Property Owner Found Liable for Injuries to Worker of Unlicensed Contractor, Again
September 17, 2018 —
Garret Murai - California Construction Law BlogIt’s not like we didn’t warn you.
In Jones v. Sorenson, Case No. C084870 (August 2, 2018), homeowner Danita Sorenson discovered to her chagrin that she had unwittingly become the employer of Mary Jones, who had been hired by Odette Miranda doing business as Designs by Leo to trim some trees, and was liable for Jones’ injuries when Jones fell off a ladder provided by Miranda. “How can this be?” you might ask. The reason, as it turns out, is simple.
Miranda was required to hold a Class D-49 Tree Service Contractor’s license in order to contract with Sorenson to trim her trees, and because Miranda did not hold that license (or, for that matter, any contractor’s license), Sorenson automatically was deemed the employer of Jones under Labor Code Section 2750.5 and, therefore, liable for her injuries.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Towards Paperless Construction: PaperLight
June 02, 2016 —
Aarni Heiskanen – AEC BusinessI just toured the newly built headquarters of a financial corporation. Our guide, a M&A specialist, boasted that they have completely removed paper from their offices. Could paperless construction become feasible any time soon? PaperLight is a portable smart board that could replace paper drawings on many occasions.
Rollout, Inc., the developer of PaperLight, says that 90% of contractors still use paper plans. AEC firms spend, on average, $1600 per employee on printing annually. Over 37 million construction drawings are printed every year. Finding a usable solution that reduces these numbers makes economic sense. Even more so if you consider all the costs of errors that result from using outdated paper drawings.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aarni@aepartners.fi
Real Estate & Construction News Roundup (10/11/23) – Millennials Struggle Finding Homes, Additional CHIPS Act Funding Available, and the Supreme Court Takes up Hotel Lawsuit Case
November 16, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, EV charging stations become more prevalent at commercial locations, home ownership becomes more difficult for younger Americans, Macy’s announces plans to build additional stores within strip malls, and more!
- Due to several factors including overpriced housing and student debt, millennials will not have the same level of home ownership as previous generations. (Jordan Rosenfeld, Yahoo)
- With the U.S. being short about 3.8 million housing units according Freddie Mac, 3-D printing may prove to be the answer while also being cost effective and environmentally friendly. (Lesley Stahl, Aliza Chasan, Shari Finkelstein and Collette Richards, CBS)
- The Department Commerce of announced a new initiative to funnel $500 million in CHIPS Act funding to projects with capital investments below $300 million that support the construction, expansion or modernization of semiconductor-related facilities in the U.S. (Sebastian Obando, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team, Pillsbury
Minnesota Addresses How Its Construction Statute of Repose Applies to Condominiums
April 27, 2020 —
William L. Doerler - The Subrogation StrategistCourts often struggle with the question of when the statute of repose starts to run for construction projects that involve multiple buildings or phases. In Village Lofts at St. Anthony Falls Ass’n v. Housing Partners III-Lofts, LLC, 937 N.W.2d 430 (Minn. 2020) (Village Lofts), the Supreme Court of Minnesota addressed how Minnesota’s 10-year statute of repose, Minn. Stat. § 541.051, applies to claims arising from the construction of a condominium complex. The court held that the statute of repose begins to run at different times for: a) statutory residential warranty claims brought pursuant to Minn. Stat. §§ 327A.01 to 327A.08, et. seq.; and b) common law claims arising out of the defective and unsafe condition of the condominium buildings.
As stated in Village Lofts, Housing Partners III-Lofts, LLC (Housing Partners) developed the Village Lofts at St. Anthony Falls, a condominium complex consisting of Building A and Building B. Housing Partners retained Kraus-Anderson Construction Company (Kraus-Anderson) as the general contractor for Building A. Kraus-Anderson retained Elness Sweeney Graham Architects, Inc. (ESG), Doody Mechanical, Inc. (Doody) and Kenneth S. Kendle, P.E. (Kendle) to work on Building A. In September 2002, the City of Minneapolis (City) issued a partial certificate of occupancy (CO) for Building A, including the building’s public spaces. On October 4, 2002, Housing Partners filed the declaration creating the Village Lofts at St. Anthony Falls condominium, to be operated by Village Lofts at St. Anthony Association (Village Lofts Association). On October 10, 2002, Housing Partners sold the first unit in Building A and in November of 2003, the City issued a CO for the entire building, excluding two units.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Additional Insured Secures Defense Under Subcontractor's Policy
October 14, 2013 —
Tred Eyerly — Insurance Law HawaiiThe court determined there were sufficient allegations in the underlying complaint and third party complaints to raise a duty to defend for the additional insured. Ill. Emcasco Ins. Co. v. Waukegan Steel Sales, 2013 Ill. App. LEXIS 624 (Ill. Ct. App. Sept. 13, 2013).
