Consumer Confidence in U.S. Increases More Than Forecast
August 26, 2015 —
Victoria Stilwell – BloombergConsumer confidence climbed more than forecast in August to the second-highest level in eight years as Americans held more favorable views of the labor market.
The Conference Board’s index rose to 101.5 this month from a revised July reading of 91, the New York-based private research group said Tuesday. The gauge exceeded the highest estimate in a Bloomberg survey of economists, whose median forecast was 93.4. The cutoff date for the survey was Aug. 13, before the recent stock-market sell-off.
Americans remained emboldened by job gains, cheaper gasoline and rising home prices in the period leading up to a slump in stock prices as global financial markets took a turn for the worse. The risk for the economy is that households will reassess their spending plans as they wait for evidence the U.S. expansion can withstand such shocks.
Read the court decisionRead the full story...Reprinted courtesy of
Victoria Stilwell, Bloomberg
Do We Need Blockchain in Construction?
June 22, 2020 —
Cristina Savian - AEC BusinessBlockchain technology claimed to have the potential to disrupt many aspects of how companies do business. And like other emerging technologies, I have been exploring its uses, benefits and assessing its potential opportunities in the construction industry. If like me, you have been wondering what it is and if its applications are limited to financial services and cryptocurrencies; you will be pleasantly surprised to discover that it has a lot more applications with exciting opportunities for our sector too.
Blockchain could have a significant impact on our industry. In writing this article I have discovered that the Australian government is full steam ahead, that many organisations are currently building their own blockchain networks and that it is something that businesses right across the built environment should be preparing for now. But more on that soon, first we need to define what blockchain is.
Read the court decisionRead the full story...Reprinted courtesy of
Cristina Savian, AEC Business
Is a Text a Writing?
June 10, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCIs a text message a writing? Project communication is constantly evolving, and text messages are an increasingly common way teams share pictures, video, and provide project updates. When texting is part of the communication flow on a project, contractors and owners might text approvals for extra work, notices of changed conditions, or other information that could be a basis for a change order.
In a text exchange about a compensable event, the notice, reply, and approval are all saved on the phone. But contracts often contain specific requirements for a contractor or subcontractor to request changes and authorization to proceed may be specifically required in writing.
For example, the Associated General Contractors of Washington – 2018 Standard Subcontract says the “Subcontractor shall make no claims for extras unless the same shall be agreed upon
in writing by Contractor prior to performance of any such extra work.” (emphasis added).
The AGC subcontract doesn’t define “writing,” so the subcontractor and contractor might wonder if a text message exchange about a potentially compensable event was an “agreement in writing.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
Firm Sued for Stopping Construction in Indiana Wants Case Tried in Germany
October 16, 2013 —
CDJ STAFFGetrag Transmission, a German firm, is being sued by a Detroit-based construction firm that Getrag had hired to build a factory in Indiana. When a court gave the go-ahead to Walbridge Construction for the suit, Getrag appealed, stating that the case should be held in German so that Getrag officials do not have the expense of traveling to Indiana.
Getrag was building the plant, which would have cost $350 million, as part of a partnership with Chrysler. Chrysler dropped from the project after filing for bankruptcy. Shortly afterward, Getrag also filed for bankruptcy.
Walbridge is seeking $118.5 million due to expenses incurred with subcontractors. Chrysler has announced its intention of finishing the plant, which they estimate will cost about $162 million. Once complete, the plant will employ about 850 workers.
Read the court decisionRead the full story...Reprinted courtesy of
When Is a Project Delay Material and Actionable?
January 11, 2022 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogWelcome to 2022! This year, the construction industry will undoubtedly reflect on the last two years as unprecedented times plagued by construction project delays. The COVID-19 pandemic contributed to suspension of work and closure of construction projects worldwide in 2020. The end of 2021 brought additional delays caused by an inexplicable clog in the supply chain of construction materials. The combined impact of these events on project milestones and completion deadlines led our clients to ask, with unusual and particular urgency, who is liable for such delays and how do contracting parties lessen the consequences from such unexpected and uncontrollable delays.
