Forethought Is Key to Overcoming Construction Calamities
February 10, 2020 —
Mitch Cohen - Construction ExecutiveWithout warning, an under-construction structure in the southern United States suffered a catastrophic collapse. The tragedy resulted in the death of several people. As a result, engineering and construction post-collapse forensics experts engaged in an 18-month investigation.
Those involved in the design and build project included the general contractor hired by the owner, a prime engineer, a consulting peer-review engineer and a prime structural design firm supported by a sub-consulting structural engineer. Although significant cracking was noticed several weeks before the failure, no one sounded the alarm or deemed the cracking worthy of corrective action.
In their findings, forensic experts found the collapse resulted from the combined failure of the general contractor, engineers and even the owner, who all failed to shut down the work once the cracking reached unacceptable levels and/or take the appropriate actions needed to secure the public safety and mitigate the risk. This was even after the general contractor requested that the engineer-of-record and design manager assess the structure’s extreme cracking. Consequently, the choice to not seriously investigate the crack or seek an independent peer review to design a rectification plan contributed directly to the tragedy. This is typically referred to within the industry as a “negligent professional design error.”
Reprinted courtesy of
Mitch Cohen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cohen may be contacted at
mitch.cohen@rtspecialty.com
Florida’s Citizens Property Insurance May Be Immune From Bad Faith, But Is Not Immune From Consequential Damages
July 15, 2019 —
Michael S. Levine, Andrea DeField & Daniel Hentschel - Hunton Insurance Recovery BlogA coverage dispute arising as a result of property damage from Hurricane Frances, which occurred in 2004, will continue following a Florida appellate court decision in an action brought against Citizens Property Insurance Corp.
The insureds, Manor House, LLC, Ocean View, LLC, and Merrit, LLC, presented a claim to Citizens for damage sustained at nine apartment buildings as a result of Hurricane Florence. After payments for a portion of the property damage were sustained, Citizens continued to dispute the full amount due. Meanwhile, the insureds suffered lost rental income because of the delay. Ultimately, the insureds filed suit against Citizens alleging, among other things, breach of contract and fraud, and sought to recover extra-contractual damages for loss of rental income due to the delay in adjusting and repairing the damaged property.
The trial court granted Citizens’ motion for partial summary judgment on several issues, including Citizens’ motion for partial summary judgment regarding appraiser and umpire fees; motion for partial summary judgment to prevent the insureds from pursuing a claim for extra-contractual, consequential damages; and motion for judgment on the pleadings on the insured’s claim for fraud.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Michael S. Levine,
Andrea DeField and
Daniel Hentschel
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2023 Edition of The Best Lawyers in America®
September 19, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2023 edition of The Best Lawyers in America®. In addition, four attorneys have been included in the 2023 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2023 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
- Lauren S. Curtis – Insurance Law
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Carolinas Storm Damage Tally Impeded by Lingering Floods
October 09, 2018 —
Jim Parsons & Tom Sawyer - Engineering News-RecordAs October rolls in, slow-moving flood crests and sluggish drainage persisting weeks after the passage of Hurricane Florence are leaving large eastern areas in the affected states too inundated for accurate damage assessments. The extent of damage is still largely uncalculated. In some cases, it’s believed to be worsening.
Reprinted courtesy of
Jim Parsons, Engineering News-Record and
Tom Sawyer, Engineering News-Record
Mr. Parsons may be contacted at sawyert@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Define the Forum and Scope of Recovery in Contract Disputes
March 02, 2020 —
Phillip L. Sampson Jr. & Richard F. Whiteley - Construction ExecutivePrivate and public companies spend billions of dollars every year on construction projects. For these projects, time is money, and incorporating the most advantageous legal terms in the construction contract can minimize the number and extent of disputes, and ultimately save money.
It is important to remember that the provisions in construction contracts are negotiable. In a common scenario, the contractor and owner informally agree to the scope of a construction project and its cost. When it is time to reduce the deal to writing, the contractor and owner decide to use an AIA contract that appears to be a standard form. The document looks to be on point, and the parties simply need to fill in a few blanks with the cost and scope-specific information. Presuming that the AIA provisions are mutually protective and beneficial, the parties do not think about altering the “standard” terms. They sign the contract, and the project begins.
