Guilty Pleas Draw Renewed Interest In Nevada’s Construction Defect Laws
December 09, 2011 —
CDJ STAFFA report this week by David McGrath Schwarz of the Las Vegas Sun suggests that Nevada’s construction defect laws will be a point of much contention in upcoming legislative sessions. The report cites renewed interest in the state’s construction defect laws due to ongoing federal investigations of construction defect attorney Nancy Quon and construction company owner Leon Benzer. Guilty pleas have been entered by at least ten individuals including an attorney, property managers, straw purchasers, and former HOA board members.
The article suggests that Nevada’s Chapter 40 laws are easily manipulated to the detriment of Nevada’s homebuilding industry. Construction industry lobbyists have tried unsuccessfully to change the laws in past legislative sessions.
The Sun’s article speculates that the building industry might be able to gain legislative concessions due to the volume of guilty pleas and what it refers to as examples of Chapter 40 abuses. ”With federal authorities collecting guilty pleas, the construction industry has prime examples of the system being abused, and how lucrative it can be for attorneys.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Utah’s Highest Court Holds That Plaintiffs Must Properly Commence an Action to Rely on the Relation-Back Doctrine to Overcome the Statute of Repose
August 20, 2018 —
Shannon M. Warren - The Subrogation StrategistEarlier this summer, in Gables & Villas at River Oaks Homeowners Ass’n v. Castlewood Builders LLC, 2018 UT 28, the Supreme Court of Utah addressed the question of whether the plaintiff’s construction defects claims against the general contractor for a construction project were timely-filed, or barred by the statute of repose. In Utah, the statute of repose requires that an action be “commenced within six years of the date of completion.” The plaintiff alleged that its 2014 amended complaint naming the general contractor as a defendant was timely-commenced because, before the date on which Utah’s statute of repose ran, a defendant filed a motion to amend its third-party complaint to name the general contractor as a defendant, and the defendant subsequently assigned its claims to the plaintiff. The plaintiff argued that the filing of its 2014 amended complaint related back[1] to the date of its original complaint. The Supreme Court disagreed, holding that an action is “commenced” by filing a complaint and that a motion for leave to amend does not count as “commencing” an action.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
1 De Haro: A Case Study on Successful Cross-Laminated Timber Design and Construction in San Francisco
November 06, 2023 —
Cait Horner, Adam J. Weaver & Allan C. Van Vliet - Gravel2Gavel Construction & Real Estate Law BlogAt the intersection of San Francisco’s SOMA, Potrero Hill and Showplace Square districts, a first-of-its-kind building offers an example of the potential widespread success of mass timber construction in the United States. 1 De Haro, a 134,000-square-foot, 4-story office and light industrial project built by Bay Area developer
SKS Partners is not only the first cross-laminated timber (CLT) building in the San Francisco, it is also the first multistory mass timber building of its type to be fully executed in California and the first CLT project in the United States to be delivered via railways. We recently sat down with Yvonne Fisher and Lee Ishida of SKS to discuss the unique design process, marketing success and overall industry buzz surrounding one of their latest
projects.
Reprinted courtesy of
Cait Horner, Pillsbury,
Adam J. Weaver, Pillsbury and
Allan C. Van Vliet, Pillsbury
Ms. Horner may be contacted at cait.horner@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Mr. Van Vliet may be contacted at allan.vanvliet@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Brooklyn Atlantic Yards Yields Dueling Suits on Tower
September 03, 2014 —
Erik Larson – BloombergForest City Ratner Cos., the initial developer of Brooklyn’s $4.9 billion Atlantic Yards project surrounding Barclays Center arena, exchanged lawsuits with the Swedish construction firm Skanska AB (SKAB) over claims of design flaws and delays in building a stalled residential tower.
The lawsuits, filed today in Manhattan state court, focus on a contract for the 34-floor “modular” residential high-rise building under construction next to the arena for the National Basketball Association’s Brooklyn Nets that opened in 2012 as the centerpiece of the former rail yard and a symbol of the New York borough’s resurgence.
