Oregon Court of Appeals Rules That Negligent Construction (Construction Defect) Claims Are Subject to a Two-Year Statute of Limitations
October 20, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCStatutes of limitations are distinct from statutes of repose. There is a lot of confusion between the two.
Generally, a statute of limitations is a law which sets the maximum period of time which one can wait before filing a lawsuit, depending on the type of case or claim. The periods vary by state and by type of claim. Most states also employ a “discovery rule,” which provides that the statute of limitations does not “accrue” until such time as the plaintiff knew or should have reasonably known that the injury or property damage has occurred.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
BWB&O’s Los Angeles Partner Eileen Gaisford and Associate Kelsey Kohnen Win a Motion for Terminating Sanctions!
April 25, 2023 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Bremer Whyte Brown & O’Meara, LLP Partner Eileen Gaisford and Associate Kelsey Kohnen for successfully arguing and winning a Motion for Terminating Sanctions for BWB&O’s client, a hotel in Los Angeles County. The court granted BWB&O’s Motion for Terminating Sanctions and Plaintiff’s Complaint was dismissed with prejudice.
Plaintiff filed a complaint alleging she sustained multiple injuries after a slip and fall in a hotel. Plaintiff’s complaint alleged that BWB&O’s client was negligent, careless, and reckless in the ownership, care, control, and maintenance of the premises. BWB&O aggressively defended its client and filed several motions, arguing Plaintiff’s conduct abused the discovery process. The Court sided with BWB&O and granted its Motion for Terminating Sanctions, and the lawsuit was dismissed with prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
The 2021 Top 50 Construction Law Firms™
June 14, 2021 —
Cybele Tamulonis - Construction ExecutiveVaccination rates continue to rise, mandates are loosening for returning to work and school, and a $2 trillion infrastructure bill is looming on the horizon, but contractors remain cautious and counseled by the legal experts who thrive in the complex field of construction law.
According to the latest report by the Bureau of Labor Statistics, construction employment numbers did not move much in April despite an increased demand for housing and a recovering economy. Due to continued fallout from the pandemic—and what seems like no end in sight for the rising costs of materials—contractors have been turning to construction law firms to navigate delayed projects, interpret contract language, assist in risk mitigation and ensure the road ahead is paved with understandable and protective clauses.
For the 2021 survey for the annual U.S. ranking of The Top 50 Construction Law Firms™, Construction Executive’s editorial team reached out to dozens of attorneys at the nation’s best construction law firms to learn how the legal landscape is changing, as well as how legal teams are aiding clients with sharpening contract language and pivoting in response to challenges in the wake of the COVID-19 pandemic.
Reprinted courtesy of
Cybele Tamulonis, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Vinny Testaverde Alleges $5 Million Mansion Riddled with Defects
January 15, 2014 —
Melissa Zaya-CDJ STAFFFormer Tampa Bay Buccaneers quarterback Vinny Testaverde and his wife Mitzi filed suit December 20, 2013 claiming breach of contract and building code violations on their $5 million, Odessa, Florida mansion, according to the Tampa Tribune. The Testaverdes allege that their six-year old, 6,700 square foot home has multiple defects, including “wet floors and walls when it rains and a grand staircase leading to the front door that is sinking, taking with it two columns that support the porch roof,” The Tampa Tribune reports.
Gray Homes of Tampa Bay were contracted by the couple to build their mansion on Lake Keystone. The Tampa Tribune stated that several months before filing suit, the Testaverdes sent a certified letter to Gray Homes stating they had uncovered “a series of defects.” According to the article, Gray Homes had not yet responded to the Tampa Tribune’s message asking for a comment.
Read the court decisionRead the full story...Reprinted courtesy of
Jersey City, New Jersey, to Get 95-Story Condo Tower
January 21, 2015 —
David M. Levitt and Terrence Dopp – BloombergA Chinese developer is planning a 95-story condominium tower for the Jersey City, New Jersey, waterfront that would be the tallest building in the state.
China Overseas America Inc. plans to construct the 950-foot (290-meter) building at 99 Hudson St., according to a statement on Tuesday from Mayor Steven Fulop. The skyscraper, with 760 for-sale dwellings, would surpass the Goldman Sachs Group Inc. tower two blocks to the south, which is 781 feet tall, according to the statement.