Granted that project delays are nothing new or unusual. They were common enough before inflation caused shipping complications and pandemic decimated the construction labor force. All delays, whatever the source, variably cause loss to all players on a construction project. But not all delays matter when it comes to claims and remedies available to the contracting parties in dispute resolution, where the determinative focus is on material delays impacting the entire project and on delays the claimant can credibly prove.
Most, if not all, jurisdictions interpret actionable delays from the contract documents for the project. The contract is definitely where you should start before pursuing any delay remedies. Delay remedies may be a time extension only, or a time extension plus your additional general conditions. Some delay remedies may be barred by the contract’s express terms and may be enforced adversely by the courts when such contract terms are indisputable. See Quinn Constr. v. Skanska USA Bldg., Inc., 730 F. Supp. 2d 401, 411 (D.C. Pa. 2010) (enforcing the subcontractor’s contractual waiver of claims for delay and disruption damages). On the other hand, delay damages that are expressly allowed by the contract—like overtime necessitated by the delays—are usually actionable and recoverable. Id. However, not only the contract terms, but applicable law, may affect the outcome.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com
First Look at Long List of AEC Firms Receiving PPP Loans
July 20, 2020 —
Tom Ichniowski & Scott Blair - Engineering News-RecordThousands of construction and design firm from all parts of the U.S. appear on lists of companies that have received federal Paycheck Protection Program forgivable loans, according to federal documents just made public.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record and
Scott Blair, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Mr. Blair may be contacted at blairs@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Triple Points to the English Court of Appeal for Clarifying the Law on LDs
July 01, 2019 —
Vincent C. Zabielski & Julia Kalinina Belcher - Gravel2GavelCan an employer recover liquidated damages (LDs) from a contractor if the contract terminates before the contractor completes the work?
Surprisingly, heretofore, English law provided no clear answer to this seemingly straightforward question, and inconsistent case law over the past century has left a trail of confusion. Given the widespread use of English law in international construction contracts, this uncertainty had gone on far too long.
The good news is that drafters of construction contracts throughout the world can now have a well-deserved good night’s sleep courtesy of the English Court of Appeal’s March 2019 decision in Triple Point Technology, Inc. v PTT Public Company Ltd [2019] EWCA Civ 230.
The Triple Point case concerned the delayed supply by Triple Point (the “Contractor”) of a new software system to employer PTT. The contract provided for payments upon achievement of milestones, however order forms incorporated into the contract set out the calendar dates on which fixed amounts were payable by PTT, resulting in an apparently contradictory requirements on when payment was due. Triple Point achieved completion (149 days late) of a portion of the work milestones, and were paid for that work. Triple Point then sought payment for the work which was not yet completed, relying on the calendar dates in the order forms rather than achievement of milestone payments. Things got progressively worse as PTT refused payment, Triple Point suspended the work for PTT’s failure to pay, PTT terminated the contract and then appointed a new contractor to complete the work.
Reprinted courtesy of
Vincent C. Zabielski, Pillsbury and
Julia Kalinina Belcher, Pillsbury
Mr. Zabielski may be contacted at vincent.zabielski@pillsburylaw.com
Ms. Belcher may be contacted at julia.belcher@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
KF-103 v. American Family Mutual Insurance: Tenth Circuit Upholds the “Complaint Rule”
May 12, 2016 —
Adria Robinson – Colorado Construction LitigationIn Colorado, the “complaint rule” requires insurance carriers to provide a defense to its insured when the allegations contained in the complaint allege any set of facts that may fall within an insurance policy. Some insurers have pushed back on this rule arguing that it may cause an insurer to exercise its duty to defend although the underlying facts ultimately do not fall within the policy.
In KF 103-CV, LLC v. American Family Mutual Insurance Company, 2015 WL 6517782, the Tenth Circuit of the United States Court of Appeals upheld the complaint rule. In its decision, the Tenth Circuit cited several Colorado state court rulings recognizing the courts’ intent to incentivize insurers to defend policies that may facially fall within the terms of the policy. Where there is uncertainty about coverage, the Tenth Circuit cited a Colorado Supreme Court case stating, “[t]he appropriate course of action for an insurer who believes that it is under no obligation to defend, is to provide a defense to the insured under the reservation of its rights.”
Read the court decisionRead the full story...Reprinted courtesy of
Adria Robinson, Higgins, Hopkins, McLain & Roswell, LLCMs. Robinson may be contacted at