Bailout for an Improperly Drafted Indemnification Provision
February 11, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent opinion came out that held that even though an indemnification provision in a subcontract was unenforceable per Florida Statute s. 725.06, the unenforceable portion is merely severed out of the indemnification clause leaving the rest of the clause intact. In essence, an otherwise invalid indemnification clause is bailed out by this ruling (which does not even discuss whether this subcontract had a severability provision that states that if any portion of any provision in the subcontract is invalid, such invalid portion shall be severed and the remaining portion of the provision shall remain in full force and effect).
This opinion arose from a construction defect case, CB Contractxors, LLC v. Allens Steel Products, Inc.,43 Fla.L.Weekly D2773a (Fla. 5thDCA 2018), where the general contractor, sued by an association, flowed down damages to subcontractors based on the contractual indemnification provision in the subcontracts. Subcontractors moved to dismiss the contractual indemnification claim because it was not compliant with Florida Statute s. 725.06. The indemnification provision required the subcontractors to indemnify the general contractor even for the general contractors own partial negligence, but failed to specify a monetary limitation on the extent of the indemnification as required by Florida Statute s. 725.06. (The indemnification clause in the subcontract was the standard intermediate form of indemnification that required the subcontractor to indemnify the general contractor for claims regardless of whether the claims were caused in part by the general contractor.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Unlicensed Contractors Nabbed in Sting Operation
September 09, 2011 —
CDJ STAFFThe California State License Board charged sixteen people in the Fresno area with accepting contracting jobs without licenses. The Statewide Investigative Fraud Team of the CSLB set up a sting operation at a home in Clovis, California seeking bids on tree service, painting, and general contracting services. Those who bid for jobs at more than $500 are required under California law to be licensed. Unlicensed contractors can only work on jobs with a cost to the homeowner of less than $500 and must inform the homeowner that they are not licensed.
In addition to citing contractors for not possessing appropriate licenses, the CSLB also cited contractors for failure to carry workers compensation insurance and illegal advertising. Further, California law limits down payments to the lesser of ten percent or $1,000. Two contractors were cited for requesting excessive down payments.
One contractor, an unlicensed tree service contractor, had been cited previously in a sting operation. He failed to show up for his court date.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
The Administrative Procedure Act and the Evolution of Environmental Law
September 19, 2022 —
Anthony B. Cavender - Gravel2GavelEnacted in 1946, the Administrative Procedure Act (APA) has provided a lasting framework for federal agency rulemaking and adjudication, as well as establishing the power of the federal courts to exercise judicial review over these actions of the federal bureaucracy. The APA is codified at 5 U.S.C. §§ 551–559, and §§ 701-706. There have been very few amendments made to the APA over these years, which indicates that Congress is reasonably satisfied with its administration and implementation.
What follows is an overview of how the APA has been used by the courts to resolve disputes involving the federal agencies, with particular attention being paid to the development of environmental law and practice. While there have been very few amendments to the statute, the courts have been free to enlarge upon the sometimes-opaque text of the APA to, in effect, change the law, even in an era when “textual fidelity” to the language of the statute is the prevalent approach.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
So You Want to Arbitrate? Better Make Sure Your Contract Covers All Bases
August 16, 2021 —
Stephanie Nolan Deviney - ConsensusDocsAs a General Contractor, you may prefer to arbitrate any contractual disputes rather than engage in protracted litigation. Many Courts favor arbitration clauses and will enforce them if there is a sufficient reason to do so. However, there are several issues that a General Contractor should consider when including an arbitration clause in its construction agreement with its client. When an arbitration clause is not properly crafted, questions can arise as to who must arbitrate? Who decides whether to arbitrate? Who selects the arbitrator? What will the subject matter of the arbitration be? A look at a recent case in Pennsylvania highlights the need for properly crafted arbitration clauses.
