“It Just Didn’t Add Up!”
November 05, 2024 —
Daniel Lund III - LexologyOverturning arbitration awards in court is difficult. One of the few bases for a challenge to an award (under the Federal Arbitration Act, 9 U.S.C. 10(a)(4), as well as most state arbitration laws) is where the arbitrator is alleged to have “exceeded [his/her] powers” afforded the arbitrator by whatever rules and agreements are in place for the arbitration. Obviously, this places a burden on the arbitrator to “color within the lines” when serving as arbitrator and issuing rulings in the case.
“After extensive discovery and a 10-day hearing, the Tribunal rendered a 142-page” award, whereupon the parties both sought to have the arbitrators correct what the parties agreed was an error in the award – increasing the award by $47,710. One of the parties, however, went further, urging that the arbitrators “erroneously included damages for claims related to production revenue” that occurred before a certain date. According to the court, that party was urging that “the Tribunal erred by factoring into its award damages related to Claims 2 and 3, which the Tribunal never substantially addressed.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Part of the Whole: Idaho District Court Holds Economic Loss Rule Bars Tort Claims Related to Water Supply Line that was Part of Home Purchase
October 03, 2022 —
Gus Sara - The Subrogation StrategistIn Safeco Ins. Co. of Ill. v. LSP Prods. Grp., 2022 U.S. Dist. LEXIS 139566, the United States District Court for the District of Idaho (District Court) considered whether the plaintiff’s tort claims against the manufacturer of an allegedly defective toilet water supply line were barred by the economic loss rule. The defendant filed a motion for summary judgment arguing that, since the supply line was a part of the home when the plaintiff’s insureds purchased it, the plaintiff was barred by the economic loss rule from bringing tort claims against the manufacturer. The District Court granted the defendant’s summary judgment motion, ruling that the supply line was a part of the home, which was the subject of the transaction, at the time it was purchased. Thus, the District Court held that the economic loss rule barred the plaintiff’s tort claims.
In 2012, Melissa Norris and Richard Meyers (collectively, the Homeowners) purchased a newly built home in Eagle, Idaho. In 2016, a toilet supply line in one of the bathrooms began leaking, causing water damage to the home as well as to window blinds, an oven and dishwasher. The Homeowners also incurred a loss of rental income. The Homeowners submitted a claim to Safeco Insurance Company (Insurer), their property insurance carrier, who ultimately covered the Homeowners’ losses.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Enerpac Plays Critical Role in Industry-changing Discovery for Long Span Bridges at The University of Nebraska-Lincoln
April 19, 2022 —
EnerpacMENOMONEE FALLS, Wis. (April 18, 2022) – Three years ago when Marc Maguire, assistant professor of construction programs at the University of Nebraska-Lincoln, started investigating a new stranded wire product for bridge girder reinforcing he thought the best strands for bridge construction were the industry standard 7-wire strands.
After running a multitude of analyses, Maguire and student researchers found that 19-wire 1-1/8 in. diameter strands outperform the typical 7-wire 1-1/6 in. diameter strands and allow bridges to reach unprecedented lengths. Further tests conducted by the Durham School of Architectural Engineering and Construction with the help of Enerpac hydraulic tools examined the bond strength, force transfer, and development length of the 19-wire strands.
"Traditionally, 19-wire strands are not often used in the U.S. because they are not widely available and they are much larger than standard strands," said Maguire. "We wanted to show that there was an alternative option to the common 7-wire strand--one that can perform at the same level, if not better."
About Enerpac
Enerpac is a global market leader in high pressure hydraulic tools, controlled force products, portable machining, on-site services and solutions for precise positioning of heavy loads. As a leading innovator with a 110-year legacy, Enerpac has helped move and maintain some of the largest structures on earth. When safety and precision matters, elite professionals in industries such as aerospace, infrastructure, manufacturing, mining, oil & gas and power generation rely on Enerpac for quality tools, services and solutions. For more information, visit www.enerpac.com.
Read the court decisionRead the full story...Reprinted courtesy of
Claims Made Insurance Policies
November 04, 2019 —
David Adelstein - Florida Construction Legal Updates“Claims-made policies are common in the professional liability insurance market. They “differ from traditional ‘occurrence’-based policies primarily based upon the scope of the risk against which they insure.” With claims-made policies, coverage is provided only where the act giving rise to coverage “is discovered and brought to the attention of the insurance company during the period of the policy.” In contrast, coverage is provided under an occurrence-based policy if the act giving rise to coverage “occurred during the period of the policy, regardless of the date a claim is actually made against the insured.” “The essence, then, of a claims-made policy is notice to the carrier within the policy period.”
