TxDOT, Flatiron/Dragados Mostly Resolve Bridge Design Dispute
March 13, 2023 —
James Leggate - Engineering News-RecordThe Texas Dept. of Transportation and contractor Flatiron/Dragados LLC have “completely satisfied”
four of the five main design safety concerns the state agency raised over the under-construction new Harbor Bridge in Corpus Christi, officials say.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Avoiding Disaster Due to Improper Licensing
February 18, 2019 —
Candace Matson - Construction & Infrastructure Law BlogIT’S NOT ENOUGH FOR A CONTRACTOR TO BE LICENSED . . . it must be properly licensed.
We are reminded of this by the recent case of JMS Air Conditioning and Appliance Service, Inc. v. Santa Monica Community College District, Bernards Bros., Inc., 30 Cal. App. 5th 945 (2018). In that case, JMS entered into an $8.2M subcontract with Bernards to install an HVAC system in a new facility being built for the District. JMS held a C-20 warm-air heating, ventilating and air-conditioning license. A year into the project, Bernards sought permission from the District to substitute another subcontractor for JMS (as required under Public Contract Code Section 4107 for listed subcontractors on public works of improvement). Among other things, Bernards contended that JMS was not properly licensed to perform that portion of the work which consisted of hydronic plumbing and hydronic boiler work. JMS countered that this work was an integral part of installing an HVAC system, and relied on Business & Profession Code Section 7059, which permits work that is “incidental and supplemental to the performance of the work for which the specialty contractor is licensed,” and a California State Licensing Board regulation which defines “incidental and supplemental” as meaning “essential to accomplish the work in which the contractor is classified.” (Cal. Code Regs., tit. 16, §831.)
Read the court decisionRead the full story...Reprinted courtesy of
Candace Matson, Sheppard MullinMs. Matson may be contacted at
cmatson@sheppardmullin.com
Lease-Leaseback Battle Continues as First District Court of Appeals Sides with Contractor and School District
August 17, 2017 —
Garret Murai - California Construction Law BlogEarlier, we wrote about Davis v. Fresno United School District (2015) 237 Cal.App.4th 261, a Fifth District California Court of Appeals decision that sent shock waves through the school construction industry and raised questions regarding the use of California’s lease-leaseback method of project delivery (Education Code sections 17400 et seq.).
California’s lease-leaseback method of project delivery provides an alternative project delivery method for public school districts than the usual design-bid-build method of project delivery. Under the lease-leaseback method of project delivery, a school district leases its property to a developer, who in turn builds a school facility on the property and leases it back to the school district. One of the benefits of the lease-leaseback method of project delivery is that school districts do not need to come up with construction funds to build school facilities since they pay for the construction over time through their lease payments to the developer. Critics, however, argue that because lease-leaseback projects do not need to be competitively bid, they are ripe for cronyism between developers and school districts.
In Davis, a taxpayer successfully brought suit against the Fresno Unified School District challenging the propriety of a lease-leaseback project because the entirety of the District’s “lease payments” occurred while the project was being constructed and thus, successfully argued the taxpayer, there was no “true” lease of a facility since it was under construction.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Beyond the Flow-Down Clause: Subcontract Provisions That Can Expose General Contractors to Increased Liability and Inconsistent Outcomes
December 10, 2024 —
Phillip L. Parham III - ConsensusDocsFlow-down clauses in construction subcontracts—blanket clauses providing that some or all of the terms and conditions in the prime contract between the general contractor and the property owner apply equally between the subcontractor and general contractor—are an important component to managing risk for a general contractor and reducing the likelihood of disputes with either/both the owner and subcontractor. Put simply, flow-down provisions can provide continuity between the general contractor’s obligations to the owner and the subcontractor’s obligations to the general contractor. Properly drafted, flow-down clauses reduce the general contractor’s risk by ensuring that the subcontractor is legally bound to meet the owner’s objectives for the project in the same way as the general contractor. But relying on blanket flow-down clauses, alone, to protect the general contractor is like a soldier going into battle with nothing but a helmet, leaving significant other areas exposed and unprotected. In other words, a general contractor should look beyond just a singular, blanket flow down of terms to ensure its bases are properly covered.
