Guessing as to your Construction Damages is Not the Best Approach
November 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitrarily guessing as to your construction damages is NOT the best approach. Sure, experts can be costly. No doubt about it. Having an expert versus guessing as to your construction damages caused by another party’s breach of contract is a no brainer. Engage an expert or, at a minimum, be in a position to competently testify as to your damages caused by another party’s breach of contract. Otherwise, the guessing is not going to get you very far as a concrete subcontractor found out in Patrick Concrete Constructors, Inc. v. Layne Christensen Co., 2018 WL 6528485 (W.D. New York 2018) where the subcontractor could not competently support its delay-related damages or change orders and, equally important, could not support that the damages were proximately caused by the general contractor’s breach of the subcontract.
In this case, the concrete subcontractor entered into a subcontract to perform concrete work for a public project. The project was delayed and the general contractor was required to pay liquidated damages to the owner. Not surprisingly, the subcontractor disputed liability for delays and sued the general contractor for all of its delay-related damages “in the form of labor and materials escalation, loss of productivity, procurement and impact costs, field and home office overhead, idle equipment, inability to take on other work, lost profits, and interest.” Patrick Concrete Constructors, 2018 WL at *1.
The general contractor moved for summary judgment as to the plaintiff’s delay-related damages – the subcontractor’s damages were nothing but guesses and the subcontractor could not prove the general contractor was the cause of the subcontractor’s damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Flying Solo: How it Helps My Construction Clients
February 18, 2015 —
Christopher G. Hill – Construction Law MusingsTwo and a half years ago, on July 1, 2010, I opened my solo practice. At the time, I really had no insight into how big this change would be from a positive, customer service, perspective.
When I made the decision to go solo with my construction law practice, I knew I wanted to have flexibility to serve my client base of contractors and subcontractors in Virginia. I started some flat rate billing and had the ability to take cases that were below the dollar value of those that my old firm was willing to take. I also knew that I would be a master of my own destiny for better or worse (and it has been much more of the former than the latter).
What I did not realize is the impact that owning my own business would have on my perspective. I have always believed that, in most cases where construction disputes occur, mediation is a great option. However mediation only occurs with conflict. For any business, whether construction or otherwise, conflict creates expenses that were not likely to have been anticipated or built in to the budget. Litigation is not something that most businesses can, or should, build into their operating budgets.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Federal Judge Refuses to Limit Coverage and Moves Forward with Policyholder’s Claims Against Insurer and Broker
December 07, 2020 —
Michael S. Levine & Casey L. Coffey - Hunton Insurance Recovery BlogOn November 10, 2020, a New York federal judge dismissed an insurer’s counterclaims seeking to cap its exposure under a $15 million sublimit and an order estopping the policyholder from pursuing any additional amounts.
In February 2017, Plaintiff Pilkington North America, Inc. (Pilkington), suffered between $60 and $100 million in damage from a tornado that struck its glass manufacturing factory in Illinois. Pilkington sought coverage for its loss under a commercial property and business interruption policy issued by Defendant Mitsui Sumitomo Insurance Company (MSI). Pilkington also claimed its insurance broker, Aon Risk Services Central, Inc. (Aon), is liable for faulty advice provided while brokering the policy. Aon’s negligence allegedly gave way to MSI’s fraudulent revision of the insurance policy, which caused the losses from the tornado to not be fully compensable.
Pilkington’s fraud and faulty brokering claims stem from MSI’s revision of an endorsement contained in the policy. The revision changed the wording of a windstorm sublimit. Allegedly, Aon was informed by MSI of the changes and failed to inform Pilkington that the revision would substantially reduce coverage for windstorms, including tornados.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Resulting Loss Provision Does Not Salvage Coverage
April 06, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court confirmed that there was no coverage for damage to the policyholder's building caused by a large volume of water. Praetorian Ins. Co. v. Arabia Shrine Ctr. Houston, 2016 U.S. Dist. LEXIS 20186 (S.D. Texas Feb. 19, 2016).
The damage occurred when water began seeping through the baseboards of the Shrine. Employees saw a large amount of water entering the building. Eventually, the city shut off a water main valve. It was later determined that an 8 inch diameter fire suppression metal pipe failed at the elbow, causing over one million gallons of water to be released into the building. Damages were estimated at nearly $1.7 million. Clean up and repair costs amounted to $237,156.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Architect Responds to Defect Lawsuit over Defects at Texas Courthouse
October 08, 2013 —
CDJ STAFFLee County, Texas has sued the architect responsible for designing the drainage system at its historic courthouse. The suit seeks $1.7 million in damages to pay for replacing the defective system and repairing the building from damage sustained due to soil saturation.
