You Are Your Brother’s Keeper. Direct Contractors in California Now Responsible for Wage Obligations of Subcontractors
January 31, 2018 —
Garret Murai – California Construction Law BlogIf there’s one law from the 2017 Legislative Session that’s garnered a lot of attention in the construction press, it’s
AB 1701. Under AB 1701, beginning January 1, 2018, for contracts entered into on or after January 1, 2018, direct contractors may be found liable for unpaid wages, fringe or other benefit payments or contributions, including interest, but excluding penalties or liquidated damages, owed by a subcontractor of any tier to their workers. Here’s what you need to know about AB 1701.
What code section did AB 1701 amend?
AB 1701 added a a new section 218.7 to the Labor Code.
To whom does AB 1701 apply?
AB 1701 applies to direct contractors only. A direct contractor is defined as a “contractor that has a direct contractual relationship with an owner.”
On what types of projects does AB 1701 apply?
AB 1701 applies to private works projects only.
When does AB 1701 take effect?
AB 1701 took effect on January 1, 2018 and applies to all contracts entered into on or after January 1, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
Garret, Murai, Wendel, Rosen, Black, Dean, LLPMr. Murai may be contacted at
gmurai@wendel.com
Hunton Andrews Kurth Insurance Attorney, Latosha M. Ellis, Honored by Business Insurance Magazine
May 03, 2021 —
Andrea DeField & Michael S. Levine - Hunton Andrews KurthWe are proud to share that Business Insurance has named Hunton Andrews Kurth insurance coverage associate, Latosha M. Ellis, one of the magazine’s 2021 Break Out Award winners. Business Insurance’s Break Out Awards honor 40 top professionals from around the country each year who are expected to be the next leaders in risk management and the property/casualty insurance field. Business Insurance reviewed hundreds of nominees, all of whom have worked in commercial insurance or related sectors for under 15 years. Out of those hundreds, Latosha was selected as one of the 40 honorees for 2021.
Latosha is well-deserving of this honor. She is committed to excellence in the practice of law and in her service to clients, both of which have earned her a sterling reputation in the Virginia and District of Columbia legal communities. In addition to her litigation success and excellent client service skills, Latosha is a leader, both in the firm and in the legal community. Latosha not only serves as a mentor to several young attorneys at our firm, but she is also a board member of the University of Richmond Law School Alumni Board (currently serving on a three-year term) and a planning member of the American Bar Association’s (ABA) professional development committee. She also co-chaired the 2021 ABA Insurance Coverage and Litigation Committee Annual CLE Conference, for which she implemented new diversity and inclusion standards and ensured several program sessions geared towards young lawyers. In addition, Latosha was selected as the firm’s 2019 Pathfinder for the Leadership Council for Legal Diversity, serves on the executive board of the Women’s Bar Association of the District of Columbia, and was inducted into the American Bar Association’s Section of Litigation Young Lawyer Leadership Program.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Ms. DeField may be contacted at adefield@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Major Change to Residential Landlord Tenant Law
July 15, 2019 —
Lawrence S. Glosser - Ahlers Cressman & Sleight PLLCGovernor Inslee has just signed SB 5600 which results in major changes to the Residential Landlord-Tenant Act (RCW 59.18) regarding the eviction process of residential tenants. The changes do not apply to non-residential tenancies which are still governed by RCW 59.12. The new law includes additional protections for tenants and limits the ability of landlords to evict tenants or recover costs for legal proceedings. It also grants judges substantial discretion in eviction hearings whereas judges were previously bound by the express terms of the statute.
The major changes to the law are listed below:
- A landlord must provide a tenant 14 days’ notice instead of three days’ notice in order to cure default in the payment of overdue rent. The Attorney General’s Office will create a uniform 14-day notice to pay and vacate default form.
- Landlords must first apply any payment by a tenant to the rent amount before applying it towards other charges, including fees or other costs.
