Key Amendments to Insurance Claims-Handling Regulations in Puerto Rico
September 23, 2019 —
Andres Avila & Richard W. Brown - SDV InsightsPolicyholders in Puerto Rico should be aware of significant benefits provided by recent amendments to the Insurance Code. New rules establish an expedited method of property insurance dispute resolution, mandatory expedited partial payments in the event of catastrophic events, and protection against bad faith claims handling by insurers.
Appraisal Process with a Puerto Rican Twist
A key amendment is the establishment of an appraisal process, widely used for many years in the United States and now adopted in Puerto Rico. Commercial and personal property insurers in Puerto Rico shall include, in their policies, a clause for an appraisal process according to Article 11.150 of the Insurance Code of Puerto Rico, 26 L.P.R.A. § 101 et seq. (“the Code”).
The appraisal process provides both policyholders and insurers the option to submit insurance claims to an impartial umpire if a dispute arises over the value of covered damages or losses. The umpire and appraisers do not have authority to resolve coverage or legal issues. They can only resolve disputes over the quantum claimed for losses already determined to be covered by the insurer. Id. Each party is required to pay its own appraiser’s fees and split equally the fees of the umpire. Id.
Reprinted courtesy of
Andres Avila, Saxe Doernberger & Vita, P.C. and
Richard W. Brown, Saxe Doernberger & Vita, P.C.
Mr. Avila may be contacted at ara@sdvlaw.com
Mr. Brown may be contacted at rwb@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Road Project to Improve Access to Peru's Machu Picchu Site
June 04, 2024 —
C.J. Schexnayder - Engineering News-RecordReaching the Incan citadel of Machu Picchu is historically famous for its difficulty. The site’s remote location was a factor in the Spanish conquistadors overlooking it as they swept Peru for its riches. Archaeologist and politician Hiram Bingham had been seeking another “lost” Incan city when he happened across it in 1911.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Vallagio HOA Appeals the Decision from the Colorado Court of Appeals
August 04, 2015 —
David M. McLain – Colorado Construction LitigationAs highlighted in our most recent post, the Colorado Court of Appeals’ Vallagio decision upheld a declaration provision that prohibited the amendment of a mandatory arbitration clause without the consent of the developer/declarant. Vallagio at Inverness Residential Condominium Association, Inc. v. Metropolitan Homes, Inc., et al., 2015COA65 (Colo. App. May 7, 2015). This case protects a developer/declarant’s ability to arbitrate construction defect claims with a well-crafted declaration that requires declarant consent in order to amend the mandatory arbitration provisions for construction defect actions.
However, the Vallagio ruling still hangs in the balance while the Colorado Supreme Court considers the condominium association’s petition for certiorari review, filed June 18, 2015. In its petition, the association argues that the declarant consent requirement violates public policy and four separate sections of the Colorado Common Interest Act (“CCIOA”).
For instance, the association argued in the courts below that a declarant consent requirement violates section 217 of CCIOA, which governs unit owners’ voting percentage requirements and provides that declarations may not require more than 67% affirmative vote for amendments. The Court of Appeals rejected this argument, reasoning that other provisions of section 217 contemplate consent requirements by parties other than unit owners, such as first mortgagees.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Insurance Policy Provides No Coverage For Slab Collapse in Vision One
August 17, 2011 —
Douglas Reiser, Builders Council BlogThis post will examine whether Division Two of the Washington Court of Appeals properly reversed and remanded several lower court decisions in the case of Vision One LLC v. Philadelphia Indemnity Insurance. In short, and from the perspective of an appellate attorney, the court of appeals got the decision right. Given the rules of contract interpretation and causation in tort claims, there was really no other way the court could have ruled. I understand that from a contractor’s perspective and insurance perspective, the decision seems odd. But from a purely legal standpoint, the decision is well-reasoned and well-supported. Let me explain.
