Harsh New Time Limits on Construction Defect Claims
April 26, 2011 —
Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq.A recent Colorado Supreme Court decision, Smith v. Executive Custom Homes, Inc., 230 P.3d 1186 (Colo. 2010), considerably shortens the time limit for bringing many construction defect lawsuits. Homeowners and homeowner associations risk losing the right to seek reimbursement from builders, developers and other construction professionals unless they carefully and quickly act upon discovery of evidence of any potential construction defect.
The Statute of Limitations for Construction Defect Claims
Colorado’s construction defect statute of limitations limits the time for homeowners and homeowners associations to bring lawsuits for construction defects against “construction professionals,” including developers, general contractors, builders, engineers, architects, other design professionals, inspectors and subcontractors. The statute requires homeowners and associations to file suit within two years “after the claim for relief arises.” A claim for relief “arises” when a homeowner or association discovers or reasonably should have discovered the physical manifestation of a construction defect.
The two-year time limitation applies to each construction defect separately, and will begin to run upon the appearance of a “manifestation” of a construction defect (which may include, for example, a condition as simple as a roof leak or drywall cracks), even if the homeowner or association does not know the cause of the apparent problem.
The Smith Opinion and its Effect on the Statute of Limitations
In Smith v. Executive Custom Homes, Inc., the plaintiff homeowner, Mrs. Smith, slipped on ice that had accumulated on her sidewalk because of a leaking gutter and suffered injury. When she first noticed the leak, she reported it to her property manager, who reported it to the builder. The builder attempted to repair the gutter, unbeknownst to Mrs. Smith, and she did not notice further problems until approximately one year after she first observed the leak, when she fell and suffered serious injury. She sued the builder within two years of her injury, but nearly three years after she first learned of the leak.
The Colorado Supreme Court dismissed Mrs. Smith’s claims as untimely and held that under the construction defect statute of limitations, the two-year period for suing for injuries due to construction defects begins when the homeowner first observes the physical manifestation of the defect, even if the resulting injury has not yet occurred. The court acknowledged that this ruling could result in “unfair results,” especially if a serious and unforeseeable injury occurs more than two years after the first time the homeowner noticed the problem, and as a result the victim is unable to seek redress from those responsible for the defect.
Read the full story…
Reprinted courtesy of Scott F. Sullan, Esq., Mari K. Perczak, Esq., and Leslie A. Tuft, Esq. of Sullan2, Sandgrund, Smith & Perczak, P.C., and they can be contacted through their web site.
Read the court decisionRead the full story...Reprinted courtesy of
Amazon Urged to Review Emergency Plans in Wake of Deadly Tornado
June 20, 2022 —
Spencer Soper - BloombergAmazon.com Inc. should better prepare workers for extreme weather events, according to federal regulators who investigated a deadly tornado strike on a company warehouse in Edwardsville, Illinois.
The storm ripped through the facility in December, killing six workers and injuring several others, prompting the Occupational Safety and Health Administration to launch a probe. At the time, Amazon said the facility complied with all construction regulations and that proper safety procedures were followed when the tornado struck. But several workers told Bloomberg that training for such events was minimal and mostly entailed pointing out emergency exits and assembly points.
An OSHA report released on Tuesday echoed those concerns. The agency said a bullhorn that was supposed to be used to tell workers to take cover was locked up in a cage and inaccessible. In interviews with investigators, some employees couldn’t recall ever participating in emergency drills and said they mistakenly took shelter in a bathroom on the south side of the building rather than in designated restrooms on the north side.
Read the court decisionRead the full story...Reprinted courtesy of
Spencer Soper, Bloomberg
A New Study: Unexpected Overtime is Predictable and Controllable
January 31, 2022 —
Aarni Heiskanen - AEC BusinessA new study by Dodge Construction Network and Versatile, a construction technology pioneer using artificial intelligence (AI) and the internet of things (IoT) to optimize construction processes, found that unexpected overtime is predictable and controllable through regular job site activity measurement. According to the study, overtime is predictable at an 88% confidence level, if proper measurement is utilized.
Overtime is a persistent feature of construction sites, however, it is often unplanned and unpredictable. Despite the cost of overtime, its impact on skilled workers, and its implications for safety and other key factors on a project site, it is often applied to address immediate concerns rather than planned to maximize its effects. This recent study shows that in order to best understand overtime and its impact, data and measurement of jobsite activities are key.
“Unique insights derived from advanced data and analytics tools will empower construction crews to build better,” said Meirav Oren, co-founder and CEO of Versatile. “Overtime can be a very effective tool on the jobsite. Through the power of data, general contractors gain the ability to minimize unnecessary overtime while maximizing its strategic benefits.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Important Information Regarding Colorado Mechanic’s Lien Rights.
November 07, 2012 —
David McLain, Colorado Construction LitigationWith payment problems in the construction economy having accelerated over the past few years, there has been a substantial increase in mechanic’s lien activity and associated litigation. The typical mechanic’s lien claimant is a material supplier, a trade subcontractor, or even a general contractor that has not been paid by the developer/owner of the construction project. The reason for filing a mechanic’s lien claim is that it offers the prospect in many cases to make the unpaid construction professional a priority creditor, with a lien on the real estate that is superior to the construction lender.