Read the court decisionRead the full story...Reprinted courtesy of
Lawrence S. Glosser, Ahlers Cressman & Sleight PLLCMr. Glosser may be contacted at
larry.glosser@acslawyers.com
Contract Change # 10: Differing Site Conditions (law note)
March 28, 2018 —
Melissa Dewey Brumback - Construction Law in North CarolinaPreviously, the A201 required a Contractor to provide notice to the Owner and Architect within 21 days after discovery of unforeseen site conditions. This notification is required prior to the conditions being disturbed, so as to allow the Design Team the ability to evaluate the site and determine the compensability of any such differing conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North Carolina
New York Bars Developers from Selling Condos due to CD Fraud Case
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to GlobeSt, New York “Attorney General Eric T. Schneiderman has announced a settlement agreement that bars developers Joseph Scarpinito and Shiraz Sanjana—and five affiliated entities they own and operate—from offering or selling securities, including condo and coop sales, in or from New York State.”
The settlement is in “result of an investigation by the Attorney General’s real estate finance bureau into allegations of fraud by the developers of the Mirada, an eight-story Harlem condominium.” GlobeSt also stated that the agreement “provides for binding arbitration with the condo purchasers for alleged construction defects, and requires the developers to pay $500,000 in penalties and fines to New York State.”
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Defend Claims of Negligence and Private Nuisance
July 10, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined there was a duty to defend negligence and private nuisance claims for dumping materials on the plaintiffs' property. Peters Heavy Construction, Inc. v. X-Pert One Tracking Corp., 2018 Wisc. App. LEXIS 358 (Wis. Ct. App. March 29, 2018).
Peters Heavy Construction sued X-Pert One for negligently depositing shingle materials, tires, and other solid materials on Peters' property, causing damage to Peters, including loss of use of portions of the property. Peters also alleged that X-Pert One's actions negligently created a private nuisance causing harm to Peters' property. X-Pert One's insurer, Northfield Insurance Company, was also sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Avoid Delay or Get Ready to Pay: The Risks of “Time-Is-of-The-Essence” Clauses
August 29, 2018 —
Stephen Orlando - Gordon & Rees Construction Law BlogLike death and taxes, construction delays are inevitable. Even the most cautious, diligent contractor may face subcontractor disputes, supply shortages, or inclement weather which slows down a project. Even if the contractor avoids unexpected problems, the sheer complexity of a job may cause a contractor to exceed the deadlines proposed in a contract.
Fortunately, courts recognize the practical reality of construction projects and the unavoidable delays which may arise. Therefore, as a general rule, a contractor is only liable for delayed completion of a project if the delay resulted from the contractor’s unreasonable performance of his or her work. Reasonable performance will typically serve as a defense to a claim of delayed completion. This defense is a vital asset when a contractor surpasses the project’s expected timeframe.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen Orlando, Gordon & Rees Scully Mansukhani
Miller Act Bond Claims Subject to “Pay If Paid”. . . Sometimes
November 04, 2019 —
Christopher G. Hill - Construction Law MusingsThe Federal Miller Act is a great tool that subcontractors and suppliers on Federal projects can use for collection of wrongfully withheld amounts due. However, as a recent federal case from the Eastern District of Virginia points out, the construction contract’s terms affect when a subcontractor or supplier can use this great collection tool and how much it can recover.
In Aarow v Travelers the Court looked at the interaction between a typical termination clause, a “pay when paid” clause, and the Miller Act. The key facts are these. The general contractor on the project at issue, Syska, did not get paid some disputed amounts by the owner and subsequently did not pay Aarow, the plaintiff and a subcontractor on the project. Aarow then refused to continue work and was terminated by Syska who then took over the completion of the work. Aarow sued, seeking damages for the value of its work prior to the termination. Travellers, the surety defended stating that, if Aarow was properly terminated for cause by Syska, then Aarow was not entitled to payment under the contract until such time as the work was completed and accepted by the owner. The termination clauses are set out in the linked opinion.
The Court agreed with Travelers, stating that the pay when paid clause created a situation whereby Aarow could not stop work merely because of a non-payment by Syska attributed to non-payment by the owner. The Court was clear in stating that the Miller Act trumps “pay when paid” in instances where the only cause for non-payment is non-payment by an owner. The Court then reasoned that it is the interaction between the termination and “pay when paid” provisions, and not the “pay when paid” clause itself, that exonerated Travelers because it created the default by Aarow due to its refusal to continue work. In short, Aarow was properly terminated for cause because it left the job without justification and therefore Travelers was not liable.
Read the court decisionRead the full story...Reprinted courtesy of