Beverley BevenFlorez-CDJ STAFFBuilder analyzed U.S. cities with populations of half a million or more and then filtered further with cities that have a “median new home closing price under $250,000, a first mortgage rate below 4 percent for new homes, and a median new home price per square foot below $125.”
Topping the list was El Paso, Texas with the lowest median price ($168,600). Fifth on the list was San Antonio-New Braunfels, Texas with a median price of $230,400.
Read the court decisionRead the full story...Reprinted courtesy of
Suing the Lowest Bidder on Public Construction Projects
September 17, 2015 —
Craig Martin – Construction Contractor AdvisorThe California Court of Appeals has allowed the second lowest bidders on public construction projects to sue the lowest bidder where it appears that the lowest bidder was only the lowest because it paid its employees less than the established prevailing wage. This is a novel theory for recovery, but may provide for an opportunity to challenge improperly low bids.
Background
Between 2009 and 2012, American Asphalt outbid two asphalt companies on 23 public works projects, totaling nearly $15 million. The two asphalt companies sued American Asphalt alleging that they were the second lowest bidder all 23 construction projects and they would have been the lowest had American Asphalt paid its employees the required prevailing wage. Importantly, the municipality awarding the contracts was not sued by the second lowest bidders. Instead, the second lowest bidders alleged that American Asphalt intentionally interfered with a business expectancy and sought damages from American Asphalt, specifically the profit that they lost by not performing these contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Construction Defect Litigation at San Diego’s Alicante Condominiums?
March 25, 2011 —
Alicante HOA WebsiteAccording to recent posts in the Alicante HOA website, construction experts and legal counsel have been retained. The HOA board has been informed that testing of a variety of the building’s components are underway or will begin in the near future.
Read More...
Read the court decisionRead the full story...Reprinted courtesy of
The Future for Tall Buildings Could Be Greener
October 01, 2013 —
CDJ STAFFSkidmore, Owens and Merrill made its reputation by creating iconic structures of steel, concrete, and glass, but in a new report, the firm puts forth ways in which the first item would be wood. Building codes in many cities stipulate that buildings taller than four stories be built of steel and concrete, but the firm says that it has come up with a way of building structures of 30 stories or more using wood.
The tallest wood-framed building currently is only ten stories tall. In order to calculate a comparison, Skidmore, Owens and Merrill designed a forty-two story building based on the design of an existing apartment building. Actually building it would require almost 4 million board-feet of wood. Unlike a typical single-family home (and its 20,000 board-feet of wood), these building would use glue-laminated timber and slabs.
The study found that the building would weigh less than half as much, allowing a less massive foundation. If the wood came from sustainable sources, its environmental impact would be drastically reduced. They calculated that instead of 9,500 tons of CO2 emissions for the conventional tower, the wood structure would be responsible for only 2,100 tons of emissions.
Skyscrapers will continue to be a feature of large cities. But instead of urban canyons of steel and concrete, in the future those towering buildings might be made of wood.
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Could Impact Contractor Performance Bonds
March 30, 2020 —
Ben Williams & MG Surety - Construction ExecutiveAs COVID-19 continues to expand around the United States and the world, it may only be a matter of time before U.S. construction projects are affected by the virus. Performance bonds guarantee that a project will be completed by a contractor according to the contract. However, what if a contractor cannot complete a project on time due to widespread disease? What, if any, impact could the virus have on a contractor’s surety bond program?
Risk Factors
Several risks associated with the virus could trigger a performance bond claim.
1. Materials. The Chinese account for a large supply of construction materials, including steel, copper, cabinetry, etc. An inability to obtain these materials could significantly delay or stop a project all together. Even if a contractor is able to obtain them from other sources, it may be at a significantly higher cost than they put into the bid.
2. Labor. There is already a shortage of qualified labor in the construction industry. Additionally, construction already lends itself to the spreading of viruses; workers are often in close proximity, handling common materials, and they may not have an easily accessible place to wash their hands. Furthermore, even though many now have paid sick leave, there is often pressure not to use it. These things could magnify the labor shortage and make it difficult to complete projects on time.
