South Adams County Water and Sanitation District Takes Proactive Step to Treat PFAS, Safeguard Water Supplies
November 28, 2022 —
Cameron McWilliam – Brown and CaldwellDENVER, Colo., Nov. 15, 2022 — The South Adams Country Water and Sanitation District (District) is enhancing its water treatment process to meet EPA Health Advisory Levels (HALs) for per- and polyfluoroalkyl substances (PFAS) in drinking water supplies.
Deemed “forever chemicals,” PFAS is a group of human-made chemicals used in many applications, including stain- and water-resistant fabrics and carpeting, cleaning products, paints, and firefighting foams. PFAS are resistant to grease, oil, water, and heat and may enter water supplies from landfills, the use of firefighting foam (e.g., at airports, fire training facilities, petroleum fires, etc.), industrial sites, and wastewater treatment plant discharge.
The District’s water supply, serving over 67,000 residents in Commerce City and parts of unincorporated Adams County, comes primarily from 13 groundwater supply wells. As it continues to meet all federal and state drinking water requirements, the District has been proactively pursuing PFAS reduction strategies since it first discovered a low-level presence in its water supply through voluntary testing in 2018. Upon discovery, the District stopped drawing from its most impacted wells and has been purchasing additional treated water to blend into its supply to reduce PFAS levels along with optimizing use of their existing granular activated carbon treatment system.
“Ever since the District first began voluntarily testing for PFAS, we have been monitoring for these compounds and working to reduce their impact on our customers,” said District Manager Abel Moreno. “The EPA has moved the goalposts, and we are taking steps to reduce the presence of PFAS even further. We are committed to finding long-term, sustainable solutions to offer our community high-quality drinking water.”
To tackle the challenge, the District has hired leading environmental and construction services firm Brown and Caldwell to design a new 18 million gallons per day (MGD) ion exchange (IX) process at its Klein Water Treatment Facility. IX treatment is currently the most effective technology in removing PFAS/PFOA, consisting of a highly porous resin that acts as a powerful magnet to adsorb and hold onto the substances. The new system at the Klein facility will consist of seven IX treatment trains, a 375,000-gallon equalization tank, and six vertical turbine pumps to feed the IX trains from the District’s 13 groundwater supply wells.
Furthermore, nine 5-micron cartridge filters will be installed to remove particulate matter in the water before reaching the IX trains, thus increasing the efficacy of the treatment process.
Scheduled for completion by the end of 2026, the new IX treatment facility will provide a peak combined capacity of 26 MGD.
About South Adams County Water and Sanitation District
The South Adams County Water and Sanitation District is a special district providing water and sanitary sewer service to over 67,000 residents in Commerce City and parts of unincorporated Adams County. For more information about the District, please visit www.sacwsd.org
About Brown and Caldwell
Headquartered in Walnut Creek, California., Brown and Caldwell is a full-service environmental engineering and construction services firm with 52 offices and 1,800 professionals across North America and the Pacific. For 75 years, our creative solutions have helped municipalities, private industry, and government agencies successfully overcome their most challenging water and environmental obstacles. As an employee-owned company, Brown and Caldwell is passionate about exceeding our clients’ expectations and making a difference for our employees, our communities, and our environment. For more information, visit www.brownandcaldwell.com
Read the court decisionRead the full story...Reprinted courtesy of
Nevada Senate Rejects Construction Defect Bill
June 07, 2011 —
CDJ STAFFThe Las Vegas Sun reports that Assembly Bill 401, the construction defect bill, lost in a vote of 9 to 12. The measure extended the time for construction defect suits to be filed, awarded legal costs only to successful plaintiffs, and set a definition of construction defects. Two Democrats joined the Republicans in the Senate in defeating the bill.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects as Occurrences, Better Decided in Law than in Courts
December 09, 2011 —
CDJ STAFFConstruction defect claims are now occurrences for insurance purposes in four states, Arkansas, Colorado, Hawaii, and South Carolina, yet there are still frustrations for commercial general liability policyholders. Business Insurance describes court decisions on whether construction defect claims are covered as “incongruous,” and this drives up coverage and litigation costs. Construction firms often find they are defending themselves on two fronts, both the construction defect claim and also whether their insurance covers it.
Frank Armstrong, the Senior Vice President and National Director of Construction Claims for Willis North America says that the problem starts with the word “occurrence,” as various state courts have different interpretations of the word. “Certain pieces of it don’t fit well, at lest according to some courts in the country, with coverage for construction defect risks.”
Another insurance executive, Julian Ehlich, the Senior Vice President of Claims for Aon Risk Solutions’ construction services group notes that “jurisdictions differ, so policyholders don’t know what they’re going to get.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Coverage for COVID-19? Two N.J. Courts Allow Litigation to Proceed
March 06, 2022 —
Bethany L. Barrese - Saxe Doernberger & Vita, P.C.Courts across the nation have struggled to determine whether insurance policies that provide coverage for “direct physical loss or damage” insure losses stemming from COVID-19. Many courts have been applying an overly stringent pleading standard, inappropriately granting insurers’ motions to dismiss as a result of the insureds’ purported failure to allege that COVID-19 caused damages covered by their policies or because certain exclusions supposedly barred coverage. However, two New Jersey state courts recently decided these issues in favor of the insureds in well-reasoned opinions that give proper deference to procedural pleading standards and substantive insurance coverage law.
A. COVID-19 causes “direct physical loss or damage”
In AC Ocean Walk, LLC v. American Guarantee and Liability Ins. Co., the New Jersey Superior Court held that physical alteration to an insured’s property is not a prerequisite to coverage for losses due to COVID-19. The insured, Ocean Casino, sued multiple insurers for COVID-19 losses, alleging that the virus caused Ocean Casino to shut down and suffer a loss of use of its property. Looking at the language of the policies, the court explained that each policy’s insuring agreement substantially read the same:
“This policy insures against direct physical loss of, or damage caused by, a covered cause of loss to covered property, at an insured location [the casino] … subject to the terms, conditions, and exclusions stated in this policy.”
