CDJ’s #7 Topic of the Year: The Las Vegas Harmon Hotel Year-Long Demolition & Trial Begins
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFThe 26-story tower in MGM’s $9 billion Las Vegas, Nevada CityCenter project, is being demolished piece by piece after a structural engineer reported that an earthquake of 7.7 could bring it down. While litigation began as early as 2010, the trial didn’t begin until October of 2014, and expectation is it will last through almost all of 2015 as well, according to Carri Geer Thevenot of the Las Vegas Review-Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Verdict In Favor Of Insured Homeowner Reversed For Improper Jury Instructions
October 23, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court reversed the jury verdict in favor of the homeowners based upon improper instructions purporting to impose a duty to adjust the claim and how to construe a contract. Citizens Prop. Ins. Corp. v Mendoza, 2018 Fla. App. LEXIS 9497 (Fla. Ct. App. July 5, 2018).
The insureds incurred water damage to their home caused by a water heater leak. After a claim was filed, the insurer sent an adjuster to investigate the claim. The insurer denied the claim due to an exclusion for constant or repeated seepage or leakage.
At trial, the insurer offered testimony that the leak was a continued and repeated seepage of water over a long period of time, which was excluded under the policy, and not a sudden and accidental discharge of water, which would have been covered.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Depreciation of Labor in Calculating Actual Cash Value Against Public Policy
February 16, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe insurer's depreciation of labor in the calculation of actual cash value was found to be against Arkansas public policy. Shelter Mut. Ins. Co. v. Goodner, 2015 Ark. LEXIS 460 (Ark. Dec. 10, 2015).
Shelter Mutual's policy provided that it would pay the insured "the actual cash value of all the damaged parts of the covered property." "Actual cash value" was defined as "total restoration cost less depreciation." The policy explained, "When calculating depreciation, we will include the depreciation of the materials, the labor, and the tax attributable to each party which must be replaced to allow for replacement of the damaged part, whether or not that part is damaged."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Former NJ Army Base $2B Makeover is 'Buzzsaw' of Activity
June 14, 2021 —
Tom Stabile - Engineering News-RecordTake a developed property the size of New York City’s Central Park with 5 million sq ft of building area, program in new construction or renovation over 20 years and across three dozen parcels for 1,600 housing units, 300,000 sq ft of civic or government space, 500,000 sq ft for retail and 2 million sq ft of offices, and you have a pretty ambitious undertaking. The $2-billion effort to redevelop Fort Monmouth, a decommissioned former U.S. Army base in the thick of New Jersey’s suburban sprawl, is all kinds of ambitious.
Reprinted courtesy of
Tom Stabile, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Dump Site Provider Has Valid Little Miller Act Claim
October 19, 2020 —
Christopher G. Hill - Construction Law MusingsYou may have thought that a Virginia “Little Miller Act” bond claim, like a mechanic’s lien, could only be brought by those that provide materials and labor incorporated into the construction project. If you did, you aren’t alone.
In fact, Safeco Insurance Co. of America, a surety, made exactly the above argument in Yard Works LLC v. GroundDown Constructors LLC. In that case, a debris hauling company failed to pay Yard Works, the company that provided the dumping site for the debris. Yard Works sued pursuant to the Little Miller Act to get paid. In response, the surety sought to have the claim against the payment bond dismissed and argued that because Yard Works did not actually improve the property or provide improvements and that Yard Works only passively provided a dump site, Yard Works could not claim under the payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
General Indemnity Agreement Can Come Back to Bite You
October 21, 2019 —
Christopher G. Hill - Construction Law MusingsI talk about payment bonds often here at Construction Law Musings. I talk a bit less about performance bonds and even less about the General Indemnity Agreements (GIA) that are signed by companies and their principals as part of the agreement between a construction company and its bonding company for the provision of these bonds. However, this does not mean that these GIA’s are not important. In fact, these are the agreements that allow a bonding provider to recoup any money paid out pursuant to either a payment or performance bond.
