Don’t Believe Everything You Hear: Liability of Asbestos Pipe Manufacturer Upheld Despite Exculpatory Testimony of Plaintiff
May 24, 2021 —
Garret Murai - California Construction Law BlogIn the next case, Morgan v. J-M Manufacturing Company, Inc. 60 Cal.App.5th 1078 (2021), the 2nd District Court of Appeal upheld a $7 million personal injury verdict against an asbestos-cement pipe manufacturer despite exculpatory testimony from the plaintiff, holding that the testimony was an issue of witness credibility rather than sufficiency of the evidence, and holding that the trial court’s denial of a jury instruction requested by the pipe manufacturer was appropriate because, while the requested jury instruction was a recitation of undisputed facts, the purpose of jury instructions is to recite the law rather than facts, even undisputed ones.
The Morgan Case
Norris Morgan was exposed to asbestos at construction sites where he worked in the 1970s and 80s. After he was diagnosed with mesothelioma in December 2017, Morgan and his wife sued a number of defendants, including J-M Manufacturing for personal injuries and loss of consortium.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Walkability Increases Real Estate Values
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFCNBC reported that environmentally-conscious Millennials are looking for homes that are within walking or biking distance to stores and work. The “areas that offer so-called walkability should see more home buyers and renters than those that don't.”
"Cities that want to thrive in our new economic and demographic realities will need to find ways to create and support more of these dynamic, productive walkable districts that are in high demand," Geoff Anderson, CEO of Smart Growth America, told CNBC. Anderson, “in conjunction with George Washington University School of Business, released a new report ranking the walkability of the nation's 30 largest metropolitan areas.”
Read the court decisionRead the full story...Reprinted courtesy of
Alaska District Court Sets Aside Rulings Under New Administration’s EO 13795
May 06, 2019 —
Anthony B. Cavender - Gravel2GavelOn March 29, the U.S. District Court for the District of Alaska issued two separate rulings that reversed and set aside energy and environmental decisions made by the current administration, which had revoked decisions made in these same matters by the prior administration. The cases are League of Conservation Voters, et al., v. Trump (concerning the development of oil and gas leases on the Outer Continental Shelf (OCS)) and Friends of Alaska National Wildlife Refuges, et al., v. Bernhardt, Acting Secretary of the U.S. Department of the Interior (which concerns a Land Exchange that would facilitate the construction of a road between two remote Alaska communities when that road would traverse parts of a designated national wilderness).
In the League of Conservation Voters matter, the District Court held that the President’s Executive Order 13795 (released on April 28, 2017), which purported to revoke President Obama’s decisions to withdraw certain OCS tracts from oil and gas exploration and development, was unlawful because it was not authorized by Section 12(a) of the Outer Continental Shelf Lands Act (OCSLA). In 2015 and 2016, President Obama issued Presidential Memorandums and an Executive Order withdrawing these particular tracts.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Sales of New U.S. Homes Rose More Than Forecast to End 2014
January 28, 2015 —
Bloomberg News(Bloomberg) -- Purchases of new homes in the U.S. jumped in December to the highest level in more than six years, a sign the industry is poised to keep expanding in 2015.
Sales increased 11.6 percent to a 481,000 annualized pace, exceeding all estimates in a Bloomberg survey of economists and the most since June 2008, figures from the Commerce Department showed Tuesday in Washington. Demand increased in three of four regions.
Gains in employment, borrowing costs close to historically low levels and easing credit may prompt more prospective buyers to enter the housing market. The improving outlook is driving up confidence among builders, and companies such as D.R. Horton Inc. and Lennar Corp. project the recovery will be sustained.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Construction Defect Lawsuit Came too Late in Minnesota
June 28, 2013 —
CDJ STAFFThe Minnesota Court of Appeals has upheld a summary judgment in a construction defect case, Lee v. Gorham. Minnesota law requires that contractors warranty that the home will be free of major construction defects during the first ten years, but claims must “be brought within two years of the discovery of the breach.” The Lees received a home inspection report in 2009 that identified a variety of defects, including “several possible structural defects.” The court noted that the report stated, “Contact your builder in writing of the findings, and discuss your options with an attorney.”