Background
First, here are the facts in a nutshell. Vision One is a construction company that undertook to construct a condo complex in Tacoma. Vision then contracted with D&D Concrete to pour a concrete slab for a section of the foundation. To shore the concrete slab, D&D further contracted Berg Equipment to provide necessary equipment to stabilize the structure. Well, something down the line went wrong. The shoring failed and the slab collapsed, causing a great deal of damage.
Read the full story…
Read the court’s decision…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
City of Birmingham Countersues Contractor for Incomplete Work
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFBack in December of 2013, WVTM News reported that Chris Woods, a contractor, filed a lawsuit against the City of Birmingham, Alabama, demanding $1.5 million for the West Police Precinct and two other projects he had been contracted on. However, “Birmingham claimed Woods was fired for not completing projects on time and other contract breaches.”
On March 7th, WVTM News reported that the City of Birmingham has filed a counterclaim against Woods, alleging that he “owes $1.2 million for incomplete work.” The city listed his “inability to meet specific construction deadlines and finish either project on time as factors for his termination.” Woods, however, blamed the city for delays, citing multiple design changes requested by Birmingham.
The city’s counterclaim also alleged that “Star Insurance Company, ‘identified major, numerous defects in the work that Woods had performed prior to the termination of the West Precinct Project.’”
Read the full story, December 2013 Article...
Read the full story, March 2014 Article... Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Clarifies Deadline to File Anti-SLAPP Motions in Light of Amended Pleadings
July 02, 2018 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogCalifornia’s “anti-SLAPP” (“SLAPP” is an acronym for strategic lawsuit against public participation) statute—codified at California Code of Civil Procedure section 425.16 et seq.—is the primary vehicle for defending against any action involving petitioning or free speech. The statute was designed to provide an early and fast summary judgment-like procedure to allow defendants and cross-defendants to file a motion to dismiss either an entire complaint, specific causes of action, or even just portions of a cause of action, and to require the plaintiff to respond before conducting discovery. By facilitating an early challenge to a plaintiff or cross-complainant’s claims, the anti-SLAPP statute allows the responding party to avoid the costs and delay that chill the exercise of constitutionally protected rights.
Under California Code of Civil Procedure section 425.16(f), an anti-SLAPP motion must be filed “within 60 days of the service of the complaint . . . .” But what if the plaintiff files an ameded complaint? In Newport Harbor Ventures, LLC v. Morris Cerullo World Evangelism (2018) 4 Cal.5th 637, the California Supreme Court held that the 60-day timeline runs from the date a complaint is filed with the cause(s) of action challenged in the anti-SLAPP motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com
Preparing For the Worst with Smart Books & Records
November 07, 2012 —
CDJ STAFFContractors are often too caught up in keeping the wheel of business churning to recognize deficiencies in how their records are managed. Working hard and working often tend to leave little time for consideration of your documents. But all too often I see the unthinkable, a contractor gets into trouble and has to call on its surety for help. At that point, you might finally get your first dose of reality about your records – and it can cost you.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas Reiser of Reiser Legal LLC.Mr. Reiser can be contacted at
info@reiserlegal.com
Appeals Court Affirms Carrier’s Duty to Pay Costs Taxed Against Insured in Construction Defect Suit
November 03, 2016 —
Jesse Howard Witt – The Witt Law FirmOne of the key reasons for builders to maintain liability insurance is to cover the cost of hiring defense counsel and paying litigation costs in the event of a construction defect lawsuit. If a builder loses a lawsuit, it will typically be responsible for paying the plaintiff’s litigation costs. Today, the Colorado Court of Appeals clarified that the “supplementary payments” section of a standard Commercial General Liability (CGL) insurance policy covers such costs, even if the carrier has reserved the right to dispute whether it has a duty to indemnify the actual damages awarded. This may seem counter-intuitive, insofar as a carrier may owe costs even if it does not cover the underlying loss, but the court’s decision is consistent with the plain language of the CGL form that most carriers use.
Reprinted courtesy of
Jesse Howard Witt, The Witt Law Firm
Mr. Witt may be contacted at his website www.witt.law