 2020 —
Courtney Arbucci, Peter A. Dubrawski & Austin F. Smith - Haight Brown & BonesteelIn Horne v. Ahern Rentals, Inc. (No. B299605, filed 6/10/2020 ord. publ. 6/10/2020), Plaintiffs filed a wrongful death action against Defendant Ahern Rentals, Inc. (“Ahern”) arising out of the fatal incident involving Ruben Dickerson (“decedent”), while employed by independent contractor 24-Hour Tire Service, Inc. Decedent was ultimately crushed on Ahern Rentals, Inc.’s property when a forklift that was improperly placed on uneven ground collapsed as decedent laid under the raised forklift as he performed tire maintenance.
Plaintiffs’ suit would normally be barred by the Privette line of decisions which arise out of the foundational principle that an independent contractor’s hirer presumptively delegates to the contractor its tort law duty to provide a safe workplace for the contractor’s employees. (Privette v. Superior Court (1993) 5 Cal.4th 689 (Privette).) The Privette rule is subject to a number of exceptions including the “peculiar risk” exception, the “nondelegable duty” exception and the “affirmative contribution” exception. (See Privette, supra.) Here, Plaintiffs’ claimed that their suit against Ahern arose out of the “affirmative contribution” exception to Privette as defined by Hooker v. Department of Transportation (2002) 27 Cal.4th 198, 202 (Hooker). Hooker allows suits otherwise barred by Privette to go forward if the hirer of the independent contractor “exercised control over safety conditions at the worksite in a way that affirmatively contributed to the employee’s injuries.”
Reprinted courtesy of Haight Brown & Bonesteel attorneys
Courtney Arbucci,
Peter A. Dubrawski and
Austin F. Smith
Ms. Arbucci may be contacted at carbucci@hbblaw.com
Mr. Dubrawski may be contacted at pdubrawski@hbblaw.com
Mr. Smith may be contacted at asmith@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Pay To Defend Product Defect Claims From Date Of Product Installation
January 31, 2018 —
Michael S. Levine & Brittany M. Davidson - Insurance Recovery BlogAn Iowa federal court recently ruled that an insurer must pay its policyholder’s defense costs from the date of installation of the allegedly faulty product, even though the underlying suits failed to allege when damage purportedly occurred. The ruling opens the door under each of the policyholder’s successive liability policies from 2000 to 2008, allowing the policyholder to recover millions of dollars in defense costs.
The policyholder sought summary judgment concerning the date(s) on which the insurer’s defense obligation was triggered by fourteen of the fifteen claims asserted against it. The policyholder argued that the duty attached from the moment property damage potentially occurred, meaning the time when the underlying claimant installed or potentially could have installed the windows at issue in the underlying claims. The policyholder cited to the following evidence to support its claim: actual dates of installation (where available), dates of delivery, purchase or manufacture of the windows; and policy period referenced in the insurer’s claims notes as being potentially implicated by the claim.
Reprinted courtesy of
Michael S. Levine, Hunton & Williams and
Brittany M. Davidson, Hunton & Williams
Mr. Levine may be contacted at mlevine@hunton.com
Ms. Davidson may be contacted at davidsonb@hunton.com
Read the court decisionRead the full story...Reprinted courtesy of
Denver Airport Terminates P3 Contract For Main Terminal Renovation
November 12, 2019 —
Mark Shaw - Engineering News-RecordIn a move that stunned transportation planners around the country, Denver International Airport terminated the contractor team working on a $650-million terminal renovation. The move also ended the airport’s $1.8-billion public-private partnership with Great Hall Partners, a consortium led by Ferrovial Airports, with partners Saunders/JLC Infrastructure.
Mark Shaw, Engineering News-Record
Mr. Shaw may be contacted at shawm@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Maryland Finally set to Diagnose an Allocation Method for Progressive Injuries
February 18, 2020 —
William S. Bennett - Saxe Doernberger & Vita, P.C.Maryland’s highest court recently heard arguments regarding the proper method of allocation of the covered damages from a slowly progressing asbestos injury amongst insurance policies in place over a period of years. Rossello v. Zurich American Insurance Company, Case No. 2436 (Md. 2019). The court may also be forced to determine what the proper trigger of coverage is for latent bodily injury claims, although the plaintiff has not framed the issue in that manner.
In Rossello, the plaintiff, Patrick Rossello, worked for a period of years for the now-defunct Lloyd E. Mitchell, Inc. (“Mitchell”), a construction company operating until 1976. In 1974 he was exposed to and inhaled asbestos fibers. He was ultimately diagnosed in 2013 with malignant mesothelioma as a result of that exposure. Rossello obtained a judgment for approximately $2,700,000 against Mitchell and secured the right to pursue its insurance. As relevant to this dispute, Mitchell carried liability insurance policies, which provide coverage for asbestos related claims, from 1974 to 1977.
Rossello seeks to hold Zurich, as successor to Maryland Casualty Company, accountable for the full value of his award, based on the 1974 policy. Although this contention actually implicates two separate issues, plaintiff’s counsel passed over the initial trigger of coverage issue and focused instead on the issue of allocation of coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Your Construction Contract
April 08, 2024 —
David Adelstein - Florida Construction Legal UpdatesYour construction contract is an important topic. What’s even more important is YOUR process for reviewing and negotiating construction contracts.
Are you simply acting as a riverboat gambler willing to assume undue risk because you don’t value the investment in understanding what you are signing? If so, it becomes hard to complain about what you agreed to and signed when you chose NOT to invest in the process. Investing in the process means you are working with a construction attorney, you have an insurance broker that understands your industry, you have resources in place to ensure risk is negotiated and allocated, and you understand what risk you are assuming to make sure you are properly protecting and perfecting your rights, and transferring risk downstream.
When it comes to construction contracts, there are really three approaches:
1. Riverboat Gambler. This is the “I’ll sign whatever you give me because I don’t want to lose the contract / revenue.” Under this approach, you are not worried about undue risk because you don’t value the investment in the next two approaches. Your thought process is that you’ll care about the risk when an issue pops up, i.e., the riverboat gambler. This is not an approach I’d recommend because it is contrary to the adage, “an ounce of prevention is worth a pound of cure.” This is simply a reactive approach to issues and risks. The other two approaches are more proactive and better suited to understand and manage risk.
Read the court decisionRead the full story...Reprinted courtesy of