Massachusetts Clarifies When the Statute of Repose is Triggered For a Multi-Phase or Multi-Building Project
December 07, 2020 —
Jeffrey J. Vita & Anna M. Perry - Saxe Doernberger & Vita, P.C.Lennar Hingham Holdings, LLC (“Lennar”) built a twenty-eight-building, 150-unit condominium project containing twenty-four discrete phases over a seven-year span. The condominium association subsequently brought an action against Lennar and others alleging design and construction defects to four main components of the common elements: “decks and columns,” “roofing/flashing,” “exterior walls/flashing/building envelope,” and “irrigation system.” In response, the defendants argued that the plaintiff’s claims with respect to six of the twenty- eight buildings were barred by Massachusetts’s six-year statute of repose, G. L. c. 206 § 2B.
The United States District Court for the District of Massachusetts previously held that all twenty-eight of the condominium’s buildings should be treated as a single improvement for purposes of application of the statute of repose. Subsequently, the court certified the following question to the Massachusetts Supreme Judicial Court: Where the factual record supports the conclusion that a builder or developer was engaged in the continuous construction of a single condominium development comprising multiple buildings or phases, when does the six-year period for an action of tort relating to the construction of the condominium’s common or limited common elements start running?
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Anna M. Perry, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Ms. Perry may be contacted at APerry@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Summary Judgment in Favor of General Contractor Under Privette Doctrine Overturned: Lessons Learned
March 27, 2023 —
Garret Murai - California Construction Law BlogIt seems like we’ve been seeing a lot of Privette doctrine cases recently. Here’s another,
Brown v. Beach House Design & Development, 85 Cal.App.5th 516 (2002), which provides a cautionary tale for general contractors to watch what they include in their scope of work and how they manage projects.
The Beach House Case
Kyle Brown was a carpenter employed by subcontractor O’Rourke Construction, Inc. who contracted with general contractor Beach House Design and Development to provide finish carpentry on a construction project. A&D Plastering Co., another subcontractor on the project, had erected scaffolding on the project.
On June 16, 2017, while using A&D’s scaffolding, Brown fell onto a concrete walkway where he suffered severe injuries. Following the accident, Beach House and A&D inspected the scaffolding and found that some of the scaffolding was not properly secured to the building and that planks, crossbars, ties and guardrails had been cut or were missing.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Construction Up in Northern Ohio
October 02, 2013 —
CDJ STAFFCrain’s Cleveland Business reports that both commercial and residential construction have seen spending increases in the last twelve months. The gain was only 5.4%, but it’s still welcome in the area. “It’s been quiet so long, it wouldn’t take much to generate an upturn,” according to Tom Laird, of Gilbane Building Co.
Some of the upturn comes from new building at universities and hospitals, but the corporate sector is also starting new project. Finally, the city of Cleveland is looking for proposals to develop parcels on their waterfront.
Still, some are wary. “It might just be a bubble,” said Jason Jones, the general manager of Turner Construction’s Cleveland office.
Read the court decisionRead the full story...Reprinted courtesy of
Professional Liability Alert: Joint Client Can't Claim Privilege For Communications With Attorney Sued By Another Joint Client
February 05, 2015 —
David W. Evans and Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Anten v. Superior Court (No. B258437 – Filed 1/30/2015), the Second Appellate District held that when joint clients do not sue each other, but one of them sues their former attorney, the nonsuing client cannot prevent the parties to the malpractice suit from discovering or introducing otherwise privileged attorney-client communications made in the course of the joint representation.
Under California Evidence Code §958, in lawsuits between an attorney and a client based on an alleged breach of a duty arising from their attorney-client relationship, communications relevant to the alleged breach are not protected by the attorney-client privilege. Similarly, Evidence Code §962 provides that if multiple clients retain or consult with an attorney on a matter of common interest and the joint clients later sue each other, then the communications between either client and the attorney made in the course of that relationship are not privileged in the suit between the clients.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com; Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
New York Governor Expected to Sign Legislation Greatly Expanding Recoverable Damages in Wrongful Death Actions
June 20, 2022 —
Nicholas P. Hurzeler - Lewis BrisboisNew York, N.Y. (June 3, 2022) - The New York Senate and Assembly recently passed
Bill S74A, also known as the Grieving Families Act, and it is expected that Governor Hochul will likely sign the bill into law. If passed, the law would significantly expand the damages available in wrongful death actions in a number of ways.
First, Section 1 would amend EPTL section 5-4.1 to extend the statute of limitations to commence a wrongful death action from two years to three years and six months, a significant increase that will permit many more wrongful death cases to go forward.
