When Construction Defects Appear, Don’t Choose Between Rebuilding and Building Your Case
October 11, 2021 —
Curtis Martin - ConsensusDocsWhen construction defects occur during construction, they intensify pressure from a schedule that may already be tight. Defects must be analyzed, confirmed, removed, and replaced and this can be time consuming. Or course, a construction schedule rarely anticipates defects, demolition, and rework and the owner will still expect the project to be completed on time; however, pressing forward with immediate remediation may have unintended consequences.
Before starting demolition, consider the evidentiary doctrine of spoliation. Spoilation occurs when a party destroys or unreasonably deprives another party of evidence and courts have imposed sanctions on a party that deprives an opponent of evidence. The doctrine has historically concerned documents, but its application has extended to electronic data, and courts also apply it to building conditions in construction defects cases. So, before tearing out or fixing defective work, consider the need to allow the opposing party to inspect, test and document it.
Imagine this scenario. The concrete in a slab placed by your subcontractor shows low compressive strength results in the 28-day cylinder tests. Tearing out the slab and replacing it will put you at least a month behind schedule and you don’t want to waste any time before removing and replacing it. Nevertheless, while you’re rebuilding the defective slab, be mindful that you are also building a case. If you plan to recover the costs you incur because of the defective concrete from the responsible parties, you should allow the subcontractor (and possibly the concrete supplier and other implicated parties) to examine, preserve, and/or test the work in question. Failure to do so may subject you to spoliation sanctions and jeopardize your right to recover damages.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis Martin, Peckar & AbramsonMr. Martin may be contacted at
cmartin@pecklaw.com
Rhode Island Affirms The Principle That Sureties Must be Provided Notice of Default Before They Can be Held Liable for Principal’s Default
August 21, 2023 —
Dennis Cavanaugh & Tasnuva Islam - Construction Law ZoneMost bond forms in use today, including the standard form AIA A312-2010, contain express condition precedents that trigger a surety’s obligations under the bond. Under a performance bond, the bond obligee is required to provide formal notice to the surety that the principal has materially defaulted and that the surety must begin to perform under the terms of the bond. This principle is grounded in the idea that the surety should have an opportunity to address the default and investigate the claim so as to mitigate its own liability. Failure to provide sufficient notice will discharge the surety of its obligations under the bond.
Reprinted courtesy of
Dennis Cavanaugh, Robinson & Cole LLP and
Tasnuva Islam, Robinson & Cole LLP
Mr. Cavanaugh may be contacted at dcavanaugh@rc.com
Ms. Islam may be contacted at tislam@rc.com
Read the court decisionRead the full story...Reprinted courtesy of
The Prompt Payment Rollercoaster
February 23, 2016 —
Garret Murai – California Construction Law BlogThis past year we
wrote about a case involving California’s prompt payment laws and the current state of confusion with the prompt payment statutes which are
scattered throughout the state Code and which are inconsistent in the use of their terminology and, thus importantly, application.
In
United Riggers & Erectors, Inc. v. Coast Iron & Steel Co., California Court of Appeals for the Second District, Case No. B258860 (December 18, 2015), the Court of Appeals for the Second District addressed whether under one of the prompt payment statutes, Civil Code section 8814, a general contractor may withhold retention without being subject to prompt payment penalties if there is a dispute of any kind between the general contractor and the subcontractor, or only when the dispute relates to the retention itself.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Designers “Airpocalyspe” Creations
May 19, 2014 —
Beverley BevenFlorez-CDJ STAFFBlaine Brownell in Architect Magazine discussed how recently some designers have created items to deal with urban pollution, however, the creations themselves are more politically-charged than practical.
Brownell lists recent examples of architects and designers “perverse” creations: “Notable smog-inspired works include the Aegis Parka, a protective jacket created by Dutch design studio Nieuwe Heren; a palladium dichloride coat that changes color in the presence of carbon dioxide emissions and is designed by London-based artist Lauren Bowker; and R&Sie(n)’s ‘Dustyrelief’ building in Bangkok, designed to collect atmospheric dust via an electrostatically-charged facade.”
“Perhaps such proposals—and the disarming irony they conjure—will motivate the changes necessary to clean up our act,” Brownell concluded.
