Elevators Take Sustainable Smart Cities to the Next Level
May 26, 2019 —
Chris Smith - Construction ExecutiveFrom electric cars to solar panels, technology has been at the forefront of innovation in sustainability efforts. As greenhouse gas emissions continue to be a critical global concern, developing smart cities and sustainable energy practices are more important than ever.
In fact, Gartner predicts that by 2020, half of all smart city objectives will be centered around climate change, resilience and sustainability. To build truly intelligent cities, we need to optimize the sharing of information at a foundational level, starting with the structures on which these cities are built.
Where do we begin?
The United Nations estimates that almost 40 percent of today’s global greenhouse gas emissions come from buildings. To reduce these levels, the industry needs to begin creating smarter structures that use data insights to streamline functions in the building, and this starts with the infrastructural backbone: the elevator.
Reprinted courtesy of
Chris Smith, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
'Taylor Swift Is an Economic Phenomenon': CE's Q1 2024 Economic Update and Forecast
April 29, 2024 —
Grace Calengor - Construction ExecutiveOn March 27, Construction Executive presented its "2024 Q1 Economic Update and Forecast," hosted by ABC Chief Economist Anirban Basu. If you've attended previous versions of this webinar, you're familiar with Basu’s pragmatic approach to the economics of the construction industry and his penchant for predicting recession. But this quarter, he opted for an almost-optimistic approach and hinted at walking back his thoughts on recession. Read the most quotable moments, new poll results and top takeaways from the presentation below.
POLL RESULTS: Q1 2024 vs. Q4 2023 Poll 1: Which of these is the leading challenge for your company today?
Supply chain and/or materials issues
Skills/worker shortage
Insufficient demand for construction services
Availability of financing for projects/project work
None of the above
December 2023 | March 2024 |
10% |
7% |
57% |
60% |
11% |
11% |
19% |
17% |
3% |
6% |
Reprinted courtesy of Grace Calengor, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Common Construction Contract Provisions: No-Damages-for-Delay Clause
March 16, 2017 —
David Cook & Chadd Reynolds - Autry, Hanrahan, Hall & Cook, LLP BlogIn continuing our series on common contract provisions found in construction contracts, this post highlights no-damages-for-delay clauses.
Parties to a contract – particularly a construction contract – may agree that the performance of the contract must occur within a set amount of time. When a party is delayed in performing a contract, it may incur additional costs due to the delay. In most circumstances, unless the parties agree otherwise, the delayed party would be entitled to an extension of time to perform the contract. But it may also seek to recover the additional costs resulting from the delay.
A no-damages-for-delay clause attempts to prevent the delayed party from recovering those additional costs. In construction contracts, an upstream party, such as an owner or prime contractor, typically relies on a no-damages-for-delay clause when presented with a delay claim by a downstream party, such as a subcontractor.
Reprinted courtesy of
David Cook, Autry, Hanrahan, Hall & Cook, LLP and
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLP
Mr. Cook may be contacted at cook@ahclaw.com
Mr. Reynolds may be contacted at reynolds@ahclaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Large Canada Employers and Jobsites Mandate COVID-19 Vaccines
November 08, 2021 —
Scott Van Voorhis - Engineering News-RecordThe push for COVID-19 vaccine mandates is gaining traction in Canada’s construction industry, with governments, large project sites and major employers setting new inoculation deadlines.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: NWP 12 and the Dakota Access Pipeline Easement Get Forced Vacations, while a Potential Violation of the Eighth Amendment Isn’t Going Anywhere
August 10, 2020 —
Anthony B. Cavender - Gravel2GavelHere’s a report on several new decisions made over the past few days.
U.S. SUPREME COURT
U.S. Army Corps of Engineers v. Northern Plains Resources Council
On July 8, 2020, the Court has issued a partial stay of the decision of the U.S. District Court for Montana, which had held that the nationwide use by the Corps of Engineers of its Nationwide Permit 12 to permit oil and gas pipelines must be vacated because the Corps, when it reissued these permits in 2012, failed to follow the requirements of the Endangered Species Act. The breadth of this ruling seems to have surprised and alarmed many past and perspective permittees of the Corps. The stay will not apply to the ongoing Ninth Circuit litigation.
FEDERAL COURTS OF APPEAL
Vega, et al. v. Semple (The U.S. Court of Appeals for the Second Circuit)
On June 29, 2020, the court refused to dismiss a putative class action by past and present inmates of Connecticut’s Garner Correctional Institution who alleged that state correctional officials exposed them to excessive amounts of radon gas in violation of the Eighth Amendment. These officials are alleged to have been “deliberately indifferent” to inmate safety. A 1993 Supreme Court decision, Helling v. McKiney, clearly established the law in this area, and the Garner facility opened in 1992. The defense clams of limited immunity as to federal law violations were rejected.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Changes To Commercial Item Contracting
May 29, 2023 —
Marcos R. Gonzalez - ConsensusDocsThe FAR Council has recently published two changes to commercial item contracting that clarify the definition of commercial services and simplify commercial item determinations (“CIDs”) for contracting officers (“COs”). Since the 1990s, the federal government has encouraged the purchase of commercial items to ease the regulatory burden on vendors who have not previously conducted federal business, encourage innovation, and lower prices[
1]. These different objectives (cost savings, broadening markets, innovation) often have corollary policies; for example, vendors who are not accustomed to the regulatory burdens of government business are encouraged to enter the market by being exempted from a slew of regulations (found in standard commercial items clause FAR 52.212-4). As a result, the regulations applicable to commercial item contracting are those required by statute and executive orders in addition to generic commercial terms that may be tailored due to potential variation in commercial terms.[
2]
Commercial Products v. Commercial Services
The first change, in effect since November 2021 pursuant to the 2019 National Defense Authorization (“NDAA”), split the old definition of “commercial item” into two separate definitions: “commercial product” and “commercial service.”[
3] We are now blessed with the following definitions of commercial products and services, respectively:
Commercial product means—
(1) A product, other than real property, that is of a type customarily used by the general public or by nongovernmental entities for purposes other than governmental purposes, and–
(i) Has been sold, leased, or licensed to the general public; or
(ii) Has been offered for sale, lease, or license to the general public;
Reprinted courtesy of
Marcos R. Gonzalez, Peckar & Abramson, P.C.
Mr. Gonzalez may be contacted at mgonzalez@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Architectural Firm Disputes Claim of Fault
May 27, 2011 —
CDJ STAFFLake-Flato Architects has disputed the arbitration panel’s conclusion that problems with the home of Tom Hanks and Rita Wilson were due to design flaws. The firm settled with the couple for $900,000, however the Idaho Mountain Express reports that David Lake said, “the settlement in the case in no way represents that Lake Flato was responsible for faulty design.” The Express reported that “the arbitrators found that problems at the home were attributable to design errors that did not take into account the cold winter climate of the Sun Valley area.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of