Competitive Bidding Statute: When it Applies and When it Does Not
April 15, 2024 —
Mason Fletcher - Ahlers Cressman & Sleight PLLCThe University of Washington (UW), a public university, aimed to secure a real estate developer for a new building on its campus. The proposal involved an 80-year ground lease (the “Lease”), and developers submitted bids. The selected developer would demolish an existing building, construct a new one, own it during the Lease at its own cost, and UW would lease back a portion, with ownership reverting to UW at the Lease’s end. Alexandria Real Equities, Inc. (ARE) was a finalist but ultimately was not selected, and the Lease was awarded to Wexford Science and Technology, LLC (Wexford). As a result, ARE filed suit against UW asserting three claims: 1) UW lacked authority to execute the Lease, 2) UW didn’t follow required competitive bidding procedures, and 3) UW’s developer selection process was arbitrary and capricious. None of these claims were successful and ARE appealed.
Division II of the Washington Court of Appeals affirmed in Alexandria Real Estate Equities Inc. v. Univ. of Wash., __ Wn. App. __, 539 P.3d 54 (2023), a published decision. The Court concluded, based on the facts in that case, that because construction was not publicly funded, UW did not have to follow competitive bidding requirements that were laid out in a statute relevant to state universities. Still, the Court applied the “bright-line cutoff point” that prohibits disappointed bidders from challenging an award once a contract has been executed. See Dick Enterprises, Inc. v. Metro. King County, 83 Wn. App. 566, 572, 922 P.2d 184 (1996).
Read the court decisionRead the full story...Reprinted courtesy of
Mason Fletcher, Ahlers Cressman & Sleight PLLCMr. Fletcher may be contacted at
mason.fletcher@acslawyers.com
2023 Construction Law Update
January 04, 2023 —
Garret Murai - California Construction Law BlogAs we approach 2023 we want to wish you and yours a happy holiday season.
A total of 1,726 bills were introduced during the second half of the 2021-2022 legislative session of which 997 were signed into law. This compares with the 2,421 bills introduced during the first half of the 2021-2022 of which 770 were signed into law. Among the legislation taking effect in 2023 are new laws applying to contractors include new workers’ compensation laws (even if you don’t have employees), a continuation of a record number of new housing affordability laws as well as environmental laws aimed at climate change, and, of course, as we see nearly every year, new procurement authorizations.
Licensing
AB 1747 – Authorizes the Contractors State License Board to issue penalties of up to $30,000 for the willful or deliberate disregard of state or local laws relating to the issuance of building permits.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Revolutionizing Buildings with Hybrid Energy Systems and Demand Response
January 08, 2024 —
Aarni Heiskanen - AEC BusinessA recent study conducted by the Finnish Building Services 2030 group explores the potential technologies and business prospects for adaptable energy systems within buildings.
Building Services 2030 is a Finnish consortium of Aalto University, Tampere University, and 14 industry partners. The consortium has defined a shared vision for the Finnish building service sector and researches topics that help reach the vision. My company is responsible for the group’s communication, so I eagerly read the research reports as they come out.
One of the new reports I found very timely is about the energy flexibility of buildings. The authors are Senior Researcher Juha Jokisalo and Professor Matti Lehtonen from Aalto University. They highlight how the contemporary energy landscape is undergoing a significant transformation.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Delaware Strengthens Jurisdictional Defenses for Foreign Corporations Registered to Do Business in Delaware
April 28, 2016 —
Randall MacTough, Timothy Martin & Christian Singewald – White & Williams LLPThe days of companies being sued in Delaware based solely upon their compliance with Delaware’s registration statutes appear over. Recently, the Delaware Supreme Court, in Genuine Parts Co. v. Cepec[1], held that Delaware Courts cannot exercise jurisdiction over a foreign corporation registered to do business in Delaware for claims unrelated to its conduct in Delaware.
In Delaware, foreign corporations must register to do business and designate a registered agent in Delaware to accept service of process to sell its products or services.[2] Since 1988, Delaware has construed these registration laws as foreign corporations’ express consent to general jurisdiction.[3]
Reprinted courtesy of White & Williams LLP attorneys
Randall MacTough,
Timothy Martin and
Christian Singewald
Mr. MacTough may be contacted at mactoughr@whiteandwilliams.com
Mr. Martin may be contacted at martint@whiteandwilliams.com
Mr. Singewald may be contacted at singewaldc@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Home Damaged by Falling Boulders
March 08, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe policy's earth movement exclusion barred coverage for the home damaged by large boulders rolling down from the hillside above. Sullivan v. Nationwide Affinity Ins. Co. of Am., 2021 U.S. App. LEZXIS 628 (10th Cir Jan. 11, 2021).
