SB800 CONFIRMED AS EXCLUSIVE REMEDY FOR CONSTRUCTION DEFECT CLAIMS
January 24, 2018 —
Jeffrey Brower and Nathan Owens - Newmeyer & Dillion, LLPIn
McMillin Albany LLC v. Superior Court (Cal. Ct. App., Aug. 26, 2015) 2015 Daily Journal D.A.R. 9931 (“
McMillin”), the Fifth Appellate District Court of Appeal in California published a resounding win for builders, general contractors, and others entities seeking the protections of the Right to Repair Act, Civil Code sections 895, et seq. (“SB800”). The
McMillin Court firmly rejected the reasoning and outcome of both
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 (“
Liberty Mutual”) and
Burch v. Superior Court (2014) 223 Cal.App.4th 1411 (“
Burch”), and held that:
the Legislature intended that all claims arising out of defects in residential construction, involving new residences sold on or after January 1, 2003 (§ 938), be subject to the standards and the requirements of the Act; the homeowner bringing such a claim must give notice to the builder and engage in the prelitigation procedures in accordance with the provisions of Chapter 4 of the Act prior to filing suit in court.
(
McMillin, Opinion, p. 15.) The
McMillin Court further held that even if the claimant’s counsel intentionally pleads around SB800 by asserting only tort causes of action, SB800 still applies to all defect claims and a stay of the action to require SB800 compliance is appropriate.
Newmeyer & Dillion has strongly supported builders’ efforts to enforce the Right to Repair Act since its inception. The firm filed an amicus brief in
McMillin on behalf of Leading Builders of America (“LBA”), an association of the leading residential homebuilders in the United States. For years, LBA members developed their warranty and dispute resolution procedures according to the Right to Repair Act and performed prelitigation repairs to the satisfaction of thousands of homeowners.
Liberty Mutual and
Burch undermined the Right to Repair Act by allowing plaintiffs’ attorneys to circumvent the prelitigation procedures to the detriment of homeowners and builders, resulting in confusion and increased litigation. The
McMillin decision breathes new life into the Right to Repair Act and sets the stage for future review by the California Supreme Court.
The
McMillin Court focused on the express language of the Right to Repair Act to arrive at its conclusion that Civil Code sections 896, 897, 943 and 944 demonstrate a clear Legislative intent to occupy the field of construction defect litigation – a belief held by nearly all in the construction industry and the California Superior Courts before
Liberty Mutual. The
McMillin Court found further support for SB800’s comprehensive nature in the Legislative history, which consistently described the Act as “groundbreaking reform” and a “major change” in construction defect litigation, designed to “significantly reduce the cost of construction defect litigation and make housing more affordable.” (
McMillin, Opinion, pp. 18-19.) The
McMillin Court found it inescapable that the Right to Repair Act exclusively governs construction defect litigation involving homes sold on or after January 1, 2003.
The
McMillin, decision will have a significant impact on construction litigation moving forward in two respects. First,
McMillin, is the only appellate decision to date to address whether a builder has the right to enforce SB800 when the claimant’s counsel deliberately attempts to plead around SB800 by asserting only tort claims. Second, the decision provides trial courts with the authority and precedent to ensure compliance with the Right to Repair Act. Trial courts may also find it necessary to revisit prior rulings against builders that relied on
Liberty Mutual.
Newmeyer & Dillion will continue to advocate in support of builders and general contractors by working vigorously to gain further support for the
McMillin, decision and setting the stage for review by the California Supreme Court.
Jeffrey R. Brower is an associate at the Newport Beach office of Newmeyer & Dillion, LLP. His practice focuses on business and construction litigation. Jeffrey can be reached at jeffrey.brower@ndlf.com.
Nathan Owens is the managing partner of the Las Vegas office for Newmeyer & Dillion, LLP. He represents businesses and individuals operating in a wide array of economic sectors including real estate, construction, insurance and health care in all stages of litigation in state and federal court. Nathan can be reached at nathan.owens@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit
www.ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Homeowners Not Compelled to Arbitration in Construction Defect Lawsuit
January 06, 2012 —
CDJ STAFFA California appeals court has ruled that developers cannot enforce CC&Rs in a case where a developer cited an arbitration clause it had inserted into the CC&R. The homeowners are alleging construction defect and wished to sue the developer who claimed a right to this under the CC&Rs.
The Marina del Rey Argonaut reports that particular appeal dealt only with whether the developer could compel arbitration. The underlying construction defect issues will subsequently have to be determined at trial.
The attorney for the homeowners’ association, Dan Clifford, noted that “arbitration has to be agreed to by both parties.” The covenant was drafted by the developer and in addition to requiring arbitration, it had a clause that it could not be amended without the consent of the developers. The court ruled that CC&Rs “can be enforced only by the homeowners association, the owner of a condominium or both.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Bright-Line Changes: Prompt Payment Act Trends
September 16, 2024 —
Stephanie L. Cooksey - Peckar & Abramson, P.C.Untimely payment by the owner for contract work and additional work on construction projects can place an unfair financial burden on contractors and subcontractors. Most states have attempted to eliminate or mitigate this inequity in construction contracting through Prompt Payment Acts that govern payment deadlines and provide remedies for untimely payment. This article addresses the legislative trends aimed at minimizing the risk of non-payment, overdue payment, and withholding retainage in favor of downstream parties to a construction contract.
