A Termination for Convenience Is Not a Termination for Default
April 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesA termination for convenience is NOT a termination for default. They are NOT the same. They should NOT be treated as the same. I am a huge proponent of termination for convenience provisions because sometimes a party needs to be able to exercise a termination for convenience, but the termination is not one that rises to a basis for default. However, exercising a termination for convenience does not mean you get to go back in time and convert the termination for convenience into a termination for default. It does not work like that. Nor should it.
An opinion out of the Civilian Board of Contract Appeals – Williams Building Company, Inc. v. Department of State, CBCA 7147, 2024 WL 1099788 (CBCA 2024 – demonstrates a fundamental distinction between a termination for convenience and a termination for default, i.e., that you don’t get to conjure up defaults when you exercise a termination for convenience:
Because a termination for convenience essentially turns a fixed-price construction contract into a cost-reimbursement contract, allowing the contractor to recover its incurred performance costs, the resolution of this appeal will involve identifying the total costs that [Contractor] incurred in performing this contract before [Government] terminated it for convenience. Since [Government] terminated the contract for convenience rather than for default, it no longer matters whether, in the past,[Contractor] acted intentionally in overstating the amount of its incurred costs or committed a contract breach. Ultimately, as permitted in response to a termination for convenience, [Contractor] will recover those allowable costs that [Contractor]establishes it incurred in performing the contract.
Williams Building Company, supra.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Catch 22: “If You’re Moving Dirt, You Need to Control Your Dust” (But Don’t Use Potable Water!)
February 18, 2015 —
Stephen McKae – California Construction Law BlogReturning from an Oregon vacation this past Summer along I-5, I found frequent reminders of the extraordinary drought conditions prevailing across California. A grey smoky gloom blanketed the California-Oregon border from Ashland to Weed from at least five wildfires. The prediction of rains in the north state was more curse than blessing as lightning threatened to touch off tender-dry fuel in the forests and start more fires. Farmers tilling fields produced massive dust clouds. And under the I-5 bridge along the Sacramento River arm of Lake Shasta, the lake had receded to the original streambed.
On NOAA’s Palmer Drought Severity Index, nearly all of California is listed as in a condition of extreme or severe drought, and the Governor has issued a Proclamation of Continued State of Emergency requiring water conservation measures affecting all California residents. Indeed, early August news reports indicate that hopes of relief from an El Nĩno year are waning. The State Water Resources Control Board’s Emergency Regulation No. 2014 issued July 15 mandates action to reduce water use and require larger water suppliers to activate their Water Shortage Contingency Plan. The emergency regulation will remain in effect until April 25, 2015 unless extended due to ongoing drought conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen McKae, Wendel Rosen Black & Dean LLPMr. McKae may be contacted at
smckae@wendel.com
U.S. Building Permits Soared to Their Highest Level in Nearly Eight Years
June 17, 2015 —
Michelle Jamrisko – BloombergThrough all its ups and downs, the U.S. homebuilding industry is making slow progress.
While housing starts declined 11.1 percent in May to a 1.04 million annualized rate, it followed a revised 1.17 million pace the prior month to cap the best back-to-back readings since late 2007, Commerce Department data showed Tuesday in Washington. Permits for future projects climbed to the highest level in almost eight years.
The stop-and-go nature of the rebound, which has been exacerbated by the inclement weather that brought construction to a near standstill at the start of the year, masks a steady recovery in the industry at the center of the past recession. While residential real estate has yet to fulfill its typical role as a pillar of this economic expansion, gains in hiring and bigger paychecks are brightening Americans’ moods and could lift home purchases in the second half of 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, Bloomberg
Precast Standards' Work Under Way as Brittle Fracture Warnings Aired
December 22, 2019 —
Nadine M. Post - Engineering News-RecordThe American Concrete Institute is gearing up to develop ACI’s first code requirements specifically for precast concrete. The recent announcement of the initiative comes on the heels of an article in the September issue of ACI’s monthly magazine, Concrete International, that sounds the alarm about the potential for brittle failures of precast, prestressed-concrete double-T parking decks, with flanges reinforced with a non-code-compliant polymer-coated carbon-fiber grid product, called C-Grid.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Seattle Developer Defaults on Renovated Office Buildings
December 23, 2024 —
Anna Edgerton - BloombergA major developer in downtown Seattle defaulted on a loan backed by two of its most prized office properties, including one that formerly housed a branch of the Federal Reserve Bank of San Francisco.