Plaintiffs' home sustained extensive damage when two or three large builders rolled down a steep hillside and struck the home. The insurer, Nationwide, hired an engineering firm that determined the boulders were not influenced by meteorological conditions such as torrential rain or high winds. The report noted that rockfall hazards existed primarily due to an undercut sandstone outcrop, and evidenced by numerous rocks from rockfall events that scattered Plaintiffs' property.
Based on the report, Nationwide denied coverage under the earth movement exclusion. The exclusion provided Nationwide did "not insure for loss caused directly or indirectly by . . . Earth Movement" and regardless of "whether or not the loss event results in widespread damage or affects a substantial area." The policy further defined "earth movement" to include "landslide . . . or any other earth movement including earth sinking, risking or shifting."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (5/29/24) – Megaprojects on the Rise, Agency Guidance for CRE, and an Upbeat Forecast for Commercial Real Estate Investment
June 21, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, summer travelers seek alternative lodging options, purpose-built wellness real estate investments grow, bonds backed by CRE debt hit are hit with losses, and more!
- Across all property types, purpose-built wellness real estate investment has grown dramatically in recent years, including properties with wellness features as a focus. (Mary Salmonsen, Multifamily Dive)
- The travelers on the road this summer will have different demographics, budgets and reasons for travel and different preferences on accommodations, with more travelers opting for alternative housing options. (Noelle Mateer, Hotel Dive)
- Megaprojects are on the rise, with massive projects, from rail tunnels to computer chip factories, having myriad stakeholders and lengthy timelines that span political administrations. (Julie Strupp, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
California Supreme Court Hands Victory to Private Property Owners Over Public Use
June 21, 2017 —
Sean M. Sherlock - Snell & Wilmer Real Estate Litigation BlogIn 1970 the California Supreme Court held that, under certain circumstances, private property owners impliedly dedicate their property to the public if they permit the public to use it. Gion v. City of Santa Cruz (1970) 2 Cal.3d 29. This holding was controversial, and the next year the California Legislature enacted Civil Code section 1009 limiting the public’s ability to permanently use private property through an implied dedication.
In the 40-plus years since then, the lower courts have wrestled with the issue of whether the statute limiting implied dedication applies only to recreational uses by the public, or also to nonrecreational uses. On June 15, 2017, the California Supreme Court issued its unanimous opinion in Scher v. Burke (June 15, 2017, S230104) ___ Cal.4th ___, holding that the limitations on implied dedication apply to nonrecreational as well as recreational uses. The case is significant because it demonstrates that the Supreme Court will apply the plain language of the state’s statutes to uphold private property rights.
Read the court decisionRead the full story...Reprinted courtesy of
Sean M. Sherlock, Snell & WilmerMr. Sherlock may be contacted at
ssherlock@swlaw.com
A Teaming Agreement is Still a Contract (or, Be Careful with Agreements to Agree)
November 18, 2019 —
Christopher G. Hill - Construction Law MusingsI have discussed teaming agreements in this past here at Construction Law Musings. These agreements are most typically where one of two entities meets a contracting requirement but may not have the capacity to fulfill a contract on its own so brings in another entity to assist. However, these agreements are contracts and are treated as such here in Virginia with all of the law of contracts behind them.
One illustrative case occurred here in Virginia and was decided by the Virginia Supreme Court. That case is CGI Fed. Inc. v. FCi Fed. Inc. While this is not strictly a “construction” case, it helps lay out some of the pitfalls of teaming agreements in general.
In this case, the parties entered into a fairly typical small business (FCI) Big Business (CGI) teaming arrangement for the processing of visas for the State Department. The parties negotiated the workshare percentage (read payment percentage) should FCI get the work and the teaming agreement set out a framework for the negotiation of a subcontract between FCI, the proposed general contractor, and CGI, the proposed subcontractor. After a while working together, FCI submitted a proposal to the State Department and as part of the negotiations of this proposal, the work percentage for CGI was lowered in exchange for some management positions for CGI relative to the work by amendment to the original teaming agreement. However, one day later FCI submitted a proposal to the State Department that not only didn’t include the management positions, but further lowered CGI’s workshare.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com