COVID-19 Business Interruption Claims Four Years Later: What Have We Learned?
September 23, 2024 —
Patrick McKnight - The Dispute ResolverFour and half years ago the COVID-19 pandemic spread around the globe, bringing with it interesting, but challenging, legal problems for construction attorneys. Construction projects ground to a halt. Ever-changing guidance from authorities ranging from the U.S. Department of Labor to local health authorities resulted in a web of evolving obligations for general contractors and subs alike. One of the most closely watched legal questions was the wave of business interruption claims filed by plaintiffs, many of whom owned businesses impacted by government shutdowns. During the opening months of the pandemic, I
noted that hundreds of business interruption claims had been filed by insureds across the country. At that time, the only thing certain was that although the outcome remained unknown, virus exclusions were likely to become more likely in the future. Needless to say, much has happened since early 2020.
What does the data say about the outcome of business interruption claims?
In sum, plaintiffs have had an uphill battle. A helpful resource for analyzing the outcome of business interruption suits is the
Covid Coverage Litigation Tracker (“Tracker”), an insurance law analytics tool offered by Penn Carey Law of the University of Pennsylvania. According to its website, “[t]he Covid Coverage Litigation Tracker is a multi-sourced database and dashboard through which to view the unfolding insurance litigation arising out of the pandemic in federal and state courts. Widely cited in briefs, judicial opinions, and the press, the tracker also serves as a proof of concept for new methods to identify, track, and understand emerging case congregations in real time.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
Enerpac Plays Critical Role in Industry-changing Discovery for Long Span Bridges at The University of Nebraska-Lincoln
April 19, 2022 —
EnerpacMENOMONEE FALLS, Wis. (April 18, 2022) – Three years ago when Marc Maguire, assistant professor of construction programs at the University of Nebraska-Lincoln, started investigating a new stranded wire product for bridge girder reinforcing he thought the best strands for bridge construction were the industry standard 7-wire strands.
After running a multitude of analyses, Maguire and student researchers found that 19-wire 1-1/8 in. diameter strands outperform the typical 7-wire 1-1/6 in. diameter strands and allow bridges to reach unprecedented lengths. Further tests conducted by the Durham School of Architectural Engineering and Construction with the help of Enerpac hydraulic tools examined the bond strength, force transfer, and development length of the 19-wire strands.
"Traditionally, 19-wire strands are not often used in the U.S. because they are not widely available and they are much larger than standard strands," said Maguire. "We wanted to show that there was an alternative option to the common 7-wire strand--one that can perform at the same level, if not better."
About Enerpac
Enerpac is a global market leader in high pressure hydraulic tools, controlled force products, portable machining, on-site services and solutions for precise positioning of heavy loads. As a leading innovator with a 110-year legacy, Enerpac has helped move and maintain some of the largest structures on earth. When safety and precision matters, elite professionals in industries such as aerospace, infrastructure, manufacturing, mining, oil & gas and power generation rely on Enerpac for quality tools, services and solutions. For more information, visit www.enerpac.com.
Read the court decisionRead the full story...Reprinted courtesy of
US-Mexico Border Wall Bids Include Tourist Attraction, Solar Panels
April 05, 2017 —
Engineering News-RecordSAN DIEGO (AP) — Tuesday was the deadline for companies to propose designs for President Donald Trump's border wall with Mexico . U.S. Customs and Border Protection will ask several of the bidders to build prototypes in San Diego . The government won't identify companies until contracts are awarded around June 1 — and even then, only the winners — but some bidders released plans on their own.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
Chimney Collapses at South African Utility’s Unfinished $13 Billion Power Plant
November 21, 2022 —
Paul Burkhardt - BloombergSouth Africa’s newest coal-fired power plant, which has been under construction since 2008 and will cost an estimated 232 billion rand ($12.7 billion), shut one of its six generating units after a duct collapsed.
The unit at the Kusile plant could remain offline “for a few months” although a clearer estimate will be known over coming weeks, state-owned utility Eskom Holdings SOC Ltd. said in a statement late Wednesday. The outage comes as the country endures record blackouts -- locally known as loadshedding.
The duct appeared to have sheared off from the unit’s main structure, a photo posted on Twitter by Anton Eberhard, a professor at the University of Cape Town’s Graduate School of Business, showed.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Burkhardt, Bloomberg
I’m Sorry Ms. Jackson, I [Sovereign Immunity] am For Real
June 08, 2020 —
Greggory Jacobs - Florida Construction Law News BlogThe Supreme Court of Florida issued its opinion in Florida Highway Patrol v. Jackson, 2020 Fla. LEXIS 108 (Fla. Jan 23, 2020), which answered the following certified question of great public importance:
Does rule 9.130 [(A)(3)(C)(XI)] permit an appeal of a non-final order denying immunity if the record shows that the defendant is entitled to immunity as a matter of law but the trial court did not explicitly preclude it as a defense?
The Court’s answer to this question was “no.” But this opinion stands for much more than just a negative answer to a certified question. Indeed, this opinion has significant implications upon procedural and substantive areas of construction law, which may affect agents of the state of Florida, including Construction Engineering and Inspection professionals and consultants (“CEI”).