Months later, the owner and contractor end up disputing delays on the project, entitlement to various payments, and whether certain aspects of the work are defective. At this point, the parties realize that some of the contract’s terms could have been drafted a bit more favorably—but by that time it’s too late. So remember, construction contracts are negotiable, even provisions within “standard” AIA contracts.
Reprinted courtesy of
Phillip L. Sampson Jr. and Richard F. Whiteley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Sampson may be contacted at phillip.sampson@bracewell.com.
Mr. Whiteley may be contacted at richard.whiteley@bracewell.com.
Read the court decisionRead the full story...Reprinted courtesy of
Two Years, Too Late: Time-Barred Hurricane Loss is Timely Reminder to Insureds
November 01, 2021 —
Michael S. Levine & Yaniel Abreu - Hunton Insurance Recovery BlogIt happens every year. A clearly covered loss occurs and for one reason or another, the policyholder delays in notifying its insurer of the loss. Usually, the cause for the delay is innocent. It may even appear to be justified, such as where the insured prioritizes steps to save its property, inventory or assist dependent customers. But no matter the reason, insurers can be hard-lined in their refusal to accept an untimely claim. This is especially true in states that presume prejudice to the insurer, or where the insurer need not show prejudice at all.
In LMP Holdings, Inc. v. Scottsdale Ins. Co., (Case No. 20-24099-CIV) (S.D. Fla.), a twenty‑seven month delay in notifying the insurer of damage from Hurricane Irma proved fatal to the claim. LMP owns a building in Miami, Florida insured under an all-risk commercial property policy issued by Scottsdale. On September 10, 2017, Hurricane Irma struck South Florida and caused extensive damage to LMP’s building, including punctures to the roof and water damage. LMP identified the damage shortly after the storm. Then, in 2018, LMP identified other storm-caused damage, including a water stain on the ceiling. It again identified additional storm damage in 2019. LMP submitted a claim to its insurer on December 10, 2019—about twenty-seven months after it first noticed the damage. Scottsdale agreed to inspect the property but reserved its rights to deny coverage based on late notice. On July 10, 2020, Scottsdale denied coverage for the damage to the property.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Spencer Mayer Receives Miami-Dade Bar Association's '40 Under 40' Award
March 04, 2024 —
Lewis Brisbois NewsroomMiami, Fla. (February 23, 2024) – Miami Associate Spencer Mayer received the 2024 Miami-Dade Bar Association Young Lawyers Section’s '40 under 40' Award at the association's annual "Miami Nights" event on February 22.
Mr. Mayer serves on the Board of Directors of the Miami Dade Bar Association’s Young Lawyers Section. Lewis Brisbois was a proud sponsor of this event, which raised funds for the organization's community service initiatives and pro bono programming.
Mr. Mayer is a member of the General Liability Practice. His practice focuses on all aspects of civil litigation, including complex commercial litigation, products liability, premises liability, wrongful death, catastrophic injury, and insurance coverage.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Federal Court Predicts Coverage In Nevada for Damage Caused by Faulty Workmanship
April 03, 2013 —
Tred Eyerly - Insurance Law HawaiiMethodically analyzing the damage claims, the federal district court largely denied the insurers' motions for summary judgment for coverage of construction defect claims. Big-D Constr. Corp. v. Take It for Granite Too, 2013 U.S.Dist. LEXIS 8377 (D. Nev. Jan. 22, 2013).
Big-D was the general contractor for a remodeling project of International Gaming Technologies' (IGT) building. Big-D subcontracted with Take it for Granite Too (TIFGT) to install various tiling and stonework on the interior and exterior of the building.
After TIFGT began its stonework, a stone tile fill from an exterior wall. Over the next several months and after completion of TIFGT's work, two additional stones fell from exterior walls. IGT directed Big-D to replace TIFGT's stonework on the walls. Big-D notified TIFGT and requested that it make immediate repairs. TIFGT did not respond and eventually went out of business.
Experts opined that the cause of the stones falling was efflorescence between the tile and the wall. Efflorescence occurred when the stone started to deteriorate, spall, and become soft. It was caused by water entering through an open joint and getting behind the stone tile.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com