Waukegan was named as an additional insured under subcontractor I-MAXX Metalworks, Inc.'s policy with Emcasco. An employee of I-MAXX, John Walls, was injured on the job site and sued Waukegan. The complaint alleged Waukegan was negligent in failing to property manage, operate and maintain the premises.
I-MAXX had a policy with Emcasco which named Waukegan as an additional insured. The coverage was limited, however, to the additional insured's vicarious liability as a result of the insured's conduct.
Emcasco refused to defend Waukegan because the allegations of direct negligence against Waukegan were excluded by the vicariously liability provision.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Mandatory Arbitration Isn’t All Bad, if. . .
August 13, 2019 —
Christopher G. Hill - Construction Law MusingsIn the past week or so mandatory arbitration has been all the rage. From those that argue that arbitration is becoming more burdensome than litigation, to my friend and fellow construction attorney Scott Wolfe who gives great advice on how to make arbitration worth it again. You can place me in the camp of those that think that mandatory arbitration clauses of the type typically found in contracts can add a layer of expense that can be unnecessary.
However, if an arbitration clause is carefully drafted, and properly used, these clauses an be helpful in assuring that the streamlining effect for which arbitration was created actually occurs. Because the contract is king in Virginia, these provisions can essentially create the rule of civil procedure used to resolve any dispute relating to the project.
Anything from the number and method of appointing the arbitrators, to the ability to use attorneys, to the time between notice and arbitration hearing and whether mediation is a requirement, to the documents and other pre-arbitration exchanges can and should be specifically outlined. The construction contract can also state who decides between court or arbitration. This can be one party or both. The possibilities are almost endless.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
New York Court Permits Asbestos Claimants to Proceed Against Insurers with Buyout Agreements
December 06, 2021 —
Patricia B. Santelle & Frank J. Perch, III - White and Williams LLPA recent New York federal district court decision addresses a number of issues in the context of asbestos coverage involving an insolvent insured, holding that policy buyout agreements between the insured and its insurers did not bar actions by certain tort judgment creditors against some of the settling insurers, and further finding that such agreements can constitute fraudulent conveyances, especially where the proceeds of the settlement are not reserved for payment of insured claims.
In the litigation pending in the Western District of New York (Mineweaser v. One Beacon Insurance Company, et al., No. 14-CV-0585A), certain asbestos plaintiffs sought recovery from excess insurers for judgments obtained against an insolvent asbestos supplier (Hedman Resources, formerly known as Hedman Mines), which ceased operations in 2007 due to insolvency. Hedman had at one time been a subsidiary of Gulf & Western. As of 2009-2011, the excess insurers of Gulf & Western were advised of exhaustion of primary insurance as well as Hedman’s insolvency.
Reprinted courtesy of
Patricia B. Santelle, White and Williams LLP and
Frank J. Perch, III, White and Williams LLP
Ms. Santelle may be contacted at santellep@whiteandwilliams.com
Mr. Perch may be contacted at perchf@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Teaming Agreements- A Contract to Pursue a Solicitation and Negotiate
November 23, 2020 —
David Adelstein - Florida Construction Legal UpdatesTeaming agreements are practical and useful agreements on public projects where a prime contractor teams with a subcontractor for purposes of submitting a bid or proposal in response to a solicitation. The prime contractor and subcontractor work together to pursue that solicitation and have the government award the contract to the prime contractor. The teaming agreement allows for information to be confidentially shared (estimating and pricing, construction methodologies, systems, and suggestions, value engineering, etc.) where the subcontractor agrees that it will only pursue the solicitation with the prime contractor. In other words, the subcontractor ideally is not going to submit pricing to another prime contractor proposing or bidding on the same project and is not going to share information the prime contractor has furnished to it. Likewise, the prime contractor is not going to use the subcontractor’s information for purposes of finding another subcontractor at a lower price and is agreeing to use its good faith efforts or best attempts to enter into a subcontract with the subcontractor if it is awarded the project. This is all memorialized in the teaming agreement.
The potential problem lies with language that requires the parties to use their good faith efforts or best attempts to enter into a subcontract if the project is awarded to the prime contractor. In essence, this can become a disfavored “agreement to agree” to a future contract that could allow either party to create an argument to back out of the deal under the auspice that they could not come to terms with the subcontract.
Read the court decisionRead the full story...Reprinted courtesy of