Accordingly, this article goes beyond the blanket flow-down clause and highlights several key subcontract provisions where inconsistent obligations among the subcontractor, general contractor, and owner expose the general contractor to increased liability and inconsistent outcomes. Specifically, this article will examine disputes resolution clauses, liquidating provisions, notice provisions, and termination provisions. However, this article will not provide a deep examination of these clauses, nor does it highlight every potentially relevant clause. Rather, it focuses on these select clauses to highlight important issues associated with flow-down provisions.
Read the court decisionRead the full story...Reprinted courtesy of
Phillip L. Parham III, Jones Walker LLPMr. Parham may be contacted at
pparham@joneswalker.com
Strict Rules for Home Remodel Contracts in California
June 06, 2018 —
Daniel F. McLennon - Smith CurrieHome remodeling in California is governed by strict contracting laws intended to protect consumers. The Contractors State Licensing Board, (“CSLB”) is particularly concerned about contractors working without permits, contractors taking payment in excess of the value of the work complete–including deposits in excess of $1,000–and contractors refusing to complete projects. They are also concerned about contractors who fail to comply with the Home Improvement Contract (“HIC”) laws. At a minimum, it takes six pages of contract language for an HIC to comply with California law. Most contractors do not get it right, leaving themselves exposed to license discipline, misdemeanor criminal prosecution, and void contracts. The stakes are high, and contractors are advised to learn and comply with the HIC laws.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel F. McLennon, Smith CurrieMr. McLennon may be contacted at
dfmclennon@smithcurrie.com
Lightstone Committing $2 Billion to Hotel Projects
February 26, 2015 —
Nadja Brandt – Bloomberg(Bloomberg) -- David Lichtenstein, whose real estate company owned Extended Stay Hotels when the chain went bankrupt, is committing $2 billion to developing and investing in lodging properties.
Lightstone Group is choosing “top-branded” select-service properties, those with limited amenities, in proven U.S. markets for its projects, Lichtenstein said in an interview. As part of the strategy, Lightstone has teamed up with Marriott International Inc. to build five Moxy hotels in New York -- four in Manhattan and one in Brooklyn. The “micro” lodgings, with high-tech features and smaller-than-average rooms, are geared toward younger travelers.
Read the court decisionRead the full story...Reprinted courtesy of
Nadja Brandt, BloombergMs. Brandt may be contacted at
nbrandt@bloomberg.net
Suit Limitation Provision Upheld
March 04, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's one year suit limitation provision was upheld, depriving insureds of benefits under the policy. Oswald v. South Central Mut. Ins. Co., 2018 Minn. App. Unpub. LEXIS 1077 (Dec. 24, 2018).
The Oswalds' hog barn burned down on June 21, 2016. Arson was a possible cause.
The Oswalds were insured under a combination policy issued by North Star Mutual Insurance Company and South Central Mutual Insurance Company. Central provided coverage for basic perils, broad perils, and limited perils, which included fire losses. The Central policy required property claims to be brought within one year after the loss. By endorsement, the North Star policy required suits be brought within two years after the loss. Presumably, the claims was denied, although the decision does not state this.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Arguing Cardinal Change is Different than Proving Cardinal Change
April 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe cardinal change doctrine has become a popular doctrine for a contractor to argue under but remains an extremely difficult doctrine to support and prove. Arguing cardinal change is one thing. Proving cardinal change is entirely different. As shown below, this is a doctrine with its origins under federal government contract law with arguments extending outside of the federal government contract arena. For this reason, the cases referenced below are not federal government contract law cases, but are cases where the cardinal change doctrine has been argued (even though these cases cite to federal government contract law cases).
A party argues cardinal change to demonstrate that the other party (generally, the owner) materially breached the contract based on the cardinal change. In reality, a party argues cardinal change because they have cost overruns they are looking to recover and this doctrine may give them an argument to do so. But it is important to recognize the distinction between raising it as an argument and the expectation that this (difficult doctrine to prove) will carry the day.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com