One of the primary rules governing a mechanic’s lien claim is that the creditor’s formal written “Notice of Intent to File a Mechanic’s Lien” (hereafter “Lien Notice”) must be (1) served on the owner of the property for which the work was done or the materials used, and (2) served at the same time on the general contractor who has handled the construction project. After the creditor has made service of the lien claim by USPS certified mail (using the green return receipt card for proof of service) or separate personal delivery of the notice to the property owner and general contractor, ten full days must pass (not including the date of mailing of the notices) before the lien notice is filed in the public records.
After ten days have expired following the date of mailing using certified mail, or personal delivery of the notice to the property owner and the general contractor, the lien notice can be filed to make the lien valid.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLC.Mr. McLain can be contacted at
mclain@hhmrlaw.com
Faulty Workmanship may be an Occurrence in Indiana CGL Policies
April 07, 2011 —
Beverley BevenFlorez CDJ STAFFThe question of whether construction defects can be an occurrence in Commercial General Liabilities (CGL) policies continues to find mixed answers. The United States District Court in Indiana denied the Plaintiff’s Motion for Summary Judgment in the case of General Casualty Insurance v. Compton Construction Co., Inc. and Mary Ann Zubak stating that faulty workmanship can be an occurrence in CGL policies.
Judge Theresa L. Springmann cited Sheehan Construction Co., et al. v. Continental Casualty Co., et al. for her decision, ”The Indiana Supreme Court reversed summary judgment, which had been granted in favor of the insurer in Sheehan, holding that faulty workmanship can constitute an ‘accident’ under a CGL policy, which means any damage would have been caused by an ‘occurrence’ triggering the insurance policy’s coverage provisions. The Indiana Supreme Court also held that, under identically-worded policy exclusion terms that are at issue in this case, defective subcontractor work could provide the basis for a claim under a CGL policy.”
As we reported on April 1st, South Carolina’s legislature is currently working on bill S-431 that would change the wording of CGL policies in their state to include construction defects. Ray Farmer, Southwest region vice president of the American Insurance Association spoke out against the bill. “CGL policies were never meant to cover faulty workmanship by the contractor,” he said. “The bill’s supplementary and erroneous liability provisions will only serve to unnecessarily impact construction costs in South Carolina.”
Read the Opinion and order...
Read the court’s ruling...
Read the American Insurance Association statement...
Read the court decisionRead the full story...Reprinted courtesy of
At Least 23 Dead as Tornadoes, Severe Storms Ravage South
March 18, 2019 —
The Associated Press (Kim Chandler) - BloombergBeauregard, Ala. (AP) -- A tornado roared into southeast Alabama and killed at least 23 people and injured several others Sunday, part of a severe storm system that caused catastrophic damage and unleashed other tornadoes around the Southeast.
"Unfortunately our toll, as far as fatalities, does stand at 23 at the current time," Lee County Sheriff Jay Jones told WRBL-TV of the death toll. He added that two people were in intensive care.
Drones flying overheard equipped with heat-seeking devices had scanned the area for survivors but the dangerous conditions halted the search late Sunday, Jones said. "The devastation is incredible," he said. An intense ground search would resume Monday morning.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Stuck in Seattle: The Aggravating Adventures of a Gigantic Tunnel Drill
April 01, 2015 —
Karen Weise – BloombergAbout 20 workers wearing hard hats and reflective vests clump together on the edge of a chasm near Seattle’s waterfront, peering down a hole 120 feet deep and 83 feet wide. The last men have been craned out of the pit in a yellow metal cage. Gulls squawk. A TV news helicopter hovers overhead.
A dozen journalists stand nearby on the bed of a truck. We’re here to see Bertha, one of the world’s biggest tunneling machines. Or at least a piece of her. A 240-foot crane is about to haul a 540,000-pound steel shield out of the ground, 20 months after Bertha started digging a highway. Almost imperceptibly, the crane starts rising.
The event, on a Thursday in mid-March, is part of a massive rescue mission to fix the $80 million machine. She broke abruptly in December 2013 after boring through just 1,000 feet, one-ninth of her job. Her seals busted, and her teeth clogged with grit and pieces of an 8-inch steel pipe left over from old groundwater tests. She stopped entirely.
Read the court decisionRead the full story...Reprinted courtesy of
Karen Weise, BloombergMs. Weise may be contacted at
kweise@bloomberg.net
Turkey Digs Out From a Catastrophe
April 18, 2023 —
Pam McFarland - Engineering News-RecordIn what’s left of Antakya, a once-thriving and cosmopolitan tourist destination in the southeastern edge of Turkey, the streets seem weirdly quiet. Buildings stand askew at odd angles or are completely toppled, and the rubble from the homes of people who lived inside of them is neatly collected into piles and mounds.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of