In Texas, a General Contractor May be Liable in Tort to a Third-Party Lessee for Property Damage Caused by a Subcontractor’s Work
February 16, 2016 —
Michael L. DeBona – White and Williams LLPIn Zbranek Custom Homes, Ltd. v. Joe Allbaugh, et al., No. 03-14-00131-CV, 2015 WL 9436630 (Tex.App.-Austin Dec. 23, 2015), the Court of Appeals of Texas, Austin, considered the circumstances under which a general contractor can be held liable for injuries to a non-contracting party’s property. The court held that, because the general contractor, Zbranek Custom Homes, Ltd. (Zbranek), exercised control over the construction of the fireplace at issue, Zbranek owed a duty of care to the first lessees of the home that Zbranek built.
In Zbranek, Bella Cima Developments, L.P. (Bella Cima) hired Zbranek to act as the general contractor for the construction of a home. As the general contractor, Zbranek engaged various subcontractors to perform different aspects of the construction, including the framing, stucco and masonry work for an outdoor fireplace.
Read the court decisionRead the full story...Reprinted courtesy of
Michael L. DeBona, White and Williams LLPMr. DeBona may be contacted at
debonam@whiteandwilliams.com
Killer Subcontract Provisions
January 20, 2020 —
Patrick McNamara - Porter Law GroupWe are frequently requested by subcontractor clients to review the subcontract that has been prepared by the prime contractor, before our client signs it. While no two agreements are identical, there are a number of problematic contract provisions that appear in many agreements. Here is a list of ten such provisions (and their variations) that are potential “deal breakers”:
- PAY IF/WHEN PAID (e.g. “Contractor shall have the right to exhaust all legal remedies, including appeals, prior to having an obligation to pay Subcontractor.”) “Pay-if-paid” provisions (“Receipt of payment from Owner shall be a condition precedent to Contractor’s duty to pay Subcontractor”) are illegal in California. However, the only legal limit on “Pay-When-Paid” provisions is that payment must be made “within a reasonable time.” The example above, as written, essentially affords the prime contractor a period of several years following completion of the project before that contractor has an independent duty to pay its subcontractors – not a “reasonable” amount of time, to those waiting to be paid. A compromise is to provide a time limit, such as 6 months or one year following substantial completion of the project.
- CROSS-PROJECT SET-OFF (e.g. “In the event of disputes or default by Subcontractor, Contractor shall have the right to withhold sums due Subcontractor on this Project and on any other project on which Subcontractor is performing work for Contractor.”) Such provisions are problematic and likely unenforceable, as they potentially bar subcontractors’ lien rights. Such provisions should be deleted.
- CONTRACTOR/SUBCONTRACTOR RESPONSIBILITY FOR DESIGN QUALITY (e.g. “Subcontractor warrants that the Work shall comply with all applicable laws, codes, statutes, standards, and ordinances.”) Unless a subcontractor’s scope of work expressly includes design work, this provision should either be deleted or modified, with the addition of the following phrase: “Subcontractor shall not be responsible for conformance of the design of its work to applicable laws, codes, statutes, standards, and ordinances.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Specific Source of Water Not Relevant in Construction Defect Claim
June 28, 2013 —
CDJ STAFFThe Nebraska Court of Appeals has concluded that a lower court came to the correct conclusion in a construction defect case involving water intrusion. The Hiatts built a home in North Platte, Nebraska, in in 2004 which they sold to the Oettingers in May, 2006. Shortly thereafter, the Oettingers started experiencing problems with water intrusion and contacted the Hiatts. The Hiatts responded by replacing the septic lift. Subsequently, the Oettingers landscaped their yard, which they allege was done with the assistance of the Hiatts. The water problems continued and “the parties took substantial remedial measures, including excavating the sidewalk and inspecting the downspouts.” The water problems continued, getting worse and requiring increasingly aggressive responses.
The Oettingers then had a series of inspections, and they hired the last of these inspectors to actually fix the water intrusion problem. At that point, they filed a lawsuit against the Hiatts alleging that the Hiatts “breached their contact by constructing and selling a home that was not built according to reasonable construction standards,” and that they “were negligent in the repair of the home in 2009.”
During the trial, Irving Hiatt testified that they “tarred the outside of the basement and put plastic into the tar and another layer of plastic over the top of that.” He claimed that the problem was with the Oettingers’ landscaping. This was further claimed in testimony of his son, Vernon Hiatt, who said the landscaping lacked drainage.
The Oettingers had three experts testify, all of whom noted that the landscaping could not have been the problem. All three experts testified as to problems with the Hiatts’ construction. The court concluded that the Hiatts had breached an implied warranty, rejecting the claim that the water intrusion was due to the landscaping. The Hiatts appealed the decision of the county court to the district court. Here, the judgment of the lowest court was confirmed, with the district court again finding a breach of the implied warranty of workmanlike performance.
The Hiatts appealed again. They alleged that the district court should not have held a breach of implied warranty existed without proving the source of the water intrusion, and that damages should have been apportioned based on the degree to which the Oettingers’ landscaping and basement alterations were responsible. The appeals court dispensed with the second claim first, noting that “they do not argue this error in their brief nor do they explain how or why the trial court should have apportioned damages.” The court also noted that although the Oettingers made a negligence claim in their suit, the case had been decided on the basis of a breach of implied warranty.