Firms tied to Martin Selig Real Estate are in default on a more than $200 million loan, according to letters from lender Acore Capital dated Nov. 15 that were filed in Washington’s King County. The buildings would change ownership 30 days after that notice if no other action is taken, according to the letters.
Read the court decisionRead the full story...Reprinted courtesy of
Anna Edgerton, Bloomberg
Subcontractor's Faulty Workmanship Is Not an "Occurrence"
March 16, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe court found there was no duty to defend the subcontractor for alleged faulty workmanship in installing stone veneer at a condominium construction project. Quality Stone Veneer, Inc. v. Selective Ins.Co. of Am., 2017 U.S. Dist. LEXIS 9393 (E.D. Pa. Jan. 23, 2017).
Quality Stone Veneer (QSV) entered a subcontract with Mignatti Construction, the general contractor, for development of a condominium. QSV agreed to provide all the materials and labor related to the installation of stone veneer at the project. After construction began, the Association filed a complaint against Mignatti, claiming deficiencies in the construction of the furnace, ventilation, roofing, alarms, sprinklers, electrical and water systems. Mignatti filed a joinder complaint against QSV for contribution and/or indemnity for breach of warranty and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pulte Home Corp. v. CBR Electric, Inc.
August 24, 2020 —
Michael Velladao - Lewis BrisboisIn Pulte Home Corp. v. CBR Electric, Inc., 50 Cal.App.5th 216 (June 10, 2020), the California Court of Appeal reversed the trial court’s entry of judgment in favor of six subcontractors with respect to an equitable subrogation lawsuit filed by St. Paul Mercury Insurance Company (“St. Paul”). St. Paul filed the lawsuit after defending Pulte Home Corp. (“Pulte”) against two construction defect lawsuits. The lawsuit contended that St. Paul was entitled to seek recovery of defense costs incurred on behalf of Pulte based on equitable subrogation. St. Paul relied on the indemnity clauses in each of the subcontracts, and argued that the subcontractors had breached their contracts with Pulte. As such, each subcontractor was obligated to pay an equitable share of the defense of the construction defect lawsuits relating to their work on the homes at issue in such lawsuits. The trial court ruled against St. Paul and held that the subcontractors’ failure to pay defense costs did not “cause” the homeowners’ claims, such that there was no causal connection supporting a claim for equitable subrogation. In addition, the trial court found that “equitable subrogation was an all-or-nothing claim, meaning it required a shifting of the entire amount of defense costs to the subcontractors on a joint and several basis and did not allow for an apportionment of costs among the defendant subcontractors.”
In reversing the trial court’s decision, the Court of Appeal reasoned that St. Paul stood in the shoes of Pulte and was limited to pursuing recovery from the subcontractors based on the same rights as afforded to Pulte under the subcontracts. The Court of Appeal noted that St. Paul was seeking reimbursement of defense costs from the subcontractors based on the theory that they were contractually liable for paying an equitable share of defense costs. The Court of Appeal also noted that St. Paul’s claim was not premised on the contention that the subcontractors’ failure to pay defense costs caused the homeowners’ claims. Rather, St. Paul’s claim was premised on the subcontractors’ breach of their defense duty owed to Pulte under the indemnity clauses in their subcontracts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Communicate with the Field to Nip Issues in the Bud
March 16, 2017 —
Christopher G. Hill – Construction Law MusingsThis past week, I spent some time meeting with clients and generally discussing the day to day operations of construction companies. One common theme of these discussions (and of this construction blog) was the need to deal with problems at a job site early. I have often discussed the contract side of catching things early, and firmly believe that this is the first step to a successful construction project. This post is about the equally important “operational” side of this advice.
What do I mean by “operational?” Essentially, while the contract negotiation and drafting tries to anticipate problems that might occur, the operational side deals with problems on a job site as they occur. In short, moving from what might occur (something I as a construction lawyer think about all the time), to what is actually occurring when putting that contract to work. Whether you are a general contractor, owner, subcontractor, or supplier to a construction project, you are likely well aware of the fact that Murphy was an optimist and something will go wrong. How you deal with this fact can be the difference between a successful, profitable project, and one that ends up in litigation (read: not as profitable). However, in order to deal with a problem properly, you need to know about the problem before it explodes. Without this knowledge, a problem could fester and lead to non-payment, subcontractor mechanic’s liens, and other headaches that don’t need to be further mentioned here.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com