Pulte Home Corp. v. CBR Electric, Inc.
August 24, 2020 —
Michael Velladao - Lewis BrisboisIn Pulte Home Corp. v. CBR Electric, Inc., 50 Cal.App.5th 216 (June 10, 2020), the California Court of Appeal reversed the trial court’s entry of judgment in favor of six subcontractors with respect to an equitable subrogation lawsuit filed by St. Paul Mercury Insurance Company (“St. Paul”). St. Paul filed the lawsuit after defending Pulte Home Corp. (“Pulte”) against two construction defect lawsuits. The lawsuit contended that St. Paul was entitled to seek recovery of defense costs incurred on behalf of Pulte based on equitable subrogation. St. Paul relied on the indemnity clauses in each of the subcontracts, and argued that the subcontractors had breached their contracts with Pulte. As such, each subcontractor was obligated to pay an equitable share of the defense of the construction defect lawsuits relating to their work on the homes at issue in such lawsuits. The trial court ruled against St. Paul and held that the subcontractors’ failure to pay defense costs did not “cause” the homeowners’ claims, such that there was no causal connection supporting a claim for equitable subrogation. In addition, the trial court found that “equitable subrogation was an all-or-nothing claim, meaning it required a shifting of the entire amount of defense costs to the subcontractors on a joint and several basis and did not allow for an apportionment of costs among the defendant subcontractors.”
In reversing the trial court’s decision, the Court of Appeal reasoned that St. Paul stood in the shoes of Pulte and was limited to pursuing recovery from the subcontractors based on the same rights as afforded to Pulte under the subcontracts. The Court of Appeal noted that St. Paul was seeking reimbursement of defense costs from the subcontractors based on the theory that they were contractually liable for paying an equitable share of defense costs. The Court of Appeal also noted that St. Paul’s claim was not premised on the contention that the subcontractors’ failure to pay defense costs caused the homeowners’ claims. Rather, St. Paul’s claim was premised on the subcontractors’ breach of their defense duty owed to Pulte under the indemnity clauses in their subcontracts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
A Court-Side Seat: Appeals and Agency Developments at the Close of 2020
December 29, 2020 —
Anthony B. Cavender - Gravel2GavelTHE FEDERAL APPELLATE COURTS
The U.S. Court of Appeals
On November 23, 2020, the court, in a 2-to-1 vote, rejected the plaintiff’s request for an emergency injunction pending appeal in the case of Manzanita Band of Kumeyaay Nation, et al. v. Wolf. The majority held the requirement for such relief did not meet the requirements set forth in Winter v. NRDC, 555 US 7 (2008). Here, the plaintiffs allege that that the government’s construction of a border wall violates several environmental laws that were illegally waived by the Secretary of the Interior. Judge Millett dissented in part because the plaintiffs demonstrated a likelihood of success on the merits. She pointed to the argument that the authority of the Secretary—or Acting Secretary—to take these actions has been successfully challenged in several federal district courts. An expedited pleading schedule was established by the court.
The U.S. Court of Appeals for the Fourth Circuit
On November 17, 2020, in Ergon-West ,Inc. v. EPA, the court again reversed the EPA’s decision denying regulatory relief to a small refinery seeking a waiver of the renewable fuels mandate of the Clean Air Act. Ergon is a small refinery and requested relief in the basis of the economic harm that compliance would entail. In 2018, the court ruled in Ergon’s favor and remanded the case back to the agency. After relief was again denied, the court held that “Ergon has come forward with sufficient evidence undermining one aspect” of the agency’s latest decision, and the ruling was returned to EPA for additional analysis. It appears that a complicated process has become even more complicated.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Eyerly may be contacted at
te@hawaiilawyer.com
Significant Issues Test Applies to Fraudulent Claims to Determine Attorney’s Fees
January 13, 2017 —
David Adelstein - Florida Construction Legal UpdatesConstruction lienors need to appreciate on the frontend that recovering statutory attorney’s fees in a construction lien action is NOT automatic—far from it. This is because the prevailing party for purposes of attorney’s fees in a construction lien action is determined by the “significant issues test,” a subjective test with no bright line standards based on who the trial court finds prevailed on the significant issues in the case. If you want to talk about the subjective and convoluted nature of recovering attorney’s fees in a construction lien action under the significant issues test, a recent opinion by the Fourth District Court of Appeal is unfortunately another nail in the coffin.
In Newman v. Guerra, 2017 WL 33702 (Fla. 4th DCA 2017), a contractor recorded a construction lien on a residential renovation project and filed a lien foreclosure lawsuit. The homeowner countersued the contractor and asserted a fraudulent lien claim pursuant to Florida Statute s. 713.31. An evidentiary hearing was held on whether the lien was a fraudulent lien and the trial court held that the lien was fraudulent (therefore unenforceable) because it included amounts that were not lienable under the law. The remaining claims including both parties’ breach of contract claims proceeded to trial. There was no attorney’s fees provision in the contract. At the conclusion of the trial, the court found that the contractor was entitled a monetary judgment on its breach of contract claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Blackstone Said to Sell Boston Buildings for $2.1 Billion
May 21, 2014 —
Hui-yong Yu – BloombergBlackstone Group LP (BX) agreed to sell five office properties in Boston to a venture led by Toronto-based Oxford Properties Group for about $2.1 billion, according to two people with knowledge of the transaction.
