Ruling Dealing with Constructive Changes, Constructive Suspension, and the Implied Covenant of Good Faith and Fair Dealing
January 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA dispute pending in the Armed Services Board of Contract Appeals (ASBCA) dealt with interesting legal issues on a motion to dismiss. See Appeals of McCarthy Hitt-Next NGA West JV, ASBCA No. 63571, 2023 WL 9179193 (ASBCA 2023). The dispute involves a contractor passing through subcontractor claims due to impacts caused by the COVID-19 pandemic and the government’s response to the pandemic. More particularly, the claim centers on the premise that the government “failed to work with [the contractor] in good faith to develop a collaborative and cooperative approach to manage and mitigate the impacts and delays arising from the COVID-19 pandemic.” See Appeals of McCarthy Hitt.
The contractor (again, submitting pass through claims from subcontractors) claimed: (a) constructive changes to the contract entitling it to an equitable adjustment under the Changes clause of Federal Acquisition Regulation (F.A.R.) 52.243-4; (b) construction suspensions of the contractor’s work entitling it to an equitable adjustment under the Suspensions of Work clause of F.A.R. 52-242-14; and (c) the government breached the implied covenant of good faith and fair dealing. Each of these legal issues and theories will be discussed below because they are need-to-know legal issues. Keep these legal issues in mind, and the ASBCA’s ruling on the motion to dismiss as its analysis may demonstrate fruitful in other applications.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Rams Owner Stan Kroenke Debuts His $5.5 Billion Dream Stadium
September 14, 2020 —
Christopher Palmeri - BloombergThe first thing you notice that’s different about SoFi Stadium is that you can walk from the parking lot almost directly into the fifth level of the arena.
There’s no passing through gate after gate or ascending endless circular walkways. Construction workers dug up over 7 million cubic yards of dirt to build an arena that sits 100 feet (30 meters) below grade.
It’s one of the many features that make SoFi, the National Football League’s biggest stadium, surprisingly visitor-friendly. Not that fans will be able to experience it just yet. When the stadium debuts Sunday with the first game of the Los Angeles Rams’ season, it will be spectator-free -- the result of pandemic-spurred restrictions on gatherings. But it will still be a spectacle.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Palmeri, Bloomberg
Following Mishaps, D.C. Metro Presses on With Repairs
February 23, 2017 —
Jim Parsons - Engineering News-RecordAn aggressive effort to overhaul the aging Metro system in Washington, D.C., is producing results as it nears the one-year mark, with more than 28,000 cross-ties and nearly two miles of grout pads now replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Connecticut Supreme Court to Review Several Issues in Asbestos Coverage Case
November 08, 2017 —
Ciaran Way & Robert F. Walsh – White and Williams LLPOn October 18, 2017, in R.T. Vanderbilt Company v. Hartford Accident & Indemnity Company, the Connecticut Supreme Court certified four issues for appeal, which relate to trigger, allocation, pollution exclusions, and the occupational disease exclusion in the context of asbestos bodily injury claims. This post identifies the issues the Connecticut Supreme Court will decide on appeal and sets forth the Appellate Court’s ruling on each issue.
Issue 1: Whether a “continuous trigger” theory of coverage applies to asbestos-related disease claims and whether expert medical testimony on the timing of injury should be precluded
The Appellate Court applied a continuous trigger, and found that the trial court properly excluded testimony from medical experts the insurers had proffered to prove that the asbestos disease process did not support a continuous trigger.
Reprinted courtesy of
Ciaran Way, White and Williams LLP and
Robert Walsh, White and Williams LLP
Ms. Way may be contacted at wayc@whiteandwilliams.com
Mr. Walsh may be contacted at walshr@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Construction-Defects Reform Law Attempt Expected in 2015
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to the Denver Post, another attempt to change Colorado’s construction defect laws to spur condo development is likely this term. Reform supporters are encouraged by the city of Lakewood’s ordinance, Denver Post reported: “"A patchwork around the state on this issue is not the way to go," Rep. Brian DelGrosso, R-Loveland, said. "Hopefully, the Lakewood measure will spur the conversation this year."
