Coverage For Advertising Injury Barred by Prior Publication Exclusion
July 01, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Ninth Circuit held that a claim for advertising injury was properly denied under the prior publication exclusion. Street Surfing, LLC v. Great Am. E&S Ins. Co., 2014 U.S. App. LEXIS 10737 (9th Cir. June 10, 2014).
Street Surfing began selling a two-wheeled, inline skateboard called the "Wave" in December 2004. By 2007, Street Surfing also sold and advertised accessories for the Wave, such as "Lime Green Street Surfing Wheels for The Wave," and the "New Ultimate Street Surfer Wheel Set."
Rhyn Noll, who owned the registered trademark "Streetsurfer," sued Street Surfing in June 2008, claiming trademark infringement, unfair competition and unfair trade practices. Street Surfing had known that Noll owned the "Streetsurfer" trademark since early 2005. In September 2008, Street Surfing submitted a claim for coverage to Great American and tendered Noll's complaint.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indemnification Against Release/“Disposal” of Hazardous Materials
May 18, 2020 —
Brian S. Wood & Miranda R. Millerick - ConsensusDocsIt is very common, if not nearly an industry standard, for construction contracts and subcontracts to contain provisions addressing the discovery of unanticipated hazardous materials. Many of these provisions require a contractor or subcontractor to discontinue work where hazardous materials are discovered. An example of such a clause can be found in the American Institute of Architects (AIA) Document A201 (2017), Section 10.3.1, which states in part:
If the Contractor encounters a hazardous material or substance not addressed in the Contract Documents and if reasonable precautions will be inadequate to prevent foreseeable bodily injury or death to persons resulting from a material or substance, including but not limited to asbestos or polychlorinated biphenyl (PCB), encountered on the site by the Contractor, the Contractor shall, upon recognizing the condition, immediately stop Work in the affected area and notify the Owner and Architect of the condition.
A similar clause in ConsensusDocs does not require the contractor to stop work, but provides that the “Contractor shall not be obligated to commence or continue work until any Hazardous Material discovered at the Work site has been removed, rendered or determined to be harmless by the Owner as certified by an independent testing laboratory and approved by the appropriate government agency.”
Reprinted courtesy of
Brian S. Wood, Smith, Currie & Hancock LLP and
Miranda R. Millerick, Smith, Currie & Hancock LLP
Mr. Wood may be contacted at bswood@smithcurrie.com
Ms. Millerick may be contacted at mrmillerick@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
Mandatory Attorneys’ Fee Award for Actions Brought Under the Underground Utility Damage Prevention Act
September 22, 2016 —
Lindsay K. Taft – Ahlers & Cressman PLLCIn Washington, RCW 19.122 (the Underground Utility Damage Prevention Act or “Call Before You Dig” statute) provides for the protection of underground utilities. The statute was recently updated in 2013 and provides that homeowners and contractors must call “811” to schedule a “utility locate” prior to commencing any excavation. Failure to do so can result in steep penalties, as well as a mandatory fee award for the prevailing party.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Mutual Or Concurrent Delay Caused By Subcontractors
March 23, 2020 —
David Adelstein - Florida Construction Legal UpdatesHow are delay damages treated when two subcontractors cause a mutual or concurrent delay to the project?
Assume multiple subcontractors concurrently contributed to an impact to the critical path resulting in a delay to the project. The delay caused the prime contractor to: (1) be assessed liquidated damages from the owner and (2) incur extended general conditions. The prime contractor will be looking to the subcontractors for reimbursement for any liquidated damages it is assessed along with its extended general conditions costs.
There is really no great case that addresses this point when two (or more) subcontractors mutually or concurrently delay the project. It is also not uncommon, and frankly expected, that a subcontractor will point the finger at another subcontractor for the cause of the delay or that another subcontractor was concurrently delaying the project.
The prime contractor should absolutely, without any exception, undertake efforts with a scheduling consultant to allocate the delay caused by subcontractors. Taking an approach that joint and several liability applies between multiple subcontractors and/or not trying to apportion delay because the subcontractors concurrently delayed the critical path at the same time is probably not the best approach. The prime contractor should have an expert render an opinion as to the allocation of the delay period amongst responsible subcontractors that delayed the critical path. Not doing so, in my opinion, is a mistake.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Why You May Not Want a Mandatory Mediation Clause in Your Construction Contract
October 26, 2017 —
Christopher G. Hill - Construction Law MusingsI know, you are likely surprised by the title of this post. You’ve read Construction Law Musings for a while now and know that as a Virginia Supreme Court certified mediator, I have advocated mediation as a great way to resolve your construction disputes short of the expensive and time consuming litigation process. Knowing all of this, you as a reader of this blog (thanks by the way) probably wonder why I think that a mandatory mediation clause may not be the best thing for your construction contracts. I can understand your possible confusion (particularly
in light of this post from @sethsmiley).
Please don’t take the headline as my suddenly taking a new view of mediation. Short of simply resolving the dispute between the parties to the construction contract, mediation still remains number one on my list of construction dispute resolution mechanisms. I still believe that it is useful even when a resolution is not met after a good faith attempt by both sides to come to a business agreement. However, I also believe that mediation works best when entered into voluntarily by the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
OSHA Finalizes PPE Fitting Requirement for Construction Workers
December 31, 2024 —
Jonathan H. Schaefer - Construction Law ZoneOn December 11, 2024, the Occupational Safety and Health Administration (OSHA) announced it finalized a revision to the personal protective equipment (PPE) standard for the construction industry. The
final rule adds specific language to the existing standard requiring employers to provide properly fitting PPE for construction industry workers. This change aligns the construction industry with the standards in place for the general industry.
According to OSHA, many types of PPE must properly fit workers. Improperly sized PPE can ineffectively protect workers, creating new hazards for them, such as oversized gloves or protective clothing being caught in machinery and discouraging use because of discomfort or poor fit. OSHA stated that the longstanding issue with improperly fitting PPE particularly impacted women, as well as physically smaller or larger workers.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan H. Schaefer, Robinson+ColeMr. Schaefer may be contacted at
jschaefer@rc.com
The Louvre Abu Dhabi’s Mega-Structure Domed Roof Completed
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFThe final part of the Louvre Abu Dhabi’s 180-metres (almost 600 feet) long domed roof was put into place on Monday, according to Arabian Business. The 12,000 tonne dome is “made up of a steel structure, weighing 7,000 tonnes (almost as much as the Eiffel Tower), and a further 5,000 tonnes of aluminum cladding.”
Carlos Antonio-Wakim, executive director of development at master developers TDIC, stated (as quoted by Arabian Business) that construction was on schedule for the opening of the museum, which is on Saadiyat Island, by the end of next year.
“The concrete works under the dome is all done, so we have all the galleries up and fit-out of those galleries has already begun,” Antonio-Wakim told Arabian Business. “There is also a lot of electromechanical works. A complex project like this requires a lot of mechanical and electrical coordination.”
Read the court decisionRead the full story...Reprinted courtesy of