Should CGL Insurer have Duty to Defend Insured During Chapter 558 Notice of Construction Defects Process???
September 01, 2016 —
David Adelstein – Florida Construction Legal UpdatesDoes a CGL insurer have a duty to defend its insured-contractor during Florida Statutes Chapter 558 notice of construction defects pre-suit process? This answer is currently undecided and will be up to the Florida Supreme Court to decide. (It is on appeal stemming from a federal district court saying that an insurer does not have a duty to defend its insured-contractor in the 558 process based on the definition of the word “suit” in the CGL policy.)
Why is this an important issue?
The 558 pre-suit notice of construction defects process is designed to facilitate an avenue for construction defect lawsuits to get resolved without having to file a lawsuit or, at least, have issues narrowed before a lawsuit needs to be filed. (Check here for a summary of the 558 process.) It requires pre-suit notifications so that implicated parties can become aware of the defects and have an opportunity to inspect the defects / damage, test the defects / damage, and respond to the notice of construction defects; it provides an avenue for beneficial pre-suit discovery. Through participating in the 558 process, the contractor and/or design professional (and those downstream from them) can: (i) offer to remedy the defect, (ii) settle the defect, whether through money or a combination of money and repairs, (iii) dispute the defect, or (iv) advise that available insurance proceeds will be determined by its liability insurer. See Fla. Stat. s. 558.004.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Where Standing, Mechanic’s Liens, and Bankruptcy Collide
September 17, 2018 —
Christopher G. Hill - Construction Law MusingsI have spoken often about mechanic’s liens and the implications of such liens as they relate to bankruptcy here at Construction Law Musings. A recent case out of Loudoun County, Virginia added another wrinkle to this discussion, that of standing and what happens on conveyance of the property and what interest in the property is required to allow a party to seek removal of the mechanic’s lien.
In Leesburg Bldg. P’rs LLC v. Mike Berger Inc. the Loudoun County Circuit Court faced the following scenario. Leesburg Building Partners developed certain condominiums and hired Lansdowne Construction to perform the work as general contractor and paid Landsdowne in full for the work. Lansdowne hired Mike Berger, Inc. (“MBI”) to perform concrete work for the project. Landsdowne didn’t pay MBI approximately $48,000.00 and subsequently filed for bankruptcy. MBI, seeking to protect it’s interest in the money it was owed, recorded a mechanic’s lien on the property. Leesburg Building Partners filed an action to declare the lien invalid and have it removed from the property based upon its “payment defense” and the fact that it had paid Landsdowne in full. A relatively simple scenario and one that has been discussed before here at Musings. Not so fast. . .
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Anatomy of a Construction Dispute- An Alternative
February 05, 2015 —
Christopher G. Hill – Construction Law MusingsOver the past three weeks, I’ve discussed three “stages” of a construction dispute from the claim, to how to increase the pressure for payment, to the litigation. While these three steps are all too often necessary tools in your construction collection arsenal, they are expensive and time consuming. No well run construction business can or should budget for litigation. The better practice would be to engage a construction attorney early in the process and avoid the dispute altogether if possible. Unfortunately, even the best of planning can lead to the need to hire a construction lawyer for the less pleasant task of assisting you in getting paid.
This post is about an alternative to the scorched earth of stage 3 of the process that can and should be at least considered either before or after the complaint or demand for arbitration has been filed. I am of course speaking about voluntary mediation. Why did I emphasize “voluntary?” Because to me mandatory mediation (as required in many construction contracts) is a bit like forced volunteerism, it is something that the parties will go through to “check a box” but will not have their hearts in it. Remember, by the time the mandatory mediation clause kicks in, the parties are likely at an impasse in their construction dispute and are ready to fight. Being forced to mediate, especially from the party seeking payment, can (and in my experience often does) make the parties just go through the motions at best and be hostile to the process at worst. Neither of these attitudes are conducive to resolving a dispute.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
North Carolina Learns More Lessons From Latest Storm
October 16, 2018 —
Pam Radtke Russell - Engineering News-RecordThere’s no big wall planned to protect North Carolina’s coast from storm surge. There’s no massive tunnel system proposed to keep floodwaters away from populated areas. There are no grant-funded resilience competitions to help the state plan to manage water more effectively.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Texas Central Wins Authority to Take Land for High-Speed Rail System
October 03, 2022 —
Barclay Nicholson & Erica Gibbons - Sheppard Mullin Construction & Infrastructure Law BlogMove over luxury bus lines and quick flights. Central Texans should be on the lookout for bulldozers and train stops. On June 24, 2022, the Supreme Court of Texas held that Texas Central Railroad & Infrastructure, Inc. and related entities (collectively “Texas Central”) have eminent domain authority to acquire property for a proposed high-speed rail system between Dallas and Houston.