The buildings total almost 3.3 million square feet (306,000 square meters) and are mostly in downtown Boston, said the people, who asked not to be named because the sale is private. The sale is Blackstone’s largest of U.S. office properties since the real estate market crash.
Oxford plans to purchase 100 High St. and 125 Summer St., and team with JPMorgan Chase & Co. (JPM)’s asset-management unit to buy three other properties: 60 State St., 225 Franklin St. and One Memorial Drive in nearby Cambridge, the people said. Blackstone also is selling its roughly half-stake in Boston’s Rowes Wharf to part-owner Morgan Stanley (MS) for about $200 million, according to one of the people.
Read the court decisionRead the full story...Reprinted courtesy of
Hui-yong Yu, BloombergHui-yong Yu may be contacted at
hyu@bloomberg.net
Dust Infiltration Due to Construction Defect Excluded from Policy
September 09, 2011 —
CDJ STAFFA summary judgment was affirmed in the case of Brown v. Farmers Group, by the California Court of Appeals. The Browns bought a new home in Oakley, California. At the time, they signed disclosure statement “acknowledging that the area around their home experienced gusty winds and would be in development for years to come, which might result in dust and airborne mold.”
The Browns found an unusual amount of dust in their home, which became worse when they ran their heating and air conditioning system. Shelia Brown was later diagnosed with chronic valley fever, which was attributed to airborne mold. The Browns contacted Farmers which investigated the house. Although the adjustor from Farmers said the Browns would be covered, Farmers denied the claim.
After the Browns moved out of the house, an inspector found that the HVAC line in the attic was disconnected, sending dust into the home. The Browns brought action against Mid-Century Insurance, which managed the policy, and Farmers. The identified the HVAC defect, window problems, and valley fever as causes, suing for breach of contact, breach of implied covenant of good faith and fair dealing, and the intentional infliction of emotional distress.
The court rejected all these claims. The policy with Farmers excluded losses due to defective construction. This ruled out the faulty HVAC system and any problems there might have been from the windows. The policy also specifically excluded losses from contamination, fungi, pathogens, and noxious substances. The court further found that the adjustor’s opinion was irrelevant to the question of what the policy actually covered. Finally, the court found no evidence of intentional infliction of emotional stress.
On review, the appeals court upheld the trial court’s conclusions and affirmed the summary judgment.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears Recognized by Best Lawyers in 2025 Best Law Firms®
December 03, 2024 —
Payne & Fears LLPPayne & Fears LLP has been named to the 2025 Best Lawyers “Best Law Firms” list. This recognition highlights firms that demonstrate professional excellence, receiving outstanding ratings from both clients and peers.
Payne & Fears has been ranked in the following practice areas:
Metropolitan Tier 1
- Orange County
- Commercial Litigation
- Employment Law – Management
- Insurance Law
- Labor Law – Management
- Litigation – Labor and Employment
- Litigation – Real Estate
Metropolitan Tier 2
Metropolitan Tier 3
- Orange County
- Litigation – Intellectual Property
Read the court decisionRead the full story...Reprinted courtesy of
Payne & Fears LLP
Class Action Certification by Association for “Matters of Common Interest”
August 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesAssociations have authority to pursue as a class, on behalf of all of their respective members, lawsuits “concerning members of common interest to the members.” Fla. R. Civ. P. 1.221. This includes, but is not limited to, the common property or the areas in which the association is responsible. But, what about matters or elements for which the association is not responsible or does not own? For example, issues or damages relative to a specific unit or owner that are prevalent throughout?
The Third District Court of Appeal addressed this question in Allied Tube and Conduit Corp. v. Latitude on the River Condominium Association, Inc., 45 Fla. L. Weekly D1518a (Fla. 3d DCA 2020) when in affirmed a class certification by a condominium association relating to the removal and replacement of the condominium building’s defective fire sprinkler system. In affirming the class certification by the condominium association, the Third District maintained:
Rule 1.221 expressly authorizes condominium associations to “institute, maintain, settle, or appeal actions or hearings in its name on behalf of all association members concerning matters of common interest to the members.” “[A]s to controversies affecting the matters of common interest . . ., the condominium association, without more, should be construed to represent the class composed of its members as a matter of law.” “[T]he common interest provision of the rule has been interpreted to permit a class action by the association for a construction defect located physically within a unit, rather than in the common elements, if the defect is prevalent throughout the building.” We, therefore, cannot say the trial court abused its discretion in finding that damages resulting from the replacement of the fire-sprinkler system throughout the building were a matter of common interest for purposes of certification at this stage of the litigation.
Allied Tube and Conduit Corp, supra (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Quick Note: Not In Contract With The Owner? Serve A Notice To Owner.
August 13, 2019 —
David Adelstein - Florida Construction Legal UpdatesA subcontractor or supplier not in direct contract with an owner must serve a Notice to Owner within 45 days of initial furnishing to preserve construction lien rights. Of course, the notice of commencement should be reviewed to determine whether the subcontractor or supplier has construction lien or payment bond rights so that it knows how to best proceed in the event of nonpayment. Serving a Notice to Owner should be done as a matter of course — a standard business operation; no exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com