Procedurally, the Court recognizes that Fla. R. App. P. 9.130 insufficiently protects the public and governmental interests as “it leaves too great a risk that erroneous denials of operational sovereign immunity will go unreviewed until it is too late.” Id. at * 19. By extension of this risk, the Jackson Court announced that “courts should determine entitlement to sovereign immunity as early as the record permits.” Id. at * 18. In fact, on that basis, courts can address a motion for summary judgment asserting entitlement to sovereign immunity even if there are outstanding disputes as to, say, the existence of a duty of care. Id. at 17-18. Accordingly, and in an effort to remedy the risk of erroneous denials going unreviewed until it is too late, the Court amended Fla. R. App. P. 9.130 to expand appellate review of nonfinal orders denying sovereign immunity. Jackson, 2020 Fla. LEXIS 108 at * 19; In re Amendments to Fla. Rule of Appellate Procedure 9.130, No. SC19-1734 (Fla. Jan. 23, 2020). The new form of Fla. R. App. P. 9.130 cements the policy mentioned above because it allows an appeal of a nonfinal order denying a motion for summary judgment due to entitlement to sovereign immunity. Meanwhile, under the old rule, the order was only appealable if the trial court order determined – as a matter of law – that a party was not entitled to sovereign immunity. As such, the new rule focuses on what was argued in the motion as opposed to what was written in the order.
Read the court decisionRead the full story...Reprinted courtesy of
Greggory Jacobs, Cole, Scott & Kissane, P.A.Mr. Jacobs may be contacted at
greggory.jacobs@csklegal.com
Atlantic City Faces Downward Spiral With Revel’s Demise
August 13, 2014 —
Terrence Dopp – BloombergThe shuttering next month of Revel, the $2.6 billion hotel and casino that was meant to usher in a new era of opulence in Atlantic City when it opened in 2012, is set to quicken the seaside community’s downward spiral.
Five years after the longest recession since the 1930s, hotel rooms sit vacant and revenue keeps falling in what was once the second-largest U.S. casino market. New Jersey Governor Chris Christie’s turnaround plan for the municipality, begun in 2011 and hinged on Revel’s success, hasn’t delivered, prompting Moody’s Investors Service to cut the city’s $245 million of general-obligation debt to junk last month.
Read the court decisionRead the full story...Reprinted courtesy of
Terrence Dopp, BloombergMr Dopp may be contacted at
tdopp@bloomberg.net
US Appeals Court Halts OSHA Vaccine Mandate, Unclear How Long
November 15, 2021 —
Debra K. Rubin & Jeff Yoders - Engineering News-RecordThe U.S. Court of Appeals in New Orleans on Nov. 6 stayed the Biden administration's requirement that workers at U.S. companies with at least 100 employees be vaccinated against COVID-19 or be tested weekly, citing potential "grave statutory and constitutional" issues raised by opponents of the US Occupational Safety and Health Administration's emergency temporary standard announced on Nov. 4.
Reprinted courtesy of
Debra K. Rubin, Engineering News-Record and
Jeff Yoders, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Mr. Yoders may be contacted at yodersj@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp Obtain Summary Judgment in Favor of Residential Property Owners
December 13, 2022 —
Gregory S. Pennington & Emily A. Velcamp - Traub LiebermanTraub Lieberman Partner Gregory S. Pennington and Associate Emily A. Velcamp obtained summary judgment in favor of their clients, owners of a residential property [the “Owners” or “Defendants”] used as a short-term rental in Beach Haven, New Jersey. Plaintiff alleged injuries resulting from a fall into an open water meter pit, located in the public sidewalk abutting the Owners’ property during the time within which the property was rented to plaintiff and his family. According to plaintiff, defendants breached their duty owed to him, relying on a Borough of Beach Haven Ordinance, thereby allowing the water meter pit to be raised in an unsafe manner, which resulted in plaintiff’s fall and subsequent injuries.
After the Court denied defendants’ initial Motion for Summary Judgment on the grounds that issues of material fact existed regarding defendants’ duty and the alleged breach of that duty, a Motion for Reconsideration was filed. Mr. Pennington and Ms. Velcamp argued that their clients, as residential landowners, owed no duty of care to plaintiff for the raised condition of the water meter pit lid, located in the abutting sidewalk, as they did not cause or contribute to the alleged condition. Defendants further argued that even if a duty of care existed, no breach occurred given the lack of notice to defendants, either actual or constructive. Plaintiff attempted to argue that defendants had constructive notice of the lid’s raised condition, relying on his expert report and the fact that defendants had 3.5 months from the date the property was purchased, to the date of the subject accident to discover the lid’s raised condition. Mr. Pennington and Ms. Velcamp successfully argued that despite plaintiff’s allegations and the findings contained in plaintiff’s expert report, authored 2 months after the alleged accident, there was still no credible, material evidence to say how long the water meter pit lid was in that raised condition to allow defendants a reasonable time to discover it, remedy it, or report it to the Borough.
Reprinted courtesy of
Gregory S. Pennington, Traub Lieberman and
Emily A. Velcamp, Traub Lieberman
Mr. Pennington may be contacted at gpennington@tlsslaw.com
Ms. Velcamp may be contacted at evelcamp@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of