A Recent Case Highlights The Importance Of Arbitration Clauses
In TEC Construction, LLC v. Greg Rich and Lora Rich filed in the Court of Common Pleas, Allegheny County, Pennsylvania, TEC Construction, LLC (“TEC”) and Greg and Lora Rich (the “Riches”), entered into a Construction Agreement with an arbitration clause. Specifically, the parties to the Construction Agreement, TEC and the Riches, agreed to arbitrate any disputes with the American Arbitration Association. Five subcontractors completed the work under the Construction Agreement but none of the subcontractors agreed to arbitrate.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Nolan Deviney, Fox Rothschild LLP (ConsensusDocs)Ms. Deviney may be contacted at
sdeviney@foxrothschild.com
New York’s Highest Court Weighs in on N.Y. Labor Law
September 23, 2024 —
Bill Wilson - Construction Law ZoneN.Y. Labor Law § 241(6) requires owners and contractors to provide reasonable and adequate protection and safety to persons employed at or lawfully frequenting a construction site. If a worker is injured on a construction site and establishes a violation of a specific and applicable Industrial Code regulation, both the owner and contractor will be held vicariously liable for the worker’s injury, without regard to their fault and even in the absence of control or supervision of the worksite. The Court of Appeals of New York recently addressed the broad scope of the Labor Law in the context of slipping hazards.
In Bazdaric v. Almah Partners, LLC, 41 N.Y.3d 310 (2024), the plaintiff, an injured painter, slipped and fell on a plastic covering placed over an escalator in an area he was assigned to paint. The plaintiff claimed that the plastic covering was a foreign substance for purposes of Industrial Code 12 NYCRR 23-1.7(d) because it was not part of the escalator. Industrial Code 12 NYCRR 23-1.7(d) states:
Slipping hazards. Employers shall not suffer or permit any employee to use a floor, passageway, walkway, scaffold, platform or other elevated working surface which is in a slippery condition. Ice, snow, water, grease and any other foreign substance which may cause slippery footing shall be removed, sanded or covered to provide safe footing.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Serving Notice of Nonpayment Under Miller Act
January 20, 2020 —
David Adelstein - Florida Construction Legal UpdatesUnder the federal Miller Act, if a claimant is NOT in privity with the prime contractor, it needs to serve a “notice of nonpayment” within 90 days of its final furnishing. In this manner, 40 U.S.C. 3133 (b)(2) states:
A person having a direct contractual relationship with a subcontractor but no contractual relationship, express or implied, with the contractor furnishing the payment bond may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made. The action must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. The notice shall be served–
(A) by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence; or
(B) in any manner in which the United States marshal of the district in which the public improvement is situated by law may serve summons.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Senior Living Facility Makes Construction Defect Claims
November 13, 2013 —
CDJ STAFFMidland Meadows Senior Living, LLC has filed a petition for declaratory judgment in the U.S. District Court in West Virginia, claiming that the contractor who built the facility, Arcon Group Incl, made a variety of errors, leading to mold and lack of water in the dining room, but also that floors were improperly constructed, sump pumps were not installed, and that the company failed to properly insulate the buildings.
The lawsuit also names Arcon Group’s insurer, First Mercury Insurance Company.
Read the court decisionRead the full story...Reprinted courtesy of
Federal District Court Finds Coverage Barred Because of Lack of Allegations of Damage During the Policy Period and Because of Late Notice
December 29, 2020 —
Robert Dennison - Traub LiebermanIn American Bankers Ins. Co. of Florida v. National Fire Ins. Co. of Hartford, 2020 WL 5630017 (Sept. 21, 2020), the Northern District of California of the United States District Court had occasion to consider whether allegations in an underlying complaint triggered a duty to defend and a late notice defense to coverage.
The underlying actions were a suit against the City of Walnut Creek for damages from flooding allegedly caused by the City’s failure to develop and maintain its storm drains.The City settled the cases then sued its liability insurers who issued its coverage in the period 1968 to 1986 for indemnification of the amounts spent to defend and settle the cases.The published decision involved three Travelers’ policies issued to the City between 1968 and 1976, as to which Travelers sought summary judgment as to the lack of coverage in its policies.
The district court first found that the definition of an “occurrence” in the policies, in one policy “an event or a continuous or repeated exposure to conditions which causes injury to person or damage to property during the policy period” and in the other two “an accident, including injurious exposure to conditions, which results during the period this policy is in effect, in bodily injury or property damage,” fell within the rule of Montrose Chemical Corp. v. Admiral Ins. Co. (1995) 10 Cal.4th 645, that injury or damage during the policy period must occur in order for the policy to be triggered.The court agreed with Travelers that while there were allegations of flooding for many years, the only claims/allegations of property damage were for the period 2000 and later.Therefore the property damage coverage in the policies was never triggered.
Read the court decisionRead the full story...Reprinted courtesy of