Skanska, a Stockholm-based firm that has grown to become New York’s second-largest building contractor, seeks at least $50 million in damages for changes to the building that were made without consultation, according to its complaint. Brooklyn-based Forest City Ratner blames Skanska for the project’s problems, citing “tens of millions of dollars” in cost overruns caused by a lack of skill and a failure to adhere to terms of the 2012 contract.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Larson, BloombergMr. Larson may be contacted at
elarson4@bloomberg.net
The Administrative Procedure Act and the Evolution of Environmental Law
September 19, 2022 —
Anthony B. Cavender - Gravel2GavelEnacted in 1946, the Administrative Procedure Act (APA) has provided a lasting framework for federal agency rulemaking and adjudication, as well as establishing the power of the federal courts to exercise judicial review over these actions of the federal bureaucracy. The APA is codified at 5 U.S.C. §§ 551–559, and §§ 701-706. There have been very few amendments made to the APA over these years, which indicates that Congress is reasonably satisfied with its administration and implementation.
What follows is an overview of how the APA has been used by the courts to resolve disputes involving the federal agencies, with particular attention being paid to the development of environmental law and practice. While there have been very few amendments to the statute, the courts have been free to enlarge upon the sometimes-opaque text of the APA to, in effect, change the law, even in an era when “textual fidelity” to the language of the statute is the prevalent approach.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Downtown Sacramento Building Riddled with Defects
July 23, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Board of Equalization tower in Sacramento, California has gone through $60 million in repairs to deal with issues such as bats, floods, leaky windows, mold, and glass panels that would “pop off the building with no warning and shatter on the sidewalk,” according to Insurance News. However, an additional $115 million in repairs are planned to deal with “crumbling core plumbing” and “concrete-and-glass exterior,” among other problems.
Now, “a Sacramento attorney filed a $50 million tort claim this month, a first step toward suing the tax-collecting department on behalf of employees who say their bosses downplayed the building's ailments and put workers' health at risk.”
"Even though my lawyers told me not to say this, I don't think it's safe," board Chairman Jerome Horton told Insurance News.
Read the court decisionRead the full story...Reprinted courtesy of
Florida Condo Collapse Victims Reach $1 Billion Settlement
May 23, 2022 —
Erik Larson - BloombergVictims of the South Florida condominium collapse that killed 98 people last year reached settlements totaling almost $1 billion with defendants including the developer of an adjacent luxury tower, engineers and a law firm for the condo association.
The massive deal was cobbled together through multiple agreements before a state court hearing Wednesday in Miami, according to Harley S. Tropin, one of the lead plaintiffs’ lawyers who had sued on behalf of survivors and victims’ families. He said he disclosed the settlements in court.
“We are pleased to have resolved this case with the defendants to get what we think is a very fair recovery to help end the litigation and allow the victims to attain some means of attempting to move forward from this horrific tragedy,” Tropin said in an emailed statement.
The 12-story Champlain Towers South condominium building in Surfside, Florida, collapsed June 24, triggering multiple lawsuits and prompting state and federal probes. A focus was the development of the Renzo Piano-designed Eighty Seven Park high-rise next door to the Champlain Towers.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Larson, Bloomberg
Napa Quake Seen Costing Up to $4 Billion as Wineries Shut
August 27, 2014 —
Michael B. Marois, Zachary Tracer and Dan Hart – BloombergThe earthquake that struck northern California yesterday will lead to economic losses of as much as $4 billion, fueled by damaged wineries and shuttered businesses that rely on tourists.
Insurers will probably cover about $2.1 billion, according to an estimate from Kinetic Analysis Corp., which projected total losses of about twice that sum. Costs borne by the industry may be limited because many homeowners don’t have earthquake coverage, according to the Insurance Information Institute.
“The main source of claims could well be commercial claims, those coming from wineries and vineyards and other commercial interests,” Robert Hartwig, the institute’s president, said in an interview today. “It will take a while for the business owners to sort this out.”
Mr. Marois may be contacted at mmarois@bloomberg.net; Mr. Tracer may be contacted at ztracer1@bloomberg.net; Mr. Hart may be contacted at dahart@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Michael B. Marois, Zachary Tracer and Dan Hart, Bloomberg