3. Safety. Finally, the world is having a serious shortage of respirators. Because of widespread panic, many people have been purchasing N95 respirators—so much that the Surgeon General has asked people to stop buying them. It has created a shortage for people who really need them, like contractors. If contractors can’t get these safety masks, certain trades will either be unable to work, or risk continuing the project without masks, which would endanger workers and open them up to OSHA penalties.
Reprinted courtesy of
Ben Williams and MG Surety, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Williams may be contacted at
benw@mgsuretybonds.com
Prior Occurrence Exclusion Bars Coverage for Construction Defects
April 11, 2022 —
Tred R. Eyerly - Insurance Law HawaiiWhile the insured's faulty work constituted an occurrence under Florida law, a prior occurrence exclusion barred coverage. Pro-Tech Caulking & Waterproofing v. TIG Ins. Co., 2022 U.S. Dist. LEXIS 12319 (S.D. Fla. Jan. 19, 2022).
Pro-Tech was a waterproofing subcontractor for construction of a oceanfront condominium building and was responsible for the installation of waterproofing systems on the Project. Pro-Tech entered into a separate contract with the developer, BRE Point Parcel, LLC to install a traffic coating on the garage floors.
BRE sued the general contractor, Pro-Tech and others for construction defects. The underlying action alleged that Pro-Tech, among other things, failed to wrap the filter fabric to protect the weep holes, improperly installed sealants between the stucco and the underside of the horizontal tile at the balcony slab edge, and failed to properly install traffic coating in one garage. The underlying complaint did not state exactly when the "property damage" resulting from Pro-Tech's alleged defective work occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Florida’s “Groundbreaking” Property Insurance Reform Law
April 18, 2023 —
Bradley S. Fischer & Laura Farrant - Lewis BrisboisFort Lauderdale, Fla. (April 18, 2023) – On December 16, 2022, Florida Governor Ron DeSantis signed into law Senate Bill 2-A (S.B. 2-A, or the Act). Widely touted as “groundbreaking,” S.B. 2-A reforms many aspects of the claims process, including the timing for paying and adjusting claims, eliminating one-way attorneys’ fee awards, and banning assignment-of-benefits agreements. This alert provides an overview of the key provisions of S.B. 2-A. Unless otherwise stated in each amended statute, December 16, 2022 appears to be the effective date of the Act.
I. Assignment of Benefits – Section 627.7152 (effective January 1, 2023)
- A policyholder may not assign any post-loss insurance benefits under any residential or commercial property insurance policy. Any attempt to assign such benefits is void, invalid, and unenforceable.
Reprinted courtesy of
Bradley S. Fischer, Lewis Brisbois and
Laura Farrant, Lewis Brisbois
Mr. Fischer may be contacted at Bradley.Fischer@lewisbrisbois.com
Ms. Farrant may be contacted at Laura.Farrant@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Subcontractor Strength Will Drive Industry’s Ability to Meet Demand, Overcome Challenges
October 10, 2022 —
Anwar Ghauche - Construction ExecutiveOwners, developers and general contractors get a lot of notoriety for construction projects, especially in these infrastructure-focused times. However, the subcontractor is truly the one under the microscope, as this group requires the most care and attention to ensure the owners and operators are able to meet accelerating demand and public expectations.
The challenges in the current environment are many. Inflation and supply chain disruptions are highly detrimental to specialty trades in the mechanical, electrical, plumbing, drywall and other areas. Reports show that the construction industry, in particular, has seen an
increase of over 20% in the cost of supplies and building materials in the last year alone and, in some cases, over
90% since the start of the pandemic. While these costs are passed along to the owner, the subcontractor still retains significant cash flow risk. This truth is amplified in a volatile market. As if the cost was not enough, equipment and material shortages coupled with rising interest rates only compound the problem—and tenfold for small businesses.
Subcontractors are likely to feel the greatest pressure from supply-related issues. Inflation combined with supply chain shortages require subcontractors to prepare earlier for projects and, when possible, purchase materials upfront. However, the consequence of this preliminary preparation equates to further strains on cash flow. In an effort to remain aligned on schedules and budgets, subcontractors frequently buy all of a project’s materials as soon as a contract is signed—if not before.
Reprinted courtesy of
Anwar Ghauche, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of