Fortifying Contractor Protections with “Bright-Line” Language
Over the last decade, states have been tightening prompt payment laws by replacing broad, general statutory language with bright-line rules. What is a bright-line rule? A specific or definite figure, a quantifiable marker—i.e., something owners, contractors, subcontractors, and suppliers should be aware of. Practically speaking, the more bright-line a prompt payment statute is, the greater the likelihood it will affect a construction project in your state.
A standard form construction contract, if not reviewed carefully, can create conflicts or confusion if it gives a party more leeway on payment deadlines than the applicable Prompt Payment Act. For example, consider an owner-issued Construction Change Directive (“CCD”) that requires a contractor to commence additional work immediately while a formal change order is negotiated. Consequently, a CCD can push financial burdens downstream, whether inadvertently or not, and may conflict with statutory payment deadlines. Nevertheless, an owner can be justified in its utilization of a CCD to maintain the project schedule. How should the parties competing interests be resolved?
Read the court decisionRead the full story...Reprinted courtesy of
Peckar & Abramson, P.C.
Big Policyholder Win in Michigan
January 05, 2017 —
Jeremiah M. Welch – Saxe Doernberger & Vita, P.C.Jeremiah Welch and
Michael Barrese recently had a big win in front of the Michigan Court of Appeals.
The case (Skanska-Schweitzer v. Farm Bureau General Insurance Company of Michigan) involved Skanska’s claim for defense and indemnity from Farm Bureau Ins. Co. of Michigan for an injury to an elementary school student arising out of the removal of playground equipment by a landscaping company, Horrocks. Farm Bureau denied coverage because it claimed that the work was not part of Horrocks’ contract with the project owner and therefore Skanska, the construction manager, did not qualify as an additional insured on the policy.
SDV argued that the AI endorsement did not specify that Horrocks’ work be performed as part of its contract with the owner; it only required that the work be performed “for Skanska.”
Read the court decisionRead the full story...Reprinted courtesy of
Jeremiah M. Welch, Saxe Doernberger & Vita, P.C.Mr. Welch may be contacted at
jmw@sdvlaw.com
BWB&O Expands to North San Diego
December 09, 2019 —
Bremer Whyte Brown & O’MearaBremer Whyte Brown & O’Meara is excited to announce our expansion to North San Diego County. Our new office location in Encinitas is strategically located between our Newport Beach and Downtown San Diego offices. The new North San Diego office will provide further resources to better serve our clients.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
Preventing Costly Litigation Through Your Construction Contract
August 17, 2011 —
Douglas Reiser, Builders Council BlogIt’s Tuesday, which means it ’s the middle of your work week. Tuesday is a great time to take an hour to look over your contracts, while the crews are pushing through their scheduled work. Today’s food for thought: How do you use your contract to reduce your litigation burden?
Your contract should do many things. It should discuss the scope of work, scheduling of work, quality of work, coverage for liabilities and conditions and timeliness for payment. But often overlooked is how your contract can lend to dispute resolution.
Commonly, you will see a simple provision that covers governing law, venue for disputes and the awarding of attorneys’ fees. But you can do better. Remember, a contract is enforced to the maximum extent possible in Washington state.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
House Passes $25B Water Resources Development Bill
June 27, 2022 —
Tom Ichniowski - Engineering News-RecordA key federal infrastructure bill advanced with approval in the House of a measure providing $25.3 billion to help finance 22 Army Corps of Engineers storm and flood protection, ecological restoration, harbor dredging and other projects around the country.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Force Majeure and COVID-19 in Construction Contracts – What You Need to Know
April 06, 2020 —
Brenda Radmacher & Jason Suh - Gordon & Rees Construction Law Blog“Force Majeure” – While most construction contracts contain these provisions, they are often not understood in relation to the implications they may have on construction projects. With the onset of the COVID-19 pandemic, we are all taking a closer look at many portions of our contracts. The following is a brief primer on how to understand your construction contract and its potential implications on your business in this season of change.
What is a Force Majeure?
Construction contracts usually take into consideration that the parties want to agree at the outset on who bears the risk of unforeseen incidents that may affect the project’s progression. These issues are generally handled in a “force majeure” clause. Force majeure, according to Mariam Webster’s Dictionary is a “superior or irresistible force; or an event or effect that cannot be reasonably anticipated or controlled.” To be deemed a force majeure, generally the circumstances must be outside of a party’s control which makes performance impossible, inadvisable, commercially impractical, or illegal. In addition to being unforeseeable, the circumstances must have external causation, and be unavoidable. However, the key to understanding if COVID-19 will be deemed a condition that will excuse a contractor’s performance is the specific language in the provision.
Generally force majeure events are unavoidable events such as “acts of God,” most notably weather conditions including hurricanes, tornadoes, floods, earthquakes, landslides, and wildfires, as well as certain man-made events like riots, wars, terrorism, explosions, labor strikes, and scarcity of energy supplies. However, there is not much case law or specifics on conditions similar to COVID-19.
Reprinted courtesy of
Brenda Radmacher, Gordon & Rees and
Jason Suh, Gordon & Rees
Ms. Radmacher may be contacted at bradmacher@grsm.com
Mr. Suh may be contacted at jwsuh@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of