The Lees contacted the contractor, Gorham Builders. After initial silence, Gorham told the Lees that problems would “have to be ‘turned over to [the] insurance company.’” Rodney noted in his testimony that he had two choices, to either sue Gorham or hire an outside contractor. Mr. Lee had concluded that the legal costs were likely to be equal to the cost of the contractor.
In June, 2011, the Lees changed their mind about bringing a suit. Gorham sought and received a summary judgment dismissing the case on the grounds that too much time had passed since the Lees learned of the construction defect. The Lees appealed.
The appeals court upheld the summary judgment. The Lees claimed that the 2009 home inspection did not alert them of a “major construction defect,” but the court concluded that the language of the report fit within the Minnesota statutory definition of a “major construction defect.”
Nor was the appeals court convinced that at any time did Gorham provide “assurances that it would cure the defects to the home.” Within the same month as the May 2009 inspection, Gorham had made it clear that any problems were an issue for the insurance company. Thus, the appeals court concluded that the Lee’s equitable-estoppel argument was without merit.
The Lees also brought to appeal the new argument that they did not realize they were dealing with “major construction defects” until they received a subsequent home inspection in 2011. The court noted that the second report does not detail “new defects or structural issues not identified in the 2009 inspection report.” In addition to being “without merit,” the court noted that this claim was not made in the district court and so the appeals court “need not consider this issue on appeal.”
Read the court decisionRead the full story...Reprinted courtesy of
When it Comes to COVID Emergency Regulations, Have a Plan
December 07, 2020 —
Christopher G. Hill - Construction Law MusingsAs I hope readers of this construction corner of the “blogosphere” know, Virginia adopted emergency COVID workplace regulations effective July 27, 2020, and with enforcement beginning at the end of September. Among the various items found in these regulations are general requirements for all employers, including among others, the requirement to self determine the employer’s risk level and disinfecting requirements. The regulations also have some requirements that seem specially directed toward construction industry employers. These include among them engineering controls and various requirements relating to communications with subcontractors. For a good overview of these requirements, see this great post at the Virginia Bar Association’s construction law blog.
One item that is not included in the emergency regulations is a statement that following the regulations immunizes an employer from COVID infection-related lawsuits. For this reason, among others, all construction (and other industry) employers should have a COVID plan that meets the requirements of these regulations at whatever “hazard level” that employer meets. These plans should be written and distributed to all employees and include protocols for workplace/job site screening and what to do if there is a need for contact tracing. I also highly recommend that any plan be created with the help of a good Virginia workplace safety consultant well versed in the COVID regulations.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Senior Housing Surplus Seen as Boomers Spur Building Boom
May 19, 2014 —
Brian Louis – BloombergReal estate developers are betting big on U.S. housing for the elderly, preparing for a surge in demand as the population of senior citizens almost doubles in the next 35 years. They may be building too fast.
A jump in supply is forecast to cut growth in senior-housing net operating income to 1.8 percent in 2015 and 1.4 percent in 2016 from 3.3 percent this year, according to Green Street Advisors Inc. The increase may hurt health-care real estate investment trusts and companies including Brookdale Senior Living Inc. (BKD), which is buying competitor Emeritus Corp. (ESC) for about $1.4 billion to become the biggest owner of senior properties, the research firm said.
“Increased supply is always worrisome in any type of commercial real estate,” said Jim Sullivan, a managing director at Newport Beach, California-based Green Street. “In senior housing, new construction has ramped up considerably over the last two years.”
Read the court decisionRead the full story...Reprinted courtesy of
Brian Louis, BloombergMr. Louis may be contacted at
blouis1@bloomberg.net