Dale A. Rabe responds that the county commissioners were more concerned with “beautifying the building” than on needed foundation repairs. Further, Mr. Rabe notes that “Lee County contracted directly with a civil engineering firm to design a drainage system.” But according to Mr. Rabe what they used instead was “a cheaper pump-based design to save money.” And even there, “Lee County failed to maintain the drainage system properly.
Read the court decisionRead the full story...Reprinted courtesy of
Florida Death Toll Rises by Three, Reaching 27 as Search Resumes
July 05, 2021 —
The Associated Press (Adriana Gomez Licon & Bobby Caina Calvan) - BloombergSurfside, Fla. (AP) -- Rescuers searched through fresh rubble Monday after the last of the collapsed Florida condo building was demolished, which allowed crews into previously inaccessible places, including bedrooms where people were believed to be sleeping at the time of the disaster, officials said.
But they faced a new challenge from thunderstorms that hit the area as Tropical Storm Elsa approached the state.
Four more victims were discovered in the new pile, Miami-Dade Assistant Fire Chief Raide Jadallah told family members, raising the death toll to 28 people. Another 117 people remain unaccounted for.
The demolition late Sunday was crucial to the search-and-rescue effort, officials said, and raised the prospect that crews could increase both the pace of their work and the number of searchers at the site, although the chance of finding survivors 12 days after the June 24 collapse has diminished.
Read the court decisionRead the full story...Reprinted courtesy of
The Associated Press, Bloomberg
Know and Meet Your Notice Requirements or Lose Your Payment Bond Claims
May 17, 2021 —
Chris Broughton, Jones Walker LLP - ConsensusDocsTime is of the essence in the construction industry, and failing to provide timely notice of your payment bond claim can end your chance of recovery. Payment bonds guarantee payment for the subcontractors and suppliers who provide labor or materials on covered construction projects. Federal and state statutes governing payment bonds on public projects and the specific terms of non-statutory, private payment bonds have strict notice and timing requirements. Claimants who fail to provide timely notice can forfeit their chance of recovery. This article provides a brief overview of the notice requirements for payment bond claims – who has to give notice, what notice is required, and when you have to give notice.
Payment bond protection is a frequent feature in construction. Payment bonds are required on most federal construction projects of over $100,000 under the federal Miller Act. Similar state statutes, typically referred to as “Little Miller Acts,” also require payment bonds on most state and local construction projects. Owners on private projects may require their general contractor to provide a payment bond to protect the property from liens. Finally, general contractors may also require subcontractors to provide payment bonds on public or private projects.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Broughton, Jones Walker LLPMr. Broughton may be contacted at
cbroughton@joneswalker.com
An Overview of the New EPA HVAC Refrigerant Regulations and Its Implications for the Construction Industry
September 30, 2024 —
Stefanie A. Salomon, Nadia Ennaji & Ali Heyat - Peckar & Abramson, P.C.The U.S. Environmental Protection Agency (EPA) recently announced a series of significant changes to the rules governing the use of refrigerants in heating, ventilation, and air conditioning (HVAC) systems. These changes, which were promulgated under the American Innovation and Manufacturing (AIM) Act, are designed to phase down the use of hydrofluorocarbons (HFCs), a class of potent greenhouse gases.
The AIM Act: A Game-Changer for HVAC Industry
The recent changes to refrigerant regulations by the EPA signify a substantial shift in environmental policy that will have profound implications for the construction industry. For the construction industry, this means a transition to next-generation technologies that do not rely on HFCs. The AIM Act’s sector-based restrictions will affect a wide range of equipment, including refrigeration and air conditioning systems integral to building design and function.
Starting January 1, 2025, the manufacturing or importing of any product in specified sectors that uses a regulated substance with a global warming potential of 700 or greater is prohibited (40 C.F.R. § 84.54(a)). The specified sectors listed include R-410A, the most common refrigerant used in the HVAC industry. The installation of systems using a regulated substance with a global warming potential of 700 or greater in specified sectors is allowed until January 1, 2026, provided that all system components are manufactured or imported before January 1, 2025. See 40 C.F.R. § 84.54 (c). “Installation” of an HVAC system is defined as the completion of assembling the system’s circuit, including charging it with a full charge, such that the system can function and is ready for its intended purpose. See 40 C.F.R. § 84.52.
Reprinted courtesy of
Stefanie A. Salomon, Peckar & Abramson, P.C. and
Nadia Ennaji, Peckar & Abramson, P.C.
Ms. Salomon may be contacted at ssalomon@pecklaw.com
Ms. Ennaji may be contacted at nennaji@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of