Crowely Maritime Corp. v. National Union Fire Ins. Co. of Pittsburgh, PA, 2019 WL 3294003 (11thCir. 2019)
The recent Eleventh Circuit Court of Appeal opinion in Crowely Maritime Corp. discussed the distinction between a claims-made insurance policy and an occurrence-based insurance policy. Professional liability policies are generally claims-made policies whereas commercial general liability policies are generally occurrence-based policies. While this opinion does not involve a construction matter, the case did concern the definition of a “claim” in a claims-made policy and whether such claim was timely reported to the insurer within the discovery period / extended reporting period.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
WARN Act Exceptions in Response to COVID-19
April 13, 2020 —
Yvette Davis & Kyle R. DiNicola - Haight Brown & BonesteelCalifornia’s WARN Act requires employers of certain covered establishments to provide 60 days written notice of any mass layoff, relocation, or termination. This notice is required to be given to employees and the Employment Development Department. An employer’s failure to comply with this requirement can result in being held liable for back-pay and value of the cost of any benefits to which the affected employee(s) may have been entitled for up to a maximum of 60 days.
Due to the COVID-19 crisis and emergency circumstances in which many employers now find themselves, the Governor of California has issued Executive Order N-31-20, which temporarily suspends the 60-days advance notice requirement and the provisions that impose liability and penalties on an employer for the duration of the COVID-19 emergency.
Reprinted courtesy of
Yvette Davis, Haight Brown & Bonesteel and
Kyle R. DiNicola, Haight Brown & Bonesteel
Ms. Davis may be contacted at ydavis@hbblaw.com
Mr. DiNicola may be contacted at kdinicola@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: A FACA Fight, a Carbon Pledge and Some Venue on the SCOTUS Menu
November 02, 2020 —
Anthony B. Cavender - Gravel2GavelIn this summary of recent developments in environmental and regulatory law, venues are challenged, standing is upheld, statutory exemption is disputed and more.
THE U.S. SUPREME COURT
Change Must Come from Within … Maryland?
As the new term begins, the Court has agreed to review BP PLC v. Mayor and City Council of Maryland, a decision of the U.S. Court of Appeals for the Fourth Circuit which held that a climate change damages case filed against many energy companies must be heard in the state courts of Maryland and not the federal courts. The petitioners argue that the federal office removal statute authorizes such removal, and the Fourth Circuit’s contrary decision conflicts with rulings from other circuit courts.
THE FEDERAL COURTS
Where Is the Fund in That?
On September 25,2020, in U.S. House of Representatives v. Mnuchin, et al., the U.S. Court of Appeals for the District of Columbia held that the lower court should not have dismissed a lawsuit filed by the U.S. House of Representatives challenging the Executive Branch’s transferal of appropriated funds to the Department of Defense to build a physical barrier along the southern border of the United State. The case is More than $8 billion is at stake, a sum that had been transferred from various federal accounts not involved with building the wall. The appeals court held that the lower court should not have dismissed this lawsuit because the House of Representatives had standing to bring this lawsuit even if the U.S. Senate was not involved with this litigation. Accordingly, the case was returned to the lower court for additional findings, with the appeals court noting that the Constitution’s Appropriation’s Clause serves as an important check on the Executive Branch.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
CDJ’s Year-End Review: The Top 12 CD Topics of 2015
December 30, 2015 —
Beverley BevenFlorez-CDJ STAFFAs a new year begins, Construction Defect Journal has put together the most important issues and topics relating to the construction defect industry in 2015. New cases have arisen to challenge Right to Repair laws and other construction-related claim procedures, some states have made legislative or code changes, as well as other intriguing topics have been discussed in board rooms and over conference calls. We hope you enjoy the look-back at 2015, and we wish you and yours a prosperous 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Courthouse Reporter Series: Louisiana Supreme Court Holds Architect Has No Duty to Safeguard Third Parties Against Injury, Regardless of Knowledge of Dangerous Conditions on the Project
July 31, 2024 —
Stu Richeson - The Dispute ResolverIn Bonilla v. Verges Rome Architects, 2023-00928 (La. 3/22/24); 382 So.3d 62, the Louisiana Supreme Court held because the terms of the agreement between the architect and the public owner did not give the architect responsibility for the means and methods of construction or for safety on the project, the architect did not have a duty to safeguard third parties against injury, regardless of whether the architect may have had knowledge of dangerous conditions on the project.
In Bonilla, the City of New Orleans entered into a contract for the renovation of a building owned by the city. The city also entered into an agreement with Verges Rome Architects (“VRA”) to serve as the project architect. The general contractor on the project subcontracted the demolition work to Meza Services, Inc. (“Meza”).
An employee of Meza was injured while attempting to demolish a “vault” on the project. The vault was a ten-foot by ten-foot cinderblock room with a nine-foot-high concrete slab ceiling located on the second floor of the building. The walls of the vault had been partially demolished when one of the employees of Meza was directed by his supervisor to stand on the ceiling of the vault with a jackhammer to continue the demolition. Shortly after beginning the task, the vault structure collapsed and caused the employee to suffer significant injury.
Read the court decisionRead the full story...Reprinted courtesy of
Stu Richeson, PhelpsMr. Richeson may be contacted at
stuart.richeson@phelps.com