Last, but NOT Least: Why You Should Take a Closer Look at Your Next Indemnification Clause
March 09, 2020 —
Aimee Cook Oleson - Construction & Infrastructure Law BlogIndemnification clauses appear in nearly every agreement, but they are often overlooked as mere boilerplate provisions after the parties have painstakingly negotiated all of the other terms. It is not uncommon for parties to simply re-use the indemnity language from a prior agreement without considering whether it is a good fit for their current project. This can be a big mistake that may lead to ambiguities and uncertainties if a dispute arises down the road. A standard or canned indemnification clause might work to undo all of the effort that has gone into properly allocating risk. These clauses often contain language such as “notwithstanding anything to the contrary herein,” or the like, which can alter and override other provisions in the agreement.
Indemnification clauses are arguably the most important part of an agreement when an accident or dispute arises on a project. Therefore, they deserve an extra look before finalizing an agreement. Here are a few issues to keep in mind when reviewing your next indemnification clause:
- Have you included all necessary parties?
- Any party who could face potential liability should be included as an indemnified party. This often includes entities and persons related to the contracting parties, not just the parties themselves.
- A well drafted indemnity clause will ensure that all parties are liable for the result of their own work and negligence and that of any party that they have hired to work on a project. This includes employees, agents, subcontractors, or any other similar party.
Read the court decisionRead the full story...Reprinted courtesy of
Aimee Cook Oleson, Sheppard MullinMs. Oleson may be contacted at
AOleson@sheppardmullin.com
Sierra Pacific v. Bradbury Goes Unchallenged: Colorado’s Six-Year Statute of Repose Begins When a Subcontractor’s Scope of Work Ends
November 03, 2016 —
Luke Mecklenburg – Snell & Wilmer Real Estate Litigation BlogIt’s official: the October 20, 2016 deadline to petition for certiorari to the Colorado Court of Appeals on its decision in Sierra Pacific Industries, Inc. v. Bradbury has passed, so it appears that decision will stand.
In Sierra Pacific, the Court of Appeals held as a matter of first impression that the statute of repose for a general contractor to sue a subcontractor begins to run when a subcontractor’s scope of work is substantially complete, regardless of the status of the overall project. Sierra Pac. Indus., Inc. v. Bradbury, 2016 COA 132, ¶ 28, ___ P.3d ___. The Court of Appeals interpreted the statute of repose in C.R.S. section 13-80-104, which requires that “all actions against any architect, contractor, builder or builder vendor, engineer, or inspector performing or furnishing the design, planning, supervision, inspection, construction, or observation of any improvement to real property” must be brought within six years of substantial completion of that improvement. C.R.S. § 13-80-104(1)(a). Recognizing that “an improvement may be [to] a discrete component of an entire project” under Shaw Construction, LLC v. United Builder Services, Inc., 296 P.3d 145 (Colo. App. 2012), the Court of Appeals determined that “a subcontractor has substantially completed its role in the improvement at issue when it finishes working on the improvement.” Sierra Pac., 2016 COA at ¶¶ 20, 28. In doing so, it rejected Sierra Pacific’s argument that the statute could be tolled under the repair doctrine “while others worked to repair [the subcontractor’s] ‘improper installation work and flawed repair work.’” Id. at ¶ 29. Because six years had undisputedly passed since the subcontractor completed its scope of work when Sierra Pacific filed suit against it, the Court of Appeals affirmed the trial court’s order granting the subcontractor’s motion for summary judgment under Section 13-80-104(1)(a).
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & Wilmer Real Estate Litigation BlogMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Colorado Senate Voted to Kill One of Three Construction Defect Bills
May 05, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Denver Business Journal reported that the Colorado Senate Appropriations Committee voted 5-2 to kill SB 219, one of the three construction defect bills introduced by Sen. Jessie Ulibarri, D-Commerce City. SB 219 “would have given the divisions of housing, insurance and law a combined $150,000 to collect data that would shine light on the reasons for the current shortage of owner-occupied affordable housing.”
However, the two other construction defect related bills are still alive. SB 216 “would offer financial incentives for building condos worth less than $500,000 and SB 220, would make it more difficult for condo owners to file a class-action lawsuit regarding alleged defects.”
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Tower Construction Defects Update: Who’s To Blame?
August 17, 2011 —
CDJ STAFFReporting on the site VegasInc.com, Liz Benton notes that “nobody wants to take the fall for what happened at Harmon.” Work on the Harmon hotel building in Las Vegas’s CityCenter stopped in 2008 after 26 of the planned 49 stories were completed. Lorence Slutzky, a construction law professor at John Marshall Law School and a partner with the Chicago firm Robbins Schwartz Nicholas Lifton & Taylor told Benton that while inspectors and others are complicit, “the real responsibility rests with Perini, which has an obligation to comply with the plan specifications.” Perini’s claim is that they were given faulty design drawings. MGM disputes this.