Lakewood’s “measure gives builders a ‘right to repair’ faulty work before facing legal action and requires that a majority of home owners approve legal action before it is taken.”
However, “Nancy Stockton, president of the homeowners association at the Vallagio at Inverness in Arapahoe County, said following Lakewood's example statewide would only make it that much harder to hold builders accountable for the quality of their work.”
Read the court decisionRead the full story...Reprinted courtesy of
Ahead of the Storm: Preparing for Irma
September 07, 2017 —
Stephen H. Reisman – Peckar & Abramson, P.C.While Hurricane Irma boils in the Atlantic and seems to be aiming towards Florida, storm preparations are well underway. As contractors are busy organizing efforts to secure their job sites, we at Peckar & Abramson offer some quick reminders that may prove helpful when the dust finally settles:
- Review your contracts, particularly the force majeure provisions, and be sure to comply with applicable notice requirements.
- Even if not expressly required at this point in time, consider providing written notice to project owners that their projects are being prepared for a potential hurricane or tropical storm and that productivity and the progress of the work will be affected, with the actual time and cost impact to be determined after the event.
- Consult your hurricane plan (which is often a contract exhibit) and confirm compliance with all specified safety, security and protection measures.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen H. Reisman, Peckar & Abramson, P.C.Mr. Reisman may be contacted at
sreisman@pecklaw.com
Embracing Generative Risk Mitigation in Construction
February 12, 2024 —
Georgia Stillwell - Construction ExecutiveProject delays have long plagued the construction industry, with risk often identified as the primary culprit. However, finding effective solutions to mitigate risk on complex projects has remained daunting. Traditional methods for simulating risk primarily focus on extending project timelines, overlooking the diverse range of opportunities available for risk mitigation. With the construction industry’s digital transformation, generative methodologies have emerged to handle complex decision-making in uncertain situations. This article aims to shed light on the limitations of existing risk modeling and introduce a novel approach known as generative risk mitigation to enhance decision-making under deep uncertainty.
According to McKinsey, 98% of megaprojects experience cost overruns exceeding 30%. Project delays have become so pervasive that the industry has grown accustomed to them. For example, in 2022, the UK government issued ‘
The Green Book,’ which requires contingency funds in projects, such as a 44% contingency budget for standard civil projects. This implies that for a $100 million project, you should allocate $144 million to manage expected risks. There is no denying significant academic literature on the root cause of these delays: it is ‘risk,’ and there is an entire industry based on it.
Conversations with project directors and risk experts reveal the same issue, different project. And that issue is that we cannot easily forecast risk, qualify the impacts or fully understand the opportunities that exist to mitigate risks and make timely decisions. A method that will finally help us overcome this has emerged within the industry.
Reprinted courtesy of
Georgia Stillwell, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
A Brief Discussion – Liquidating Agreements
June 27, 2022 —
Gerard J. Onorata - Peckar & Abramson, P.C.During a construction project, it is not uncommon for disputes to arise between a general contractor and a subcontractor. Frequently, these disputes involve claims for extra work and delay damages that can be attributed to the owner of the project due to deficient design or unforeseen conditions. When these occasions arise, the parties can often resolve these claims without the need for litigation or arbitration by entering into a “liquidating agreement.”
What is a Liquidating Agreement?
Because there is no direct contractual relationship between a subcontractor and an owner, there does not exist a legal basis for a subcontractor to assert a breach of contract claim against a project owner. In legal parlance, this is known as “lack of contractual privity.” A liquidating agreement bridges this contractual gap and allows a subcontractor to pass its claim against the owner through the general contractor. Essentially, with a liquidating agreement, the general contractor acts as a conduit for passing through the subcontractor’s claim.
Read the court decisionRead the full story...Reprinted courtesy of
Gerard J. Onorata, Peckar & Abramson, P.C.Mr. Onorata may be contacted at
gonorata@pecklaw.com