Massachusetts Clarifies When the Statute of Repose is Triggered For a Multi-Phase or Multi-Building Project
December 07, 2020 —
Jeffrey J. Vita & Anna M. Perry - Saxe Doernberger & Vita, P.C.Lennar Hingham Holdings, LLC (“Lennar”) built a twenty-eight-building, 150-unit condominium project containing twenty-four discrete phases over a seven-year span. The condominium association subsequently brought an action against Lennar and others alleging design and construction defects to four main components of the common elements: “decks and columns,” “roofing/flashing,” “exterior walls/flashing/building envelope,” and “irrigation system.” In response, the defendants argued that the plaintiff’s claims with respect to six of the twenty- eight buildings were barred by Massachusetts’s six-year statute of repose, G. L. c. 206 § 2B.
The United States District Court for the District of Massachusetts previously held that all twenty-eight of the condominium’s buildings should be treated as a single improvement for purposes of application of the statute of repose. Subsequently, the court certified the following question to the Massachusetts Supreme Judicial Court: Where the factual record supports the conclusion that a builder or developer was engaged in the continuous construction of a single condominium development comprising multiple buildings or phases, when does the six-year period for an action of tort relating to the construction of the condominium’s common or limited common elements start running?
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Anna M. Perry, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Ms. Perry may be contacted at APerry@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Carbon Monoxide Injuries Caused by One Occurrence
April 01, 2014 —
Tred R. Eyerly – Insurance Law HawaiiInjuries from carbon monoxide poisoning to two families living in the insured's apartment complex arose from a single occurrence. Kosnoski v. Rogers, No. 13-0494, Memorandum and Decision (W. Va. Feb. 18, 2014).
The families lived in two apartments in the same complex owed by Marc Rogers. Members of the two families suffered serious injuries from carbon monoxide poisoning and one family member died. A gas boiler furnace in the basement of the apartment complex created the carbon monoxide.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
“Freelance Isn’t Free” New Regulations Adopted in New York City Requiring Written Contracts with Independent Contractors
June 15, 2017 —
Kevin J. O'Connor - Peckar & Abramson. P.C.Attacks on employers for alleged misclassification of workers—particularly independent contractors—are continuing unabated, and the risk of liability for employers operating in New York City just increased. New York City has just adopted sweeping regulations requiring written contracts with certain freelancers and independent contractors. Anyone doing business in that jurisdiction should take notice and take action to comply with the law.
New York City’s “Freelance Isn’t Free Act,” N.Y.C. Administrative Code §§ 20-927 et seq. (“FIFA”) went into effect on May 15, 2017. This new law substantially regulates the relationship between a business and an independent contractor or “freelancer” working in New York City.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. O'Connor, Peckar & Abramson. P.C.Mr. O'Connor may be contacted at
koconnor@pecklaw.com
The Insurance Coverage Debate on Construction Defects Continues
February 05, 2015 —
Craig Martin – Construction Contractor AdvisorNew Hampshire is the first court of 2015 to weigh in on construction defect coverage issues. The case, Cogswell Farm Condominium Association v. Tower Group, involved a typical situation. Lemery Building Company was hired to build 24 residential condominium units. After construction, the condominium association sued the builder asserting that the weather barrier, including the water/ice shield, flashing, siding, and vapor barrier, was defectively constructed and resulted in damage to the units due to water leaks. The condominium association also sued Lemery’s insurer for a determination as to whether the builder’s Commercial General Liability (CGL) insurer had to provide coverage for the claim.
The trial court ruled against the condominium association, finding that the “your work” exclusion applied. The exclusion in the builder’s CGL policy provided that there was no coverage for property damage to “[t]hat particular part of any property that must be restored, repaired or replaced because ‘your work’ was incorrectly performed on it.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
PSA: Pay If Paid Ban Goes into Effect on January 1, 2023
December 05, 2022 —
Christopher G. Hill - Construction Law MusingsI have
written a couple of times here at Musings regarding the new pay-if-paid legislation passed by the General Assembly last session. While the statute has some inconsistencies and a working group has made
some recommendations, the legislation as passed will go into effect on January 1, 2023, without any changes (at least until next session). As always, such action by our legislature here in Virginia will create work for construction attorneys assisting their clients to amend contracts to meet the new rules.
