Construction Litigation Roundup: “Wrap Music to an Insurer’s Ears?”
February 05, 2024 —
Daniel Lund III - LexologyThe general contractor on a New Orleans condominium construction project obtained a Contractor Controlled Insurance Program/CCIP policy or "Wrap-Up" policy for the job.
An accident occurred on the job when a construction elevator/hoist fell, injuring several workers. The elevator/hoist was provided by a subcontractor, pursuant to a rental agreement and related subcontract with the general contractor. Contained within the subcontract was a provision which states that the general contractor "has arranged for the Project to be insured under a controlled insurance program (the "CCIP" or "WrapUp"),” and that the CCIP shall provide "commercial general liability insurance and excess liability insurance, in connection with the performance of the Work at the Project site."
A third-party administrator for the wrap-up policy had been in communication with the subcontractor prior to the commencement of the work, “specifically advising that insurance coverage was not automatic” and providing the subcontractor with an enrollment form for the CCIP. Ultimately, the subcontractor “declined to comply with the request,” stating that the subcontractor would "not participate in paying any wrap insurance premiums" – because the subcontractor had its own insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
OSHA Begins Enforcement of its Respirable Crystalline Silica in Construction Standard. Try Saying That Five Times Real Fast
November 02, 2017 —
Garret Murai - California Construction Law BlogOn October 23, 2017, the U.S. Occupational Safety and Health Administration (OSHA) began enforcement of its Respirable Crystalline Silica in Construction Standard (Construction Silica Standard). OSHA enforcement of its Construction Silica Standard actually began on September 23, 2017, but for a period of 30 days, OSHA offered compliance assistance in lieu of enforcement for employers who were making good faith efforts to comply with the Construction Silica Standard.
California’s Occupational Safety and Health Administration (Cal/OSHA) has a nearly identical construction silica standard that requires employers to limit worker exposure to respirable crystalline silica above 25 micrograms per cubic meter of air (25 μg/m3) as an 8-hour time-weighted average (TWA) under any foreseeable condition.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Packard Condominiums Settled with Kosene & Kosene Residential
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFResidents of the Packard Condominiums in Indianapolis, Indiana “have settled a two-year-old lawsuit with developer Kosene & Kosene Residential,” according to the Indianapolis Business Journal. The Homeowners association stated that “the agreement would lead to repayment of a construction loan and avoidance of a special assessment on residents.”
The association claimed to have spent “$3 million on ‘renovation and remediation’ of subpar construction of the condo building,” reported the Indianapolis Business Journal.
The article also declared that at least 25 subcontractors participated in the mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Building Stagnant in Las Cruces Region
November 20, 2013 —
CDJ STAFFThere was an increase in the number of building permits issued in Las Cruces, New Mexico through the first ten months of 2013, but the 2,162 permits represent only a minimal increase over last year’s 2,158 permits. To make matters worse for building suppliers and workers, builders can “pull all the permits for a subdivision at one time but might not start some of those for six months,” said Lee Rawson, the owner of Rawson Builders Supply.
For a comparison, during the building boom of 2006, Las Cruces issued 3,529 building permits. The values are down too. Although fewer permits were issued in 2012, their valuation was $147 million, while the marginally larger number in 2013 is worth only $128 million.
As a result, the area is losing skilled labor. After 25 consecutive months of declining construction, workers are leaving the construction industry. Mr. Rawson noted that “you can’t just go find that skilled labor, it doesn’t exist.”
Read the court decisionRead the full story...Reprinted courtesy of
California Contractor Spills Coffee on Himself by Failing to Stay Mechanics Lien Action While Pursuing Arbitration
August 14, 2018 —
Garret Murai - California Construction Law BlogIt bugs the Mrs. that I have a habit of reading the directions. “Just plug the darn thing in!” said the Mrs. when we got a new coffee maker to replace our old one which we’ve had since I think before we were married (Life Lesson No. 347: Get a coffee maker you really, really like because they last forever). “But . . . the directions?,” I said.
By the time I had finished reading the instruction manual I could smell the coffee brewing in the kitchen. Granted, the Mrs. is more practical than I am in many ways (e.g., “You know, you didn’t need to buy 10 cans of corn to get the 10 for $10 discount. I guess you’re going to be eating a lot of corn”). But still. What might have happened if there was a serious coffee mishap?
