Eighth Circuit Rejects Retroactive Application of Construction Defect Legislation
September 17, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Eighth Circuit refused to retroactively apply an Arkansas statute establishing coverage for faulty workmanship. J-McDaniel Const. Co., Inc. v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 14911 (8th Cir. Aug. 4, 2014).
The homeowners sued J-McDaniel for faulty workmanship in constructing their home. The defective construction work was performed by subcontractors. Mid-Continent refused to defend or indemnify J-McDaniel.
The insured sued Mid-Continent. The district court dismissed the claim pursuant to Essex Ins. Co. v. Holder, 261 S.W. 3d 456, 460 (Ark. 2008). In Essex, the Arkansas Supreme Court held that defective workmanship resulting in damages only to the work product itself was not an occurrence. Although The Arkansas legislature overruled Essex by statute, the district court found that the Arkansas case law barred retroactive application of the statute.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Litigation Roundup: “Sudden Death”
October 17, 2023 —
Daniel Lund III - LexologyIt’s not football, though. Rather, just when you thought it was safe in Louisiana to wait to file a garden-variety construction contract payment claim, an appellate court slams the door on it – applying a statute of “repose” to your claim.
“Personal actions” – such as an action on contract – are generally subject in Louisiana to a 10-year “liberative prescription,” the applicable statute of limitations pursuant to Louisiana Civil Code article 3499.
Like some other states, Louisiana has a statute of “repose” – imposing “peremption” rather than prescription for claims having to do with construction projects – limiting those claims (generally speaking) to five years post-completion. Like other statutes of “repose,” Louisiana Revised Statute 9:2772 provides that claims on construction projects may not be filed after five years, a duration which is not subject to interruption or extension.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Fraud Claims and Breach Of Warranty Claims Against Manufacturer
March 04, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case touches upon two issues that are noteworthy when considering fraud claims and breach of warranty claims against a manufacturer. Below contains a discussion on these claims.
Independent Tort Doctrine
“Florida’s independent tort doctrine provides that a party may not recover in tort for a contract dispute unless the tort is independent of any breach of contract.” MidAmerica C2L Inc. v. Siemens Energy, Inc., 2024 WL 414620, *6 (M.D.Fla. 2024). This means tort allegations and claims MUST be separate and distinct from performance under the contract. Id. (citation omitted).
In MidAmerica C2L, a plaintiff sued a manufacturer relating to sophisticated equipment for a coal gasification plant. The parties entered into different agreements for the equipment and a license where the plaintiff could use the manufacturer’s patented technology for its coal gasification plants. A dispute arose and the plaintiff sued the manufacturer under various legal theories. The manufacturer moved for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Litigation Roundup: “A Close Call?”
August 05, 2024 —
Daniel Lund III - LexologyNot really, said a Florida state appellate court when a public construction project owner sued a defaulted general contractor after recovering from the general contractor’s surety.
The general contractor, Close Construction, entered into a contract for a lift station rehabilitation construction project with the City of Riviera Beach in Florida. During the course of the work the public owner terminated the contract, whereupon the GC and the owner brought claims against each other in court. A jury ultimately held against the general contractor and in favor of the public owner in the amount of approximately $1.9 million. The general contractor appealed.
On appeal, the general contractor noted that the public works surety which it was required by the contract to obtain for the project had hired another company to complete the work when the general contractor was terminated and had otherwise “settled with the District under its bond for $1,000,000.” Based on that settlement, the general contractor had moved, unsuccessfully, in the trial court for a post-trial setoff because the “settlement covered the same damages that the jury assessed” against the GC, and because the surety was “jointly and severally liable” with the GC – pursuant to the terms of the bond – for those damages. In essence, the general contractor sought to avoid having the public owner “obtain a double recovery.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Insurer Must Defend Faulty Workmanship Claims
May 02, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that the insurer improperly denied a defense for construction defect claims made against the insured. Amerisure Mut. Ins. Co. v. McMillin Tex. Homes, 2022 U.S. Dist. LEIS 40363 (W.D. Texas March 8, 2022).
McMillin was a developer, general contractor and home seller. It constructed multiple homes in various communities in the San Antonio area. After the homes were completed, homeowners observed defects in the artificial stucco exterior finish. After claims were lodged against McMillin, the various claims were tendered to Amerisure. Amerisure filed for declaratory judgment that it had to duty to defend or indemnify and moved for summary judgment.