A 2018 case illustrates their importance. In Allegheny Cas. Co. v. River City Roofing, LLC, the Court considered a claim by Allegheny seeking both specific performance of the collateral agreement and reimbursement of certain expenses and investigative costs expended by Allegheny pursuant to its performance bond. Allegheny sought to be reimbursed for certain payments for siding work, investigative costs, and costs spent enforcing the GIA. Allegheny further sought to force the defendants to post sufficient collateral. To do so, Allegheny sued in the Eastern District of Virginia and then moved for summary judgment stating that the GAI uneuivocally required such a result due to the good faith payment for the siding work and the plain language of the GIA.
In response, the Defendants, River City Roofing and its principals that had personally guaranteed the indemnity, argued that the GIA did not apply to the siding work because only the roofing contract was subject to the performance bond and that any bond claims for which collateral was demanded were inchoate and therefore not proper for specific performance.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Substituting Materials and Failure to Comply with Contractual Requirements
November 19, 2021 —
David Adelstein - Florida Construction Legal UpdatesIt is important to remember that if you are going to substitute materials from those specified, you need to make sure there is proper approval in doing so–make sure to comply with the contractual requirements to substitute materials. Otherwise, you could be in a situation where you are contractually required to remove the installed substituted materials and replace with the correct specified materials. This is not the situation you want to find yourself in because this is oftentimes a costly endeavor. This was the situation in Appeal-of-Sauer, Inc., discussed below, on a federal project. The best thing that you can do is comply with the contractual requirements if you want to substitute materials. If you are in the situation where it is too late, i.e., you already installed incorrect materials, you want to demonstrate the substituted materials are functionally equivalent to the specified materials and/or come up with an engineering solution, as required, that could be less costly then ripping out the installed material and replacing with the correct material. Even doing so, however, is not a “get out of jail free card” and does not necessarily mean there is not a strong basis to require you to install the correct specified material.
In Appeal of- Sauer, Inc., ASBCA 61847, 2021 WL 4888192 (ASBCA September 29, 2021), a federal project’s engineering requirements required cast iron piping for the above ground sanitary system. However, the prime contractor installed PVC piping instead of cast iron piping. The prime contractor believed it had the appropriate approval through its submittal. The government, through its contracting officer, directed the prime contractor to remove installed PVC piping to replace with cast iron. The government did not believe PVC piping was the functional equivalent of cast iron piping for the above ground sanitary system due to its concern with the noise level of waste materials flowing through the piping. The prime contractor submitted a claim for its removal and replacement costs which was denied by the contracting officer. On appeal with the Armed Services Board of Contract Appeals, the Board agreed with the contracting officer explaining: “While we agree that a design change could be approved by the designer of record and brought to the attention of the government before being incorporated into the design documents, the [prime contractor’s] task order required that such a design change meet the minimum requirements of the solicitation and accepted proposal. The plumbing submittal [the prime contractor] issued here, showing the use of PVC instead of cast iron for the above ground waste piping, did not meet the minimum requirements of the solicitation.” Appeal of-Sauer, Inc., supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
CA Court of Appeal Reinstates Class Action Construction Defect Claims Against Homebuilder
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFLaurence R. Phillips, Andrew S. Azarmi, and Stefani Warren of Dentons reported that “on August 19, the California Court of Appeal, Fourth District, reinstated a class action asserting construction defect claims against a nationwide homebuilder.” According to the article, the decision is significant because “it effectively opens the door to class claims against homebuilders (and potentially other service providers employed in the homebuilding industry) arising out of alleged construction defects on California residential development and construction projects.”
The decision is unpublished, but “could signal a troubling trend for companies involved in the homebuilding industry in California. It is not yet clear whether the decision will be appealed to the California Supreme Court.”
Read the court decisionRead the full story...Reprinted courtesy of