Essentially (and with minor inconsistencies between public and private contracts), the bill requires that any construction contract entered into after January 1, 2023 have the following provisions:
- On public projects: A payment clause that obligates a contractor on a construction contract to be liable for the entire amount owed to any subcontractor with which it contracts. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor’s noncompliance with the terms of the contract. However, in the event that the contractor withholds all or a part of the amount promised to the subcontractor under the contract, the contractor shall notify the subcontractor, in writing, of his intention to withhold all or a part of the subcontractor’s payment with the reason for nonpayment.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Another Municipality Takes Action to Address the Lack of Condominiums Being Built in its Jurisdiction
March 12, 2015 —
Heather M. Anderson – Higgins, Hopkins, McLain & Roswell, LLCWhether you are in the market to downsize or are looking to be a first time home buyer, you have likely noticed that your housing options in Colorado have become extremely limited over the course of the last several years. If you are a contractor and have worked on multi-family projects in the recent past, you know why the housing options are limited in the State of Colorado. In the past two years, there have been studies commissioned and articles published in local periodicals investigating the extreme slowdown seen in the construction of owner-occupied multi-family housing, namely condominiums and townhomes. Those of us involved in and with the construction industry are intimately familiar with the lengthy, complicated, and incredibly expensive construction defect litigation that has plagued multi-family construction in the State of Colorado and brought it to a virtual halt.
And now, local municipalities and elected officials are starting to take notice. Most recently, the City of Lone Tree passed Ordinance No. 15-01, to become effective on April 1, 2015. According to the City of Lone Tree, Ordinance No. 15-01 is “aimed at encouraging the development of owner-occupied, multi-family residential projects through the adoption of regulations designed to balance the risk and exposure to builders and developers of such projects, while still protecting homeowners from legitimate construction defect claims.”
Read the court decisionRead the full story...Reprinted courtesy of
Heather M. Anderson, Higgins, Hopkins, McLain & Roswell, LLCMs. Anderson may be contacted at
Anderson@hhmrlaw.com
Heads I Win, Tails You Lose. Court Finds Indemnity Provision Went Too Far
May 25, 2020 —
Garret Murai - California Construction Law BlogWe all love David and Goliath stories. The underdog winning against the far stronger (and dastardly) opponent. Think Rocky Balboa versus Ivan Drago, the Star Wars Rebellion versus the Galatic Empire, Indiana Jones versus a good chunk of the Third Reich. And now, we have Margaret Williams.
The Story of Margaret Williams and her LLC
The story, told in Long Beach Unified School District v. Margaret Williams, LLC, Case No. B290069 (December 9, 2019), is about Margaret Williams. Ms. Williams (we’ll just call her “Margaret” going forward because it just sounds better when telling a story) worked for nearly ten years full-time for the Long Beach Unified School District, toiling day in and day out doing construction management and environmental compliance work, including work involving the clean up of material at a school construction site contaminated with arsenic.
Although she worked full-time for the District for nearly ten years, she wasn’t an employee. Rather, she was a contractor. And, on top of it all, as a condition of working for the District, the District required that she form a company in order to contract with the District. According to Margaret, “In order to work with the District, I was directed . . . to form a corporation or partnership. This was the only way I could work for the District: I could not enter into a contract with the District as an individual.” So, in 2006, she formed a company, simply called Margaret Williams, LLC.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Federal Court Opinion Has Huge Impact on the Construction Industry
July 06, 2020 —
Wally Zimolong - Supplemental ConditionsThe United States District Court for the Eastern District of Pennsylvania in Philadelphia recently issued an opinion that should get the attention of any contractor or subcontractor performing work on a federal funded construction project. In U.S. ex rel IBEW Local 98 v. The Fairfield Company, the federal court held that a contractor on a SEPTA project could be held liable under the False Claims Act for failing to pay its workers under the Davis Bacon Act. The court found that liability was appropriate under the FCA even through the contractor did not knowingly violate the Davis Bacon Act. The court awarded the plaintiff over $1,000,000 in damages and an additional over $1,000,000 in attorneys fees.
An Extremely Brief Primer on the FCA
A full discussion of the FCA is beyond the realm of this blog post and you could write a book on FCA cases. But in a nutshell, the FCA prohibits a contractor from knowingly submitting a claim for payment to the federal government (or an entity receiving funding from the federal government, like SEPTA) that is false. Importantly, knowingly does not equal actual knowledge of the falsity of the claim. Rather, “reckless disregard of the truth or falsity” of the submission is sufficient. As explained below, this standard played an important role in the court’s decision and should give contractors performing work on federally funded projects pause.
Read the court decisionRead the full story...Reprinted courtesy of