Underpowered AC Not a Construction Defect
November 07, 2012 —
CDJ STAFFAfter buying a home in Louisiana, Mike Gines determined that the home’s air conditioning unit was insufficient to maintain an appropriate temperature. He contacted the home builder, D.R. Horton, Inc., which worked with the air conditioning installer, Reliant Heating & Air Conditioning, in order to repair the system. When the problems persisted, Gines filed a class action petition against Horton and Reliant in state court. Horton and Reliant moved the case to the federal courts, whereupon Gines asserted the defendants were in violation of the Louisiana New Home Warranty Act (NHWA). Horton stated that the claim under the NHWA was invalid, because Gines had not alleged actual physical damage to his home.
The district court granted Horton’s motion to dismiss. Gines sought a reversal from the Fifth Circuit Court of Appeals and sought to have two questions of state law addressed by the Louisiana Supreme Court.
The district court ruled that the NHWA was the “sole remedy under Louisiana law for a purchaser of a new home with construction defects. Gines argued that court erred in this, but also conceded that this was the conclusion of the Louisiana Supreme Court.
Further, Gines argued that a provision in the NHWA that allows the inclusion of construction defects that do not cause damage was satisfied by paragraph 6 of the contract. The court noted that Gines did not attach a copy of the contract to either the original or amended complaint, and so the court does not need to address these claims. However, the court cautioned that if a copy had been included, they still would have rejected the claim, as “the cited language does not indicate a waiver of the physical damage requirement.” They also note that “paragraph 13 of the contract shows that Gines was aware to the absence of any such waiver in the contract.”
The court concludes that “the moral of this story is that in order to avoid the harsh result that has obtained here, the buyer of a newly constructed home in Louisiana should seek to obtain in the contract of sale an express waiver of the actual damage requirement of the NHWA.” The appeals court affirmed the decision of the circuit court and denied the application to certify questions to the Louisiana Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Impact of Lis Pendens on Unrecorded Interests / Liens
September 15, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a previous article, I discussed the importance of recording a lis pendens in a construction lien foreclosure action.
There is another noteworthy point relating to the impact of lis pendens that can provide quite a bit of consternation.
Florida Statute 48.23(1)(d) provides:
Except for the interest of persons in possession or easements of use, the recording of such notice of lis pendens, provided that during the pendency of the proceeding it has not expired pursuant to subsection (2) or been withdrawn or discharged, constitutes a bar to the enforcement against the property described in the notice of all interests and liens, including, but not limited to, federal tax liens and levies, unrecorded at the time of recording the notice unless the holder of any such unrecorded interest or lien intervenes in such proceedings within 30 days after the recording of the notice. If the holder of any such unrecorded interest or lien does not intervene in the proceedings and if such proceedings are prosecuted to a judicial sale of the property described in the notice, the property shall be forever discharged from all such unrecorded interests and liens. If the notice of lis pendens expires or is withdrawn or discharged, the expiration, withdrawal, or discharge of the notice does not affect the validity of any unrecorded interest or lien.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Engineering Report Finds More Investigation Needed of Balconies at New Jersey Condo
March 20, 2023 —
Engineering News-RecordPress of Atlantic City
SEA ISLE CITY - An engineering report on the Spinnaker Condominiums' South Tower found that balconies directly beneath the one that collapsed last month, killing a worker, need further investigation before they are deemed safe for use.
Reprinted courtesy of
Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insured's Experts Excluded, But Insurer's Motion for Summary Judgment Denied
October 26, 2020 —
Tred R. Eyerly - Insurance Law HawaiiDespite barring the insured's expert witnesses from testifying as to the cause of the loss, lay witnesses were still available, making the district court's award of summary judgment to the insurer improper. Greater Hall Temple Church of God v. Southern Mut. Church Ins. Co., 2020 U.S. App. LEXIS 21934 (11th Cir. July 15, 2020).
Hurricane Matthew damaged the Greater Hall Temple Church of God's (Church) roof. Leaks occurred, causing water damage to the Church's interior. A claim was submitted to Southern Mutual. The policy did not cover loss caused by water. Nor did it cover loss to the interior of buildings unless the rain entered through openings made by a specified peril. An independent adjuster found that the damage was caused not by wind, but by pre-exisiting structural issues. Southern Mutual denied the claim.
The Church filed suit. Southern Mutual moved for summary judgment and also moved to strike three of the Church's expert witnesses. The district court agreed that none of the witnesses could qualify as experts. Two of the witnesses did not have the requisite experience nor had they used a sufficiently reliable methodology formulating their opinions. A third expert was barred because his expert opinion had not been timely disclosed. Thereafter, Southern Mutual's motion for summary judgment was granted because the Church had not provided admissible evidence that damage to the Church's roof was caused by Hurricane Matthew.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Boston Developer Sues Contractor Alleging Delays That Cost Millions
November 01, 2021 —
James Leggate - Engineering News-RecordA Miami developer is suing the general contractor it hired to build a 22-story mixed-use tower in Boston’s trendy Seaport District, alleging construction delays cost it $4.9 million in lost revenue.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insurer Beware: Failure to Defend Ends with Hefty Verdict
June 01, 2011 —
Douglas Reiser, Builders Council BlogServed with a lawsuit that you turned over to your insurer? Insurer refusing to defend you? Well, find some hope in this news. Washington’s IFCA has the claws to ensure that insurers perform their duties.
Contractors heavily rely on the defense provisions of their Commercial General Liability (CGL) policies. In construction, a legal dispute can easily rear its head when you least expect it. Luckily, Washington registered contractors are required to maintain CGL insurance. That insurance often provides contractors with adequate legal defense in the event that they are sued.
But, what if your insurer turns down the defense request? They might be staring at massive damages. A current Reiser Legal client, Australia Unlimited, Inc., recently won a large verdict against Hartford Insurance, after the insurer unreasonably denied their claim. The firm who represented Australia Unlimited Inc. in that case, Hackett Beecher and Hart, were successful in procuring a $5.43 Million verdict
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Fluor Agrees to $14.5M Fixed-Price Project Cost Pact with SEC
September 25, 2023 —
Debra K. Rubin - Engineering News-RecordFluor Corp. has agreed to pay $14.5 million to resolve a U.S. Securities and Exchange Commission investigation for alleged “improper accounting” and "overly optimistic" cost and timing estimates in bidding two legacy fixed-price projects that forced the company to restate its 2020 financial results, the agency said on Sept. 6.
Reprinted courtesy of
Debra K. Rubin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of