Perini has offered to repair the building defects, however MGM has released a statement that they have “zero confidence or trust that Perini can and will properly fix a building it has so badly constructed thus far.” One MGM spokesperson likened these requests from Perini to “the director of ‘Ishar’ demanding a sequel.” “Ishtar,’ cost Columbia Pictures $55 million dollars and earned only $4.2 million in its initial run. Perini claims that MGM halted work because of the economy.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Employees in Construction Industry Entitled to Compensation for Time Spent Complying with Employer-Mandated Security Protocols
August 19, 2024 —
Garret Murai - California Construction Law BlogWage and hour laws dictating how employers must compensate their employees for time worked can, given the innumerable ways that employees perform their jobs, raise a number of questions. The next case, Huerta v. CSI Electrical Contractors, 15 Cal.5th 908 (2024) – which I won’t spend a lot of time discussing since I think it applies in somewhat limited situations – addresses whether employees are entitled to be paid while waiting to enter and exit worksites and for meal periods when they are not allowed to exit a worksite.
The Huerta Case
The 9th Circuit Court of Appeals requested that the California Supreme Court address three questions related to whether employees should be compensated under California wage and hour laws for time spent waiting to enter and exit worksites and for meal periods when they are not allowed to exit a worksite:
- Whether employees should be paid for time spent waiting in a personal vehicle to be scanned in and out of a worksite;
- Whether employees should be paid for time spent traveling in a personal vehicle from a security gate to employee parking lots; and
- Whether employees should be paid during meal periods if they are not permitted to leave a worksite.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
EPA and the Corps of Engineers Repeal the 2015 “Waters of the United States” Rule
January 13, 2020 —
Anthony B. Cavender - Gravel2GavelThe pre-publication version of the final rule to be promulgated by EPA and the U.S. Army Corps of Engineers (ACOE) to repeal the 2015 redefinition of the Clean Water Act’s term “Waters of the United States” which is the linchpin of these agencies’ regulatory power under the CWA, was made available on September 12, 2019. The rule should be published in the Federal Register in the next few weeks, and it will be effective 60 days thereafter. Many challenges are expected to be filed in the federal courts.
The 2015 rule was very controversial, and petitions challenging the rule were filed in many federal district courts, several courts of appeal, and finally in the Supreme Court (see NAM v. Department of Defense), which held that all initial challenges must be filed in the federal district courts. The upshot of these challenges is that, at this time, the 2015 rule has been enjoined in more than half the states while the other states are bound by the 2015 rule, a situation which is frustrating for everyone.
In addition to repealing the 2015 rule, the agencies also restored the pre-2015 definition had had been in place since 1986. As a result, the pre-2015 definition of waters of the U.S. will again govern the application of the following rules: (a) the ACOE’s definition of “waters of the U.S.” at 33 CFR Section 328.3; (b) EPA’s general Oil Discharge rule at 40 CFR Section 110; (c) the SPCC rules at 40 CFR Part 112; (d) EPA’s designation of hazardous substances at 40 CFR Part 116; (e) EPA’s hazardous substance reportable quantity rule at 40 CFR Part 117; (f) the NPDES permitting rules at 40 CFR Part 122; (g) the guidelines for dredged or fill disposal sites at 40 CFR Part 230; (g) Exempt activities not requiring a CWA 404 permit (guidelines for 404 disposal sites at 40 CFR Part 232); (h) the National Contingency Plan rules at 40 CFR Part 300; (i) the designation of reportable quantities of hazardous substances at 40 CFR Part 302; and (j) EPA’s Effluent Guidelines standards at 40 CFR Part 401.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
HP Unveils Cheaper, 3-D Printing System to Spur Sales
November 05, 2014 —
Jack Clark - BloombergHewlett-Packard Co. (HPQ) unveiled a new 3-D-capable computer and speedier 3-D printer technology as it prepares to spin off its personal-computer and printer businesses into a stand-alone company.
The company today introduced Sprout, an $1,899 computer that lets people scan and manipulate 2-D and 3-D objects. It will be available early next month online and in some U.S. stores. Hewlett-Packard also said new 3-D printer technology will make the process cheaper and faster than competitors.
The Palo Alto, California-based company is betting that 3-D technology will help revitalize sales and spur growth in the printer industry. More than 2.3 million 3-D printers will ship in 2018, up from about 108000 this year, according to researcher Gartner Inc. Earlier this month, Hewlett-Packard said it would split into two companies by late 2015, with one focused on corporate hardware services and the other -- dubbed HP Inc. -- on PCs and printers.
Read the court decisionRead the full story...Reprinted courtesy of
Jack Clark, BloombergMr. Clark may be contacted at
jclark185@bloomberg.net
A Look at Trending Legislative Changes Impacting Workers' Comp
February 26, 2024 —
Rosanna Shamash - Construction ExecutiveThe tides are shifting in the construction industry when it comes to legal matters—and business owners could feel the brunt of it.
Recent legislative changes in the state of New York could signal how workers’ compensation cases move forward across the country and impact business owners in the space. Arguably, New York has historically laid the groundwork for workers’ compensation law in numerous other states. Now, we’re seeing a clear shift in favor of workers with some of the recent legislative changes. Owners, operators and executives in the construction space have increasingly found themselves facing costly claims that in years prior carried a smaller dollar value and were largely viewed as inconsequential.
So, what’s the best way for business owners in the construction industry to protect their businesses for the future? Start by gaining a basic understanding of changes in the legal landscape, by securing defense attorneys who know the construction space and by taking steps to protect your business before an incident happens.
Reprinted courtesy of