Read the court decisionRead the full story...Reprinted courtesy of
Bethany L. Barrese, Saxe Doernberger & Vita, P.C.Ms. Barrese may be contacted at
BBarrese@sdvlaw.com
Municipal Ordinances Create Additional Opportunities for the Defense of Construction Defect Claims in Colorado
August 22, 2022 —
Ricky Nolen - Colorado Construction Litigation BlogMunicipal ordinances may provide additional defenses for construction professionals where state law does not provide sufficient protection for Colorado’s builders. Colorado state law can be a minefield of potential liability for construction professionals. Even though the state legislature has stated that it must “recognize that Construction defect laws are an existing policy issue that many developers indicate adds to for-sale costs,” the legislature has remained hesitant to provide any meaningful protection from construction defect claims, resulting in almost unlimited exposure for Colorado’s construction professionals.
Given this background of state laws that do not go far enough in protecting Colorado’s construction professionals, it may be fruitful to review municipal ordinances for new defenses and to temper state law developments applicable to construction defect claims. This is an area of law that is only just developing in Colorado. In fact, the ordinances discussed in this article were only passed in the last two years with many cities only adopting the present versions of the ordinances in 2021. The two model ordinances discussed below are potentially helpful in three ways. The first model ordinance gives construction professionals a right to repair defects in the multi-family construction and in the common interest community context. The second model ordinance is helpful in two ways. First, it establishes that homeowners associations may not unilaterally circumvent ADR protections included in the original declarations for such communities.[1] Second, the ordinance reduces the risk that strict liability will be imposed on a construction professional where a building code is violated.
Read the court decisionRead the full story...Reprinted courtesy of
Ricky Nolen, Higgins, Hopkins, McLain & Roswell, LLCMr. Nolen may be contacted at
nolen@hhmrlaw.com
Apartment Boom in Denver a Shortcut Around Condo Construction Defect Suits?
September 24, 2013 —
CDJ STAFFFor every condo currently being built in Denver, there are 40 apartment units. And there are some who think that this is being done to evade construction defect lawsuits. At issue is the statute of limitations for construction defects. Under Colorado law, condominium buyers have six years after the completion of constrution to sue for construction defects, unless the defect isn’t discovered until the fifth or six year, in which case they are given until the eighth year. But what if someone built an apartment building, rented out the units for six years, and then converted the whole thing to condominiums?
Some think that the construction defect clock would be reset. Amie Mayhew, the CEO of the Colorado Association of Home Builders noted that if this is the case, “you’d be back at square one.” But Doug Benson, a construction defect attorney, thinks that if a builder did this, and didn’t make any further construction, no one would be able to sue for construction defects, even if the condo owners found them. Mr. Benson, who represents homeowners, said that “they’re apartment homes and that’s just to avoid liability.”
Mike Gifford, the president of the Associated General Contractors of Colorado, noted that insurance companies were already wary of apartment complexes, fearing that they would be turned into condos. Whatever the cause, Denver seems to have a shortage of condos. But, they’re going to have a lot of apartments available.
Read the court decisionRead the full story...Reprinted courtesy of
Claims Litigated Under Government Claims Act Must “Fairly Reflect” Factual Claims Made in Underlying Government Claim
November 27, 2023 —
Garret Murai - California Construction Law BlogUnlike horseshoes and hand grenades, close sometimes isn’t close enough.
In the next case, Hernandez v. City of Stockton, 90 Cal.App.5th 1222 (2023), the Third District Court of appeal found that a pedestrian who sued a public entity for personal injuries caused by an “uplifted sidewalk” was barred from pursuing his claim when it was revealed that he had in fact injured himself by falling into a hole left by an “empty tree well” (i.e., a tree well that did not contain a tree”). According to the Court, the pedestrian’s claim was barred because the factual basis for recovery asserted in his complaint was not “fairly reflected” in his government claim.
The Hernandez Case
In April 2018, pedestrian Manual Sanchez Hernandez injured himself while walking on a public sidewalk in Stockton, California. He submitted a government claim with the City of Stockton claiming that his injuries, which included injuries to his knee, hands and back, was caused by a dangerous condition on public property. In his government claim, Hernandez alleged that he tripped on an “uplifted sidewalk” at or near 230 E. Charter Way in Stockton, California and that his injuries were due because the City “negligently and recklessly designed, maintained and operated the subject property so as to cause [his] injuries.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
There Are Consequences to Executed Documents Such as the Accord and Satisfaction Defense
October 01, 2024 —
David Adelstein - Florida Construction Legal UpdatesA federal government contractor in Jackson Construction Co., Inc. v. U.S., 62 Fed.Cl. 84 (Fed.Cl. 2024) sought delay damages against the government. It lost. The reason for the loss is a crucial reminder that documents parties sign ALWAYS matter. ALWAYS!!
In Jackson Construction Co., the contractor’s delay claim was premised on relocating a waterline. The contractor, however, received additional money for relocating the waterline, but no additional time, and this was memorialized in a modification to the contract (i.e., a change order). In executing the modification for the additional work, the contractor did NOT reserve rights for time or money. Indeed, the modification reflected that the monetary adjustment constitutes full compensation for the additional work including delay, namely:
The contract period of performance remains the same. It is further understood and agreed that this adjustment constitutes compensation in full on behalf of the contractor and his subcontractors and suppliers for all costs and markup directly or indirectly, including extended overhead, attributable to the change order, for all delays related thereto, and for performance of the change within the time frame stated.
Jackson Construction Co., supra, at 90.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com