Mr. Levitt may be contacted at dlevitt@bloomberg.net; Mr. Dopp may be contacted at tdopp@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
David M. Levitt and Terrence Dopp, Bloomberg
Committeewoman Requests Refund on Attorney Fees after Failed Legal Efforts
February 10, 2014 —
Beverley BevenFlorez-CDJ STAFFWest Deptford, New Jersey township redevelopment counsel Mark Cimino had spent a year arguing that the city should receive a $4 million reduction in construction costs due to “inadequate documentation provided by the bank, as well as receipts showing disbursement had ‘improperly’ been made toward uses other than construction,” according to a December 30th 2013 article in the South Jersey Times. However, a state appellate court upheld the ruling that “the township had no basis” to request the reduction.
Now, Committeewoman Denice DiCarlo is “seeking a $10,000 refund on the attorney fees paid” to Cimino, the South Jersey Times reported on February 6th. “This entire matter has been a monumental waste of tax dollars, and I am angry that the entire township committee was misled by Mr. Cimino and induced to believe we had any reasonable chance of recovering loan proceeds from this lawsuit,” DiCarlo stated in a letter to Mayor Raymond Chintall.
Not all committee members agree with DiCarlo. Committeeman Sam Cianfarini told South Jersey Times that “he still believed Fulton Bank owed it to West Deptford to answer for any funds put toward anything other than construction.”
Cimino declared “that both the lawsuit and appeal were valid,” according to the February 6th article. He “accused DiCarlo of ‘playing politics.’”
Read the full story, December 30th Article...
Read the full story, February 6th Article... Read the court decisionRead the full story...Reprinted courtesy of
Design-Assist Collaboration/Follow-up Post
March 16, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCShortly after posting the blog article “Design-Assist an Ambiguous Term Causing Conflict in the Construction Industry,” I received an email from Brian Perlberg, the Executive Director and Senior Counsel for ConsensusDocs. He brought two ConsensusDocs forms to my attention: ConsensusDocs 541 Design Assist Addendum and ConsensusDocs 300 Integrated Form of Agreement (IFOA). In the ConsensusDocs model of “design-assist,” the lead design professional retains design responsibility but benefits from input and consultation from the construction team during design development. By contrast, in the design-build project delivery method, the constructor assumes design responsibility and liability for either the entire project design (design-build) or just a component of the design (delegated design).
The ConsensusDocs 541 document goal is to provide “accurate information concerning program, quality, cost, constructability and schedule from all parties.” It provides a range of standard and optimal services during design development that essentially shifts the curve of selecting the construction manager (CM) and most importantly, special trade contractors, to much earlier in the process, perhaps as soon as the owner’s program is developed. This opens a world of possibilities for the design and construction team to collaborate early and often. The design professional, however, does not abdicate its design responsibility or authority in this process. The ultimate goal is to end the all-too-common wasteful cycle of design and redesign that is common in construction projects.[1]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Risk Transfer: The Souffle of Construction Litigation
December 13, 2022 —
Alexa Stephenson & Ivette Kincaid - Kahana FeldWho does not love a good souffle?! Enthusiasts will know that a great souffle is not something you can obtain quickly. Rather, it is common in restaurants to order the souffle as dessert at the beginning of the meal because it takes an hour to bake. Risk transfer – like a good souffle – also requires planning, preparation, and the right ingredients.
In construction litigation, attorneys are often not retained until after the project has been completed for several years as the dispute between the homeowner and the general contractor or developer took time to escalate to formal litigation. A significant part of defense counsel’s legal analysis involves assessing and evaluating risk transfer opportunities. For example, in the case of a general contractor or developer who did not self-perform the construction work but instead retained subcontractors to do so, counsel will assess if risk can be transferred from the general contractor or developer to the subcontractors who performed the work which the homeowners allege is defective. In other words, a developer or general contractor can reduce their risk (i.e. liability and money owed) by transferring said risk (i.e. pointing the finger at) to a third party.
Sounds easy, right? Unfortunately, just like the souffle making process, it is easier said than done. This task can be exceedingly difficult in the absence of contracts that contain strong indemnity and insurance provisions – the essential ingredients to effect risk transfer. Worry not! We have provided “baking” instructions for you below to help you get a great risk transfer souffle time and again.
Reprinted courtesy of
Alexa Stephenson, Kahana Feld and
Ivette Kincaid, Kahana Feld
Ms. Stephenson may be contacted at astephenson@kahanafeld.com
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of