Amerisure first argued the homeowners' faulty workmanship claims did not allege "property damage" under the policies. It argued there were no allegations that any property damage existed, but merely that the stucco suffered from construction defects. The court disagreed. Among the allegations was the statement that due to the construction defects, the homes suffered damage "not only to the exterior stucco, but also to the underlying wire lath, paper backing, house wrap, flashing, water resistive barriers, sheathing, interior walls, interior floors and/ or other property." Consequently, the underlying claims amounted to property damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Makes an Unsettling Inference to Find that the Statute of Limitations Bars Claims Arising from a 1997 Northridge Earthquake Settlement
April 15, 2015 —
David W. Evans and Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Britton v. Girardi (No. B249232 – Filed 4/1/2015), the Second Appellate District upheld the trial court’s dismissal due to the statute of limitations based on an inference it drew from a letter attached to the complaint, while reaffirming its prior application of the limitations period in Probate Code section 16460 for fraud claims in the related case of Prakashpalan v. Engstrom, Lipscomb & Lack (2/27/2014) 223 Cal.App.4th 1105.
In Britton, just as in Prakashpalan, the plaintiffs sued the attorneys who had represented them in connection with claims against their insurer arising out of the Northridge earthquake. In 1997, the attorneys had settled that litigation for more than $100 million. The plaintiffs allege that the attorneys breached their fiduciary duty by (1) failing to provide an accounting for the settlement, (2) failing to obtain their informed consent to the settlement, and (3) concealing their misappropriation of the settlement funds. They claim that they did not discover this wrongdoing until nearly fifteen years later, in 2012, when the Prakashpalans contacted them about their settlement. Significantly, the plaintiffs attached as an exhibit to the complaint a page of the November 3, 1997 letter to the Prakashpalans (rather than the plaintiffs), which stated that a retired judge who presided over the settlement had determined the allocations and the attorneys could not distribute the proceeds until the plaintiffs signed the “Master Settlement Agreement” by which the plaintiffs agreed to its terms and to give up all claims against the insurer.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida Federal Court to Examine Issues of Alleged Arbitrator Conflicts of Interests in Panama Canal Case
May 24, 2021 —
Sarah B. Biser & Philip Z. Langer - ConsensusDocsThe parties in a $238-million dispute over the construction of the third set of locks for the Panama Canal are raising issues concerning alleged conflicts of interest on the part of the International Chamber of Commerce (“ICC”) arbitrators in the United States District Court for the Southern District of Florida.[2] The case may address rarely litigated issues concerning whether arbitrators who sit on multiple arbitration panels together or who support appointment of each other to lead arbitration panels have disabling conflicts of interest.
The case pits Grupo Unidos por el Canal, S.A. (“Grupo”), a consortium of Spanish, Italian, Belgian, and Panamanian construction firms, against Autoridad del Canal de Panama (“ACP”), the Panamanian entity that operates the Panama Canal and that sponsored the multi-billion-dollar, decade-long project to expand the Canal’s capacity by building a new set of locks (the “Project”). The current dispute (the “Panama 1 Arbitration”), which centers on the suitability of the rock coming from the excavations to be used to produce concrete aggregates for the Project, was arbitrated before a three-member ICC Tribunal and resulted in a $238-million award to ACP and against Grupo. The ICC Tribunal reversed a decision of the dispute review board established in the parties’ contract.
Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLP and
Philip Z. Langer, Fox Rothschild LLP
Ms. Biser may be contacted at sbiser@foxrothschild.com
Mr. Langer may be contacted at planger@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
Denver Court Rules that Condo Owners Must Follow Arbitration Agreement
November 07, 2012 —
CDJ STAFFPrior to initiating a construction defect lawsuit, the Glass House Residential Association voted to invalidate the arbitration agreement that had been written into its declaration and bylaws by the developer and general contractor. After the association started their construction defect claims, the developer and general contractor argued that the case must go to arbitration, as the arbitration clause contained a provision that it could not be altered without the agreement of the developer and general contractor.
The Denver District Court has ruled against that association, determining that the res triction was not in violation of Colorado condominium law. And, as a post from Polsinelli Shughart PC on JDSupra notes, the Colorado Common Interest Ownership Act encourages the use of arbitration procedures to settle disputes. The CCIOA does prohibit “certain restrictions on the homeowners association’s ability to amend the condominium declarations,” however, preserving an arbitration agreement is not one of them.
Read the court decisionRead the full story...Reprinted courtesy of