Property Damage to Non-Defective Work Is Covered
February 18, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe New Hampshire Supreme Court found some of the property damage evolving from the insured's portion of the work was covered under its liability policy. Cogswell Farm Condo. Ass'n v. Tower Group, Inc., 2015 N.H. LEXIS 3 (N.H. Jan. 13, 2015).
Lemery Building Company, Inc. constructed and developed 24 residential condominium units. After units were sold, the Cogswell Farm Condominium Association sued Lemery, asserting that the "weather barrier" components of the units were defectively constructed and resulted in damage to the units due to water leaks. Cogswell then sued its insurer, Tower Group, Inc., seeking a declaratory judgment that its claims against Lemery were covered.
The trial court eventually determined that exclusions J (1) and J (6) both applied to exclude coverage. Exclusion J (1) excluded coverage for "property damage" to property that Lemery "owns, rents, or occupies." Exclusion J (6) excluded coverage for property damage to "[t] hat particular part of any property that must be restored, repaired or replaced because [Lemery's] work was incorrectly performed on it."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
OSHA Issues Fines for Fatal Building Collapse in Philadelphia
November 27, 2013 —
CDJ STAFFThe Occupational Safety and Health Administration has issued $400,000 in fines to two contactors who were involved with the collapse of a building in Philadelphia. Six people died and 14 more were injured in an adjacent building. OSHA concluded that the two firms, Campbell Construction and S&R Contracting, violated workplace safety regulations 12 times in their demolition of the building.
According to OSHA, Campbell Construction removed structural supports and portions of the lower floors of the building while upper stories were still being demolished. Both firms failed to provide its workers with fall protection equipment.
Read the court decisionRead the full story...Reprinted courtesy of
Ensuing Loss Provision Does Not Salvage Coverage
December 09, 2011 —
Tred R. Eyerly - Insurance Law HawaiiWater intrusion caused by a construction defect was not covered under the all risk policy’s ensuing loss provision. See Friedberg v. Chubb & Son, Inc., 2011 U.S. Dist. LEXIS 123582 (D. Minn. Oct. 25, 2011).
Extensive water damage was discovered in the insureds’ home when a small hole in the exterior wall was being repaired. Chubb’s adjuster and an expert found water intrusion causing rot, mold, and damage to the home’s wood framing and insulation. Chubb denied coverage because water intruded through the roof and wall, resulting in gradual deterioration. The insureds filed suit.
The policy excluded coverage for construction defects, but insured "ensuing covered loss unless another exclusion applies."
The court agreed there was a prima facie case for coverage because the home suffered a physical loss.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Sales of New U.S. Homes Rose More Than Forecast to End 2014
January 28, 2015 —
Bloomberg News(Bloomberg) -- Purchases of new homes in the U.S. jumped in December to the highest level in more than six years, a sign the industry is poised to keep expanding in 2015.
Sales increased 11.6 percent to a 481,000 annualized pace, exceeding all estimates in a Bloomberg survey of economists and the most since June 2008, figures from the Commerce Department showed Tuesday in Washington. Demand increased in three of four regions.
Gains in employment, borrowing costs close to historically low levels and easing credit may prompt more prospective buyers to enter the housing market. The improving outlook is driving up confidence among builders, and companies such as D.R. Horton Inc. and Lennar Corp. project the recovery will be sustained.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg News
Vancouver’s George Massey Tunnel Replacement May Now be a Tunnel Instead of a Bridge
January 06, 2020 —
Tim Newcomb - Engineering News-RecordThe constant political back-and-forth in British Columbia, Canada, over how to deal with an aging George Massey Tunnel, opened in 1959, has ping-ponged from uncertainty to a $3.5 billion, 10-lane bridge, back to uncertainty, to no bridge and now to an eight-lane submerged tunnel.
Tim Newcomb, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Common Construction Contract Provisions: No-Damages-for-Delay Clause
March 16, 2017 —
David Cook & Chadd Reynolds - Autry, Hanrahan, Hall & Cook, LLP BlogIn continuing our series on common contract provisions found in construction contracts, this post highlights no-damages-for-delay clauses.