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania’s Supreme Court Limits The Scope Of A Builder’s Implied Warranty Of Habitability
September 10, 2014 —
Edward A. Jaeger, Jr. and William L. Doerler – White and Williams LLPIn Conway v. Cutler Group, Inc., -- A.3d --, 2014 WL 4064261 (Pa.), the Supreme Court of Pennsylvania addressed the question of whether a subsequent home buyer can recover from a home builder pursuant to the builder’s implied warranty of habitability, a warranty that protects those who purchase a newly constructed home from latent defects. Concluding that a builder’s warranty of habitability is grounded in contract, the Court held that a subsequent purchaser of a previously inhabited home cannot recover damages from a builder-vendor based on the builder-vendor’s breach of the implied warranty of habitability. The Court’s decision leaves unanswered the question of whether a purchaser who is also the first user-purchaser of a new home can pursue a breach of warranty action against a builder with whom the purchaser is not in privity of contract.
In Conway, the Cutler Group, Inc. (Cutler) sold a new home to Davey and Holly Fields. The Fields subsequently sold the home to Michael and Deborah Conway. After the Conways discovered water infiltration problems in their home, they filed a one-count complaint against Cutler, alleging that Cutler breached its implied warranty of habitability. In response to the Conways’ complaint, Cutler filed preliminary objections, arguing that the warranty of habitability extends from the builder only to the first purchaser of a newly constructed home. The trial court sustained Cutler’s preliminary objections based on the lack of contractual privity between the parties and the Conways appealed the trial court’s decision. On appeal, the Superior Court reversed, stating that the implied warranty of habitability is based on public policy considerations and exists independently of any representations by the builder, and even in the absence of an express contract between the builder and the purchaser. Cutler appealed the Superior Court’s decision to the Supreme Court.
To address the question of whether the implied warranty of habitability extends to a subsequent purchaser of a used residence, the Court discussed the history of the implied warranty of habitability in Pennsylvania. As stated by the Court, the Court adopted the implied warranty of habitability in the context of new home sales to reject the traditional doctrine of caveat emptor (buyer beware) because the purchaser of a new home justifiably relies on the skill of the developer. Thus, as between the builder-vendor and the buyer, the builder should bear the risk that the home he builds is habitable and functional. In adopting the doctrine, the Court noted that the doctrine is rooted in the existence of a contract – an agreement of sale – between the builder-vendor and the buyer.
Reprinted courtesy of
Edward A. Jaeger, Jr., White and Williams LLP and
William L. Doerler, White and Williams LLP
Mr. Jaeger may be contacted at jaegere@whiteandwilliams.com; Mr. Doerler may be contacted at doerlerw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
The Roads to Justice: Building New Bridges
August 23, 2021 —
Aileen Cho - Engineering News-RecordFormer U.S. Dept. of Transportation Secretary Anthony Foxx grew up on “the wrong side of the tracks.”
“My home was a stone’s throw from Interstates 85 and 77,” recalls Foxx, who grew up in Charlotte, N.C., and served as DOT Secretary from 2013-17 under President Barack Obama. “The airport was nearby. Planes flew at low altitude over our house. Whether or not I was using the system, I sure heard and saw a lot of it.” Desirable areas to live were far away from transportation infrastructure, “and the property values of those living near these projects was diminished.”
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
How AI and Machine Learning Are Helping Construction Reduce Risk and Improve Margins
November 28, 2018 —
Manu Venugopal - Construction ExecutiveThe construction industry is often characterized as high risk and low margin. According to a McKinsey report, almost 98 percent of projects incur cost overruns or delays. Meanwhile, the construction productivity curve has remained flat when compared to other industries.
In the last decade, with the advent of cloud and mobile technologies, industry leaders have been focused on digitizing construction workflows. This has resulted in improved efficiencies, but also has created an explosion of new data sources in the construction industry. Project teams are now capturing and documenting data on mobile devices, site progress is documented via drones and sensors are used to create a connected jobsite.
Reprinted courtesy of
Manu Venugopal, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
PSA: Latest Updates from AGC-VA on COVID Rules (UPDATED)
June 14, 2021 —
Christopher G. Hill - Construction Law MusingsThe recent changes in masking requirements and COVID-related restrictions have prompted questions and concerns throughout the construction industry. We understand your questions and continue to work closely with the Department of Labor and Industry (DOLI) and the Safety and Health Codes Board.
Here is what we know at this point:
- The Governor’s second order terminates the state of public emergency as of May 28, 2021. At that point, the DOLI Safety and Health Codes Board will have 2 weeks to meet and decide whether to rescind, modify, or continue the Final Permanent Standard for Prevention of Covid-19. Companies should continue to follow the standard until further notice.
- UPDATE: At present, the emergency order does not expire before June 30, unless amended or otherwise changed. Therefore, the two-week period to announce a meeting of the SCHB to review the permanent COVID-19 standard does not begin until July 1, though the meeting can occur after the two-week period. AGCVA has joined other groups in pushing for a meeting as soon as possible.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at