Lost Productivity or Inefficiency Claim Can Be Challenging to Prove
May 02, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the most challenging claims to prove is a lost productivity or inefficiency claim. There is an alluring appeal to these claims because there are oftentimes intriguing facts and high damages. But the allure of the presentation of the claim does not compensate for the actual burden of proof in proving the lost productivity or inefficiency claim, which will require an expert. And they really are challenging to prove.
Don’t take it from me. A recent Federal Claims Court opinion, Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, (Fed.Cl. 2022), that I also discussed in the preceding
article, exemplifies this point.
To determine lost productivity or inefficiency, the claimant’s expert tried three different methodologies.
First, the expert looked at industry standard lost productivity factors such as those promulgated by the Mechanical Contractor’s Association. However, the claimant was not a mechanical contractor and there is a bunch of subjectivity involved when using these factors. The expert decided not to use such industry standard factors correctly noting they provide value when you are looking at a potential impact prospectively, but once you incur actual damages and have real data, it is not an accurate measure.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
IoT: Take Guessing Out of the Concrete Drying Process
February 06, 2019 —
Aarni Heiskanen - AEC BusinessFlooring, tiling, or painting on a concrete surface that is insufficiently dry can end up being a disaster. An experimental project recently used IoT sensors and AI to determine when it is safe to start finishing concrete surfaces.
Haste and Imperfect Conditions Lead to Failure
To successfully first cure and then dry concrete requires specific conditions. You need to maintain a temperature higher than 10°C and a relative humidity of greater than 80 percent in the concrete.
Once the concrete is hardened, you have to make sure that it is dry enough for finishing. Typically, the relative humidity should not exceed 82 percent. Some flooring materials require a humidity of less than 75 percent for successful application.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New Jersey Court Upholds Registration Requirement for Joint Ventures Bidding on Public Works Contracts
December 16, 2023 —
Nicholas J. Zaita & Brian Glicos - Peckar & Abramson, P.C.Introduction
In a matter of “first impression,” on November 30, 2023, the Appellate Division affirmed the New Jersey Superior Court decision in
Ernest Bock & Sons-Dobco Pennsauken Joint Venture v. Township of Pennsauken and Terminal Construction Corp., finding that the New Jersey Public Works Contractor Registration Act, N.J.S.A. 34:11-56.48 to -56.57 (“PWCRA” or the “Act”), applies to a joint venture formed for the sole purpose of bidding on a public works contract. Therefore, the Court held that the PWCRA requires any joint venture bidding on public works projects in New Jersey to be registered under the Act at the time of bid submission. Accordingly, the Township of Pennsauken acted within its authority and properly rejected the bid submission of the Ernest Bock & Sons-Dobco Joint Venture which was not registered under the Act in the name of the joint venture at the time of its bid submission, despite the individual members of the joint venture being registered.
Reprinted courtesy of
Nicholas J. Zaita, Peckar & Abramson, P.C. and
Brian Glicos, Peckar & Abramson, P.C.
Mr. Zaita may be contacted at nzaita@pecklaw.com
Mr. Glicos may be contacted at bglicos@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Balancing Cybersecurity Threats in Smart Cities: Is the Potential Convenience of “Smart” Intersections Worth the Risk?
September 02, 2024 —
James P. Bobotek & Brian E. Finch - Gravel2Gavel Construction & Real Estate Law BlogThe term “smart cities” has become popular parlance for municipalities’ attempts to enhance delivery of urban services and infrastructure through information and communications technology. While they may conjure images of neon-lit high rises or streetscapes populated by sleek, hovering vehicles, a bit like the 1960s-era The Jetsons cartoon envisioned our high-tech future, the reality of smart cities has begun to emerge in more subtle, less glamourous forms. Cities tend to focus on wastewater monitoring, traffic control and energy distribution technologies in their efforts to become incrementally “smarter.”
Smart cities lean heavily on automation, internet connectivity and the Internet of Things (IoT)—including smartphones, connected cars and a host of web-based appliances and utilities—to boost the delivery and quality of essential urban services and infrastructure like transit, sanitation, water, energy, emergency response and more. Successful smart cities need infrastructure that supports such connectivity, and they pull data from hundreds, or even thousands, of sensors that can be used to analyze and shepherd the direction of resources.
Reprinted courtesy of
James P. Bobotek, Pillsbury and
Brian E. Finch, Pillsbury
Mr. Bobotek may be contacted at james.bobotek@pillsburylaw.com
Mr. Finch may be contacted at brian.finch@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Rhode Island Closes One Bridge and May Have Burned Others with Ensuing Lawsuit
October 07, 2024 —
Bill Wilson - Construction Law ZoneThe state of Rhode Island recently filed a lawsuit against 13 companies that provided design, construction, and inspection services over the past ten years (the extent allowed by the applicable statute of limitations) to the Washington Bridge, which carries I-195 between East Providence and Providence. The bridge was abruptly closed in December 2023 following the discovery of alleged fractured steel tie-downs critical to the bridge’s stability and additional deterioration in cantilever beams throughout the bridge. Before the closure, approximately 90,000 vehicles per day traveled over the bridge.
The complaint alleges that the defendants, the majority of which are experienced, industry-leading firms in their respective fields, were negligent and breached their respective contracts with the State. The State contends that every company that worked on the bridge over the past ten years missed the serious structural conditions alleged. The lawsuit also claims that the State has suffered millions of dollars of damages since the bridge was closed and seeks indemnity and contribution from all defendants to the extent that the State may be liable to third parties in the future.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLP
Kushner Company Files Suit Against Jersey City Over Delays to Planned Towers
July 10, 2018 —
Associated Press - Engineering News-RecordJERSEY CITY, N.J. (AP) — Jared Kushner's family company has filed a lawsuit against a New Jersey city, saying it forced the delay of a major twin-tower project due to "political animus" toward President Donald Trump.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR staff may be contacted at
ENR.com@bnpmedia.com
Indictments Issued in Las Vegas HOA Scam
January 22, 2013 —
CDJ STAFFA federal grand jury has indicted eleven individuals involved in the Las Vegas homeowners association scam. Leon Benzer, Keith Gregory, and Barry Levinson were all indicted for their roles in the scam, where conspirators took over homeowners associations in order to profit from construction defect suits. According to the Las Vegas Review Journal, all eleven were charged with conspiracy to commit mail and wire fraud. Mr. Levinson's license to practice law has been suspended due to an investigation that he misappropriated client funds. Mr. Benzer has been described as the "mastermind" of the scam.
Twenty-eight defendants have plead guilty, with all but one agreeing to cooperate with investigators. The report quotes William C. Woerner, the acting special agent in charge of the FBI in Las Vegas, as saying that "today's indictment demonstrates the continued commitment of the FBI and its law enforcement partners to identify and root out public corruption at all levels."
Read the court decisionRead the full story...Reprinted courtesy of