Parties to a contract – particularly a construction contract – may agree that the performance of the contract must occur within a set amount of time. When a party is delayed in performing a contract, it may incur additional costs due to the delay. In most circumstances, unless the parties agree otherwise, the delayed party would be entitled to an extension of time to perform the contract. But it may also seek to recover the additional costs resulting from the delay.
A no-damages-for-delay clause attempts to prevent the delayed party from recovering those additional costs. In construction contracts, an upstream party, such as an owner or prime contractor, typically relies on a no-damages-for-delay clause when presented with a delay claim by a downstream party, such as a subcontractor.
Reprinted courtesy of
David Cook, Autry, Hanrahan, Hall & Cook, LLP and
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLP
Mr. Cook may be contacted at cook@ahclaw.com
Mr. Reynolds may be contacted at reynolds@ahclaw.com
Read the court decisionRead the full story...Reprinted courtesy of
School Blown Down by Wind Still Set to Open on Schedule
November 06, 2013 —
CDJ STAFFThe framing was going up for a new elementary school in Pasco, Ohio, when winds of about 60 miles per hour ripped the area. The winds brought down part of the structure. School district officials met with the contractor, Fowler Construction. John Morgan, the assistant director of operations for the Pasco School District, said that they did not “anticipate any delay in the opening of the new school.”
Groundbreaking at the school happened in June and the school is scheduled to be open in the fall. The damage had not yet been determined.
Read the court decisionRead the full story...Reprinted courtesy of
Court Strikes Down Reasonable Construction Defect Settlement
December 20, 2012 —
CDJ STAFFThe Court of Appeals of Washington has struck down a construction defect settlement between a building owner and the companies she hired to repair the siding, among other repairs to bring the building up to code. Yuan Zhang hired Hawk Construction LLC to do repair work. Hawk, in turn, hired Ready Construction LLC for some aspects of the project. Hawk and Ready were both insured by Capital Specialty Insurance Corporation.
There were several problems with Ready’s work. After removing old siding, they did not protect the building, nor did they remove all of the damaged layers. Ready covered, but did not fix, a mildew problem under the old siding. When new siding was reattached, the nails used were too short to adequately attach it.
After paying for an inspection of the work, Zhang had Hawk and Ready begin the repairs again, but the work was abandoned without being completed. Zhang sued Hawk for breach of contract. Hawk then sued Ready, claiming that “Ready was liable to Hawk to the extent that Hawk was liable to Zhang.” Capitol retained defense for both contractors.
Zhang settled with Hawk, in an agreement that gave her “the right to collect and/or pursue all costs and attorney fees paid by Hawk or its insurance company defending against the Zhang’s claims and pursuing claims against Ready.” Subsequently, she also settled with Ready. Both companies ceased operations.
Zhang had the settlements reviewed by a court, which concluded that the settlements were reasonable. Capital was allowed to appeal, claiming that the settlement included costs that were Zhang’s responsibility. The appeals court did not examine the question of the reasonableness of the settlement, concluding that Capitol’s interests were relevant only to “questions of bad faith, collusion, and fraud.”
In the case of Zhang, the court concluded that the relationship between Zhang and her former contractors was collusive. The court noted that “bad faith or collusion may exist when the evidence indicates a joint effort to create, in a non-adversarial atmosphere, a resolution beneficial to both parties, yet highly prejudicial to the insurer as intervener.” The court noted that both companies had minimal assets which were, in any case, exempted from the agreement. Further, the court found that the agreements failed to determine “what amount of the repairs related to preexisting water damage.” Zhang’s calculation of costs also included her expenses for architectural and engineering services, which the court points out, “where always Zhang’s costs to bear.”
The court concluded that “the overall structure of the settlements is highly probative of collusion, fraud, or bad faith.” Zhang’s agreements with Hawk and Ready allowed her to collect compensation from Hawk and then collect Ready’s compensation to Hawk for their portion of the settlement, allowing Zhang to collect the monies twice. Further, she was allowed to pursue Capitol for Hawk’s attorney expenses, even though Hawk had none. “The right to recover Hawk’s fees merely set up a windfall recovery for Zhang.” The court described the agreements among Zhang, Hawk, and Ready as “precisely the type of manipulation [the law] is intended to preclude.”
Read the court decisionRead the full story...Reprinted courtesy of