Second, Section 2 amends EPTL section 5-4.3, to allow recovery for emotional damages if a tortfeasor is found liable for causing a death. The current law only allows recovery of economic damages, such as economic hardship caused by a loss of parental guidance. The old law did not permit recovery of damages for grief, sympathy, and loss of companionship or consortium (see, e.g., Liff v. Schildkrout, 49 N.Y.2d 622 (1980); Bumpurs v. New York City Hous. Auth., 139 A.D.2d 438, 439 (1st Dept. 1988)), but that would change with passage of the new bill.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas P. Hurzeler, Lewis BrisboisMr. Hurzeler may be contacted at
Nicholas.Hurzeler@lewisbrisbois.com
Biden Administration Focus on Environmental Justice Raises Questions for Industry
March 22, 2021 —
Karen C. Bennett, Jane C. Luxton, Rose Quam-Wickham & William J. Walsh - Lewis BrisboisThe Biden Administration has left no doubt that it intends to prioritize environmental justice (EJ) in implementing energy and environmental policy. While EJ is not new – in fact, President Clinton signed the first EJ Executive Order (EO 12898) in 1994 – the new Administration’s plan to expand the concept to include “climate justice” and “health equity” is both novel and undefined. Similar to actions taken on climate change (see our previous alert from January 28), President Biden has announced plans for elevating EJ by designating new Cabinet level offices, intensifying enforcement, and advocating for Congressional action. Given the likelihood of serious impacts from these sweeping changes, industry will need to step up engagement as these concepts are integrated into regulatory decisions and U.S. positions globally.
Authority for addressing injustice caused by environmental pollution that disproportionately affects certain communities is found in Title VI of the Civil Rights Act of 1964. The Act imposed a responsibility on the Environmental Protection Agency (EPA or Agency) to ensure that its funds are not being used to subsidize discrimination, based on race, color, or national origin, making EPA’s Office of Civil Rights responsible for the investigation and enforcement of Title VI within the Agency. President Clinton relied on this authority in signing EO 12898, which directed federal agencies to identify and address disproportionately high adverse human health and environmental effects of their programs, policies, and activities on minority and, going beyond the protections covered by Title VI, low-income populations.
Reprinted courtesy of
Karen C. Bennett, Lewis Brisbois,
Jane C. Luxton, Lewis Brisbois,
Rose Quam-Wickham, Lewis Brisbois and
William J. Walsh, Lewis Brisbois
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Ms. Quam-Wickham may be contacted at Rose.QuamWickham@lewisbrisbois.com
Mr. Walsh may be contacted at William.Walsh@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Brooklyn Atlantic Yards Yields Dueling Suits on Tower
September 03, 2014 —
Erik Larson – BloombergForest City Ratner Cos., the initial developer of Brooklyn’s $4.9 billion Atlantic Yards project surrounding Barclays Center arena, exchanged lawsuits with the Swedish construction firm Skanska AB (SKAB) over claims of design flaws and delays in building a stalled residential tower.
The lawsuits, filed today in Manhattan state court, focus on a contract for the 34-floor “modular” residential high-rise building under construction next to the arena for the National Basketball Association’s Brooklyn Nets that opened in 2012 as the centerpiece of the former rail yard and a symbol of the New York borough’s resurgence.
Skanska, a Stockholm-based firm that has grown to become New York’s second-largest building contractor, seeks at least $50 million in damages for changes to the building that were made without consultation, according to its complaint. Brooklyn-based Forest City Ratner blames Skanska for the project’s problems, citing “tens of millions of dollars” in cost overruns caused by a lack of skill and a failure to adhere to terms of the 2012 contract.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Larson, BloombergMr. Larson may be contacted at
elarson4@bloomberg.net
KB Homes Sues Condo Buyers over Alleged Cybersquatting and Hacking
October 22, 2013 —
CDJ STAFFWillowbrook, a condominium complex in Lakewood Ranch, Florida has had problems with water intrusion. Now the builder is having problems with some of the residents. National home builder KB Homes is alleging that a pair of Willowbrook home owners who created a web site about their problems have violated federal cybersquatting laws, as the web site names they have registered are close to that KB Homes. The suit alleges that Andrew Smith and Daniel Koehler hope to either get KB Homes to purchase the web site or to buy back their homes.
The lawsuit also alleges that three other individuals, William Crismon, Patrick McGettigan, and Armando Oyola-Delgado, conspired to intercept e-mails between KB Home and Dueall Construction. KB Homes claims that the three gained access to a WiFi hotspot used by Dueall.
Read the court decisionRead the full story...Reprinted courtesy of