Anticipatory Repudiation of a Contract — The Prospective Breach
July 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThere are instances where a party can engage in the anticipatory repudiation of their obligations under a contract. In essence, this is basically a party prospectively breaching the contract by repudiating their obligations in the contract.
A prospective breach of contract occurs where there is absolute repudiation by one of the parties prior to the time when his performance is due under the terms of the contract. Such a repudiation may be evidenced by words or voluntary acts but the refusal must be distinct, unequivocal, and absolute. Moreover, repudiation can be shown where one party makes additional demands not included in the initial agreement:
The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.
24 Hr Air Service, Inc. v. Hosanna Community Baptist Church, Inc., 46 Fla. L. Weekly, D1344a (Fla. 3d DCA 2021) (quotations and citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Phillips & Jordan Awarded $176M Everglades Restoration Contract
March 01, 2021 —
Thomas F. Armistead - Engineering News-RecordConstruction of the next major project for the Everglades Agricultural Area Reservoir south of Lake Okeechobee is set to begin in April following the South Florida Water Management District's award of a $175.8-million lump-sum contract to Phillips and Jordan Inc.
Reprinted courtesy of
Thomas F. Armistead, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
MTA Implements Revised Contractors Debarment Regulations
July 06, 2020 —
Steven M. Charney, Gregory H. Chertoff & Paul Monte - Peckar & Abramson, P.C.On June 3, 2020, the Metropolitan Transit Authority (“MTA”) published and implemented revised regulations pertaining to the debarment of contractors. The revised regulations address many of the deep concerns raised by the contracting community.
Under relevant administrative procedure, the MTA publication of the revised regulations starts a 45 day notice period before the regulations can be adopted as final.
The prior regulations essentially required that debarment occur upon a purely formulaic calculation establishing that a contractor: 1) was more than 10% late, or 2) had submitted invalid claims that exceeded the adjusted contract price by a measure of 10%.
The revised regulations represent improvements over the prior regulations.
Critically, the revised regulations address the primary concern raised by the contracting community, that being the mandate of purely formulaic debarment. Instead, the revised regulations establish a process that includes greater flexibility and discretion before debarment may ensue.
Reprinted courtesy of Peckar & Abramson, P.C. attorneys
Steven M. Charney,
Gregory H. Chertoff and
Paul Monte
Mr. Charney may be contacted at scharney@pecklaw.com
Mr. Chertoff may be contacted at gchertoff@pecklaw.com
Mr. Monte may be contacted at pmonte@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Extreme Weather Events Show Why the Construction Supply Chain Needs a Risk-Management Transformation
July 24, 2023 —
Brad Barth - Construction ExecutiveA perfect storm of recent extreme weather events has exposed the fragility of North America’s construction supply chains amid an increasingly fluctuating, fast-changing risk landscape. Supply chains that were already reeling from resurgent demand for raw materials coming out of the pandemic have been further disrupted by major storms such as recent tornados in Arkansas and Mississippi. Such events can have a ripple effect across many distinct supply lines as exemplified when the 2021 Texas freeze caused railroad closures and knocked out both petrochemical and semiconductor plants, causing shortages that affected construction and many other industries.
The wide-ranging reverberations from these events demonstrate how stakeholders across all stages of capital projects increasingly share common vulnerabilities. Crucially, the way in which disruption from extreme weather events has caused project delays and cost overruns shows how time, cost and scope are increasingly interlinked and equally vulnerable to systemic risks.
Traditional project-management methods where risks are not collectively managed and mitigated by all stakeholders are becoming increasingly inadequate, as risks to cost, time and scope are often considered in isolation. The domino effect of supply-chain disruption across capital projects similarly shows the inadequacy of project-management models where suppliers are not afforded a key stake in the project (or sometimes even a seat at the planning table). This traditional model cannot adapt to sudden, systemic risks that disrupt multiple suppliers and ripple out across all stakeholders, deliverables and project-management metrics.
Reprinted courtesy of
Brad Barth, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Tips for Contractors Who Want to Help Rebuild After the California Wildfires
November 02, 2017 —
Garret Murai - California Construction Law BlogI received a call from one of my contractor clients this past week to see what he could do to help those affected by California’s North Bay fires.
The North Bay fires are the deadliest and most destructive wildfires in California’s history. To date, the fires have claimed 42 lives, burned more than 200,000 acres of land, destroyed an estimated 8,400 structures and likely damaged tens of thousands more. By comparison, the state’s second most deadly wildfire, the Oakland Hills fire of 1991, claimed the lives of 25 people, burned 1,600 acres of land, and destroyed 2,900 structures. Rebuilding costs for the North Bay fires, according to the California Insurance Commissioner, are expected to top $1 billion.
For those with insurance, insurance experts say that the rebuilding process can take two years or more for those whose homes and businesses were destroyed. For those whose homes and businesses were fortunate enough only to be damaged, rebuilding efforts are already underway.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Three lawyers from Haight were recognized in The Best Lawyers in America© 2020 Edition
September 30, 2019 —
William G. Baumgaertner, Michael Leahy, & Denis Moriarty - Haight Brown & BonesteelCongratulations to Haight’s attorneys who were recognized in The Best Lawyers in America© 2020 Edition
Los Angeles, California
William G. Baumgaertner for personal injury and product liability litigation for plaintiffs and defendants
Michael Leahy for insurance law
Denis Moriarty for insurance law
Reprinted courtesy of Haight Brown & Bonesteel attorneys
William G. Baumgaertner,
Michael Leahy and
Denis J. Moriarty
Mr. Baumgaertner may be contacted at wbaum@hbblaw.com
Mr. Leahy may be contacted at mleahy@hbblaw.com
Mr. Moriarty may be contacted at dmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Banks Rejected by U.S. High Court on Mortgage Securities Suits
January 12, 2015 —
Greg Stohr – BloombergThe U.S. Supreme Court dealt a blow to Royal Bank of Scotland Group Plc and Nomura Holdings Inc. (8604), refusing to derail federal government lawsuits that seek billions of dollars over the sale of risky mortgage-backed securities.
The justices today turned away an appeal by four banks, including units of RBS and Nomura, in a case stemming from the collapse of two credit unions that owned more than $1.7 billion in those securities.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Stohr, BloombergMr. Stohr may be contacted at
gstohr@bloomberg.net
Yet Another Reminder that Tort and Contract Don’t Mix
January 25, 2021 —
Christopher G. Hill - Construction Law MusingsI have stated on numerous occasions here at Musings that in Virginia, contract claims and tort claims (read fraud) don’t mix. A recent case from the Federal District Court for the Eastern District of Virginia presents another example of this principle. In Itility LLC v. The Staffing Resource Group, Judge Ellis of the Alexandria Division, considered ITility’s claims of fraud and breach of contract against SRG and one of its officers based upon SRG’s alleged violation of its duties under a teaming agreement. The claim by ITility was that TSRG provided false and misleading resumes and thus damaged ITility. SRG filed a Motion to Dismiss and the Court was therefore required to resolve the following issues: (1) whether plaintiff’s fraud claim is barred by Virginia’s “source of duty” rule; (2) whether plaintiff’s claim for tortious interference with a business expectancy is barred by SRG’s participation in the business expectancy, and (3) whether the teaming agreement between the parties bars plaintiff’s claims for consequential and punitive damages.
Reprinted courtesy of
The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of