And worrier as I may be mishaps can happen if you don’t read the directions. James Zenovic didn’t read the directions, and here’s his story . . .
Von Becelaere Ventures, LLC v. Zenovic
In Von Becelaere Ventures, LLC v. Zenovic, Case No. D072620 (June 6, 2018), James Zeonovic doing business as James Zeonovic Construction entered into a construction contract to build a single-family house for Von Becelaere Ventures, LLC in Laguna Beach, California. The construction contract included an arbitration provision that stated:
If any dispute arises concerning this Contract or the interpretation thereof, of concerning construction of the Improvements, or the Limited Warranty, customer service, defects, damages, or obligations therewith (a “Construction Dispute”), such Construction Dispute will be settled by binding arbitration. Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Court Agrees to Stay Coverage Matter While Underlying State Action is Pending
October 29, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court granted the insured's motion to stay the coverage action while the construction defect case was pending in state court. Auto Owners Ins. Co. v. Essex Homes Southeast, Inc., 2014 U.S. Dist. LEXIS 133120 (D. S.C., Sept. 23, 2014).
The homeowners sued Essex Homes in state court for construction defects in a home built and sold to them by Essex Homes. The suit sought damages for property damage based on negligence, breach of implied warranty, and breach of express warranties arising out of the alleged construction defects. The complaint alleged that a water leak in the house caused water damage and resulted in mold growth that was not discovered for several years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
It’s Getting Harder and Harder to be a Concrete Supplier in California
December 04, 2018 —
Garret Murai - California Construction Law BlogIn 2015, the California state legislature passed AB 219, which amended the state’s prevailing wage law to add Labor Code section 1720.9, which requires the payment of prevailing wages to “ready-mixed concrete” drivers on state and local public works projects.
Ready-mixed concrete suppliers filed suit in Allied Concrete and Supply Co. v. Baker (September 20, 2018) U.S. Court of Appeals for the Ninth Circuit, challenging the law on the ground that, because AB 219 singled out ready-mixed concrete drivers but not other drivers of materials on state and local public works projects, the law violated the Equal Protection Clause of the U.S. Constitution.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
M&A Representation and Warranty Insurance Considerations in the Wake of the Coronavirus Pandemic
April 06, 2020 —
Lori Smith & Patrick Devine - White and Williams Taking Care of Business BlogIncreasingly, M&A transactions are using representation and warranty insurance (RWI) to bridge the gap between a buyer’s desire for adequate recourse to recover damages arising out of breach of representations in the purchase agreement and a seller’s desire to minimize post-closing risk and holdbacks or purchase price escrows traditionally used as the means to satisfy such obligations. When it works, RWI provides a significant benefit to both parties: it mitigates the buyer’s risk in the event that the seller’s representations and warranties prove untrue, and it permits the seller to reduce the portion of the purchase price that it would otherwise have to leave in escrow to cover future claims for breach of those representations and warranties. However, as the coronavirus pandemic ravages the global economy, insurers are now expressly adding COVID-19 exclusions to their RWI policies. If RWI insurers decline coverage for these losses, the allocation of risk in the representations and warranties (and related indemnity provisions) will be more critical than the parties contemplated when they negotiated the transaction documents.
Unlike in the case of a natural disaster, insurers cannot quantify the economic fallout that may result from the coronavirus pandemic. This uncertainty breeds systemic concern about the number of insurance claims that covered parties of all varieties will bring, which in turn creates an industry-wide reluctance to cover the claims. Based on discussions with market participants, we understand that, at the present time, 70% to 80% of RWI insurers are broadly excluding losses resulting from COVID-19 and similar viruses, epidemics, and pandemics (including government actions in response thereto), 5% to 10% are narrowly excluding specific coronavirus-related losses that are more likely to be implicated in a particular transaction (e.g., losses caused by business interruption), and 10% to 15% may be willing to narrow their exclusions upon completion of the underwriting process, depending on their comfort level after conducting rigorous and heightened diligence. Insurers’ concerns are wide-ranging, but the representations and warranties causing the greatest distress appear to be those regarding customer retention, supply chain matters, undisclosed liabilities, and the absence of changes between the date of the seller’s most recent financial statements and the transaction closing date.
Reprinted courtesy of
Lori Smith, White and Williams and
Patrick Devine, White and Williams
Ms. Smith may be contacted at smithl@whiteandwilliams.com
Mr. Devine may be contacted at devinep@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of