[1] Specifically, the Court held that the corporation qualifies as an “interurban electric railway company” under the Texas Transportation Code. This ruling grants Texas Central the broad condemnation authority to procure land for the project.
Texas Central has Statutory Authority to Take Land
The plaintiff in the matter, a farm owner with property south of Dallas along the proposed path of the bullet train, challenged the companies power to condemn land. The landowner’s declaratory judgment action challenged Texas Central’s eminent-domain authority. Under Texas law, condemnation power must be conferred by the legislature, either expressly or by necessary implication.
[2]
Here, Texas Central was created for the purpose of constructing, acquiring, maintaining, or operating lines of electric railway between Texas municipalities. The Court found that Texas Central is engaged in activities to further that purpose. Therefore, the Court concluded, that although legislators did not contemplate high-speed railways at the time of drafting the Transportation Code, Texas Central nonetheless qualified as “interurban electric railway companies” under the statute.
Reprinted courtesy of
Barclay Nicholson, Sheppard Mullin and
Erica Gibbons, Sheppard Mullin
Mr. Nicholson may be contacted at bnicholson@sheppardmullin.com
Ms. Gibbons may be contacted at egibbons@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Shimmick Gets Nod for Second Pilot Pile at Settling Millennium Tower
December 13, 2021 —
Nadine M. Post - Engineering News-RecordAfter the successful installation of a 24-in.-dia permanent pilot pile at the troubled foundation upgrade of the settling Millennium Tower in San Francisco, the Dept. of Building Inspection (DBI) has given Shimmick Construction Co. permission to install a second pilot pile, beginning Dec. 1.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
“Bee” Careful: Unique Considerations When Negotiating a Bee Storage Lease Agreement
March 27, 2019 —
Colton Addy - Snell & Wilmer Real Estate Litigation BlogAs demand for commercial bees used to pollinate crops (such as almond trees) has grown, so has the demand for facilities to store bees. Entering a lease agreement for the storage of live bees presents some unique issues the parties need to consider when negotiating the lease agreement.
Don’t Bee Short-Sighted: Bees are often transported to different areas depending on the time of year, which means bees are not stored in the same facility all year. The lease agreement will often only provide for the storage of bees during the season when the bees are used for pollination in that particular area, but that does not mean the parties must limit the term of the lease agreement to a single season. The parties may consider entering into a lease agreement for multiple years that only applies during the pollination season each year.
Bee Mindful of the Rent: Whereas the parties usually base rent in a typical commercial lease agreement off of the square footage of space the tenant uses in the premises, it often makes more sense for both parties negotiating a lease for the storage of bees to base the rent on the number of beehives or bee colony boxes stored at the facility. Basing the rent on the number of beehives or bee colony boxes provides the landlord with flexibility in storing the bees of multiple tenants in the same facility, and it can give the tenant flexibility with the number of bees it may need stored at the facility in any given season. With such a rental arrangement, a landlord should consider asking for a commitment from the tenant to deliver at least a certain number of beehives or colonies for storage, and the tenant should consider asking for a commitment from the landlord to reserve space in the facility for at least that same number of beehives or colonies as the tenant is giving a commitment for. Additionally, the parties will need to determine when rent will be paid. In a general commercial lease agreement, rent is usually paid monthly. With a bee storage lease agreement, however, a landlord may want to require the tenant to pay all of the rent for the season upon delivery of the bees, and the landlord may also want the tenant to pay a percentage of the rent to reserve space in the facility prior to delivery of the bees. This allows the landlord to get an early indication of what space in the facility it will have available in the facility for other tenants given the somewhat flexible rental arrangement of the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Colton Addy, Snell & WilmerMr. Addy may be contacted at
caddy@swlaw.com
Mortgage Battle Flares as U.K. Homebuying Loses Allure
January 28, 2015 —
Neil Callanan and Richard Partington – BloombergU.K. banks, which spent six years repairing their balance sheets after the 2008 property crash, want to advance more credit to homebuyers. Borrowers aren’t as enthusiastic.
Cheap funding costs and low default rates have made homebuyers attractive to lenders in recent years, boosting returns for companies such as Nationwide Building Society and Lloyds Banking Group Plc. (LLOY) Now, with demand for property cooling, they’re having to fight harder for business. Interest rates on the most popular mortgages fell to record lows in December, according to the Bank of England.
Mr. Callanan may be contacted at ncallanan@bloomberg.net; Mr. Partington may be contacted at rpartington@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan and Richard Partington, Bloomberg