The appeals court upheld the Oettingers’ claim of a breach of implied warranty. In order to do this, the court noted that the Oettingers had to show that an implied warranty existed, that the Haitts breached that warranty, damage was suffered as a result, and that no express warranty limited the implied warranty. That court noted that “the record is sufficient to prove that the Hiatts breached the implied warranty in the method in which they constructed the basement” and that “this breach was the cause of the Oettingers’ damages.”
The court concluded that the Oettingers “provided sufficient evidence that the Hiatts’ faulty construction allowed water, whatever its source, to infiltrate the basement.” The court rejected the Hiatts’ claim that the Oettingers’ repairs voided the warranty, as it was clear that the Hiatts were involved in carrying out these repairs. The court’s final conclusion was that “the evidence in the record supports the trial court’s factual finding that the Hiatts’ flawed construction caused water damage to the Oettingers’ basement.”
Read the court decisionRead the full story...Reprinted courtesy of
As Evidence Grows, Regions Prepare for Sea Level Rise
July 02, 2018 —
Pam Radtke Russell - Engineering News RecordCities, states and regions are taking steps to prepare their buildings, infrastructure and homes for the impacts of climate change as bad news continues to mount about rising sea levels.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Chambers USA 2020 Ranks White and Williams as a Leading Law Firm
June 15, 2020 —
White and Williams LLPWhite and Williams is once again recognized by Chambers USA as a leading law firm in Pennsylvania for achievements and client service in the area of insurance law. In addition, four lawyers received individual honors – two for their work in insurance, one for his work in banking and finance and another for his work in commercial litigation.
White and Williams is acknowledged for its renowned practice offering expert representation to insurers and reinsurers across an impressive range of areas including coverage, bad faith litigation and excess liability. The firm is recognized for its notable strength in transactional and regulatory matters, complemented by its adroit handling of complex alternative dispute resolution proceedings and is described as "reasoned and respectful." Chambers also acknowledged the firm's broad trial capabilities, including handling data privacy, professional liability and toxic tort coverage claims as well as its experience in substantial claims arising from bodily injury and wrongful death suits. White and Williams' cross-disciplinary team is also highlighted, characterized for "work[ing] well together and provid[ing] exceptional representation."
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Insureds' Summary Judgment Motion on Mold Limitation Denied
November 10, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe insureds' motion for partial summary judgment on the applicability of the homeowner's mold limitation was denied. R.W.& R. v. Liberty Mutual Fire Ins. Co., 2016 U.S.Dist. LEXIS 131586 (W.D. Wash. Sept. 26, 2016).
The policy imposed a $5,000 limit on losses caused by mold. Plaintiffs discovered that their dishwasher was leaking and reported the loss to Liberty. Liberty's contractor concluded that the bottom of the dishwasher had rusted out, causing water to seep into parts of the kitchen and the laundry/utility room below. The contractor used dehumidifiers to extract moisture from the affected areas and removed damaged cabinetry, drywall and tiling. The contractor discovered mold that it believed predated the dishwasher leak. Although the contractor took steps to remove the mold, its dehumidification efforts exacerbated the problem by dispersing mold spores throughout portions of the house.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Loan Modifications Due to COVID-19 Pandemic: FDIC Answers CARES Act FAQs
May 11, 2020 —
Nancy Sabol Frantz, Marissa Levy, Timothy E. Davis & Kristen E. Andreoli - White and WilliamsIn support of financial institutions and borrowers during the COVID-19 pandemic, the newly enacted Coronavirus Aid, Relief, and Economic Security Act (CARES Act) includes a number of provisions permitting lenders to suspend, during a covered period, requirements under U.S. Generally Accepted Accounting Principles (GAAP) with respect to categorizing certain loan modifications as a troubled debt restructuring (TDR) due to COVID-19. In light of the CARES Act, the Federal Deposit Insurance Corporation (FDIC) issued a series of answers to FAQs for financial institutions with respect to loan modifications. The FAQs help guide lenders as well as borrowers as they address pending defaults under existing credit facilities. The FAQs encourage financial institutions to work with borrowers who may be unable to meet their payment obligations due to COVID-19 in several ways:
Payment Accommodations
Short-term accommodations which modify, extend, suspend or defer repayment terms should be intended to facilitate the borrower’s ability to work through the immediate impact of the virus. According to the FAQs, all loan accommodation programs should ultimately be targeted towards repayment. To that end, the FDIC recommends that financial institutions address deferred or skipped payments by either extending the original maturity date or by making those payments due in a balloon payment at the maturity date of the loan.
Reprinted courtesy of White and Williams attorneys
Nancy Sabol Frantz,
Marissa Levy,
Timothy E. Davis and
Kristen E. Andreoli
Ms. Frantz may be contacted at frantzn@whiteandwilliams.com
Ms. Levy may be contacted at levymp@whiteandwilliams.com
Mr. Davis may be contacted at davist@whiteandwilliams.com
Ms. Andreoli may be contacted at andreolik@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of