The International Codes Development Process is Changing to Continue Building Code Modernization
March 06, 2023 —
The International Code CouncilWashington D.C., March 02, 2023 (GLOBE NEWSWIRE) -- The International Code Council is revising its rigorous code development process. The changes will take effect in 2024-2026 for the development of the 2027 International Codes (I-Codes) and will move the development process to an integrated and continuous three-year cycle.
In the new timeline, year one will include two Committee Action Hearings for Group A Codes; year two will include two Committee Action Hearings for Group B Codes; and year three will be the joint Public Comment Hearings and Online Governmental Consensus Vote for both Group A and B Codes.
The addition of the second Committee Actions Hearings in year one and two will foster a more in-depth vetting of code change proposals, allowing an opportunity for the committee members to review and evaluate the original proposals and consider the submitted responses. This also provides more opportunity for proponents to build consensus for their code change proposal and ensure the best version of their intended improvement to the existing codes.
Additionally, with combined Public Comment Hearings in the third year, voting members are able to vote on all suggested changes to the next edition of the I-Codes at one time. The updated process also provides more opportunity for proposed new referenced standards to be developed and finalized on a consistent timeline regardless of the group (Group A or B) with which they are associated.
About the International Code Council
The International Code Council is the leading global source of model codes and standards and building safety solutions. Code Council codes, standards and solutions are used to ensure safe, affordable and sustainable communities and buildings worldwide.
Read the court decisionRead the full story...Reprinted courtesy of
7 Sustainability Ideas for Modular Classrooms in the Education Industry (guest post)
June 10, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, a guest post on sustainable modular classrooms from Kathy Werder, a freelance architect by profession and a researcher by nature. According to Kathy, most of her research papers focus on promoting integration that leads to sustainable and lean design and construction practices. Kathy is obsessed with the latest rage in the construction industry – modular building solutions. She is also an avid writer, and loves blogging about green buildings and portable construction units. Welcome, Kathy!
According to Wikipedia, a sustainable building refers to “ a structure and using process that is environmentally responsible and resource-efficient throughout a building’s life-cycle from sitting, to design, construction, operation, maintenance, renovation, and demolition.”
So if we accept this definition to be true, in order to make an actual sustainable building we have to consider the entire process of building right from the blueprint stage all the way to demolition, and ensure that at every step of the way there is minimal or no negative impact on the environment, especially in terms of resource efficiency.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback may be contacted at
mbrumback@rl-law.com
Proposed Law Protecting Tenants Amended: AB 828 Updated
June 08, 2020 —
Rhonda Kreger – Newmeyer DillionOn May 18, 2020, AB 828 was amended and is currently on its second reading in the Senate Rules Committee. This legislation proposes a temporary moratorium on foreclosures and unlawful detainers while Governor Newsom's COVID-19 emergency order is in effect. In addition to the moratorium, AB 828 also required landlords to reduce rent by 25% under certain circumstances. AB 828 was amended to remove the provision that required landlords to reduce rent by 25% for 12 months. The new provision requires landlords to allow tenant to remain in possession, and requires tenants to start paying rent the month following the end of the emergency order. Tenants must timely pay monthly rent plus 10% of any rent due and owing when the emergency order ended.
Under AB 828, a tenant may stipulate to the entry of an order in response to a residential unlawful detainer action filed by the landlord. Upon a hearing, the court determines if the tenant's inability to pay rent is the result of increased expenses or a reduction in income due to COVID-19. The court must also make a determination that there is no material economic hardship for the landlord. Upon making such determinations, the court will issue an order that permits the tenant to remain in possession, and requires tenant to commence rental payments the month following the end of the COVID-19 emergency order. Tenant's payment would include the monthly rent plus 10% of an unpaid rent during the COVID-19 emergency order, but excludes any late charges or other fees or charges. The tenant would be required to make timely payments, and if tenant fails to do so, after a 48 hour notice from landlord, the landlord can file for an immediate writ of possession in favor of the landlord and money judgment for any unpaid balance, court costs and attorneys' fees.
Newmeyer Dillion continues to follow COVID-19 and its impact on your business and our communities. Feel free to reach out to us at NDcovid19response@ndlf.com or visit us at www.newmeyerdillion.com/covid-19-multidisciplinary-task-force/.
Rhonda Kreger is Senior Counsel on Newmeyer Dillion's transactional team at our Newport Beach office. Her practice focuses on all aspects of commercial real estate law, with a particular emphasis on the representation of residential developers, merchant builders and institutional investors. You can reach Rhonda at rhonda.kreger@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Material Prices Climb…And Climb…Are You Considering A Material Escalation Provision?
May 31, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you may know, material prices have been climbing. And they continue to climb based on the volatility of the material market. On top of that, there are lead times in getting material due to supply chain and other related concerns. The question is, how are you addressing these risks? These are risks that need to be addressed in your contract.
As it relates to climbing material prices, one consideration is a material escalation provision. The objective of this provision is to address the volatility of the material market in economic climates, such as today’s climate, where the price of material continues to climb. Locking down a material price today will be different than locking down the same price months from today. This volatility and risk impacts pricing and budgets. Naturally, an owner and contractor would like to be in a position to lock down supplier prices as soon as possible—both to secure pricing and to account for items with long lead times or that recent data forecasts a long lead time due to supply chain concerns. However, this is not always possible or practical and can depend on numerous issues such as when the owner contracts with the contractor, when the owner issues the notice to proceed (and permits are issued), final construction documents and revisions to the construction documents, the type of material, whether there is staging or storage available for the materials, and the current status including climitazation of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
High Court Could Alter Point-Source Discharge Definition in Taking Clean-Water Case
March 18, 2019 —
Mary B. Powers - Engineering News-RecordThe U.S. Supreme Court's decision to review lower court rulings on whether a permit is required under the federal Clean Water Act when pollutants originate from a point source but are carried to navigable waters by a non-point source such as groundwater could set some new parameters for compliance, observers say.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, ENRENR may be contacted at
ENR.com@bnpmedia.com
Reminder: A Little Pain Now Can Save a Lot of Pain Later
April 28, 2016 —
Christopher G. Hill – Construction Law MusingsI know, you think you hear it enough from me here at Construction Law Musings. I am seemingly constantly beating the drum of early advice from a construction attorney and the benefits of spending a bit of money now to avoid spending a lot of money later. I do this because real world examples of both the costs of failing to prepare early and the benefits of following this advice abound.
An example of the costs of failing to prepare early can be
found at the Construction Payment where the zLien folks discuss a New Hampshire case where a contractor lost two thirds of its potential damages because it did not properly set out the contractual terms and what was to be included in contractual damages. Without any clear line to go on, the Court found liability against the NHDOT for negligent misrepresentation and could only award damages up to a cap that was approximately a third of the damages awarded by the jury and about half of what the trial court had determined to be the damages.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
2013 May Be Bay Area’s Best Year for Commercial Building
November 20, 2013 —
CDJ STAFFA tech boom has resulted in something of a commercial building boom for the Bay Area. The region will see about $6 billion in commercial construction projects during 2013. This is better than the totals for 2012, 2011, and 2009. During that period, however, 2010 set a record for the area with $6 billion of construction. Some estimates see 2013 beating that with as much as $6.7 billion in construction by year’s end.
The surge has been attributed to job creation. One Bay-area company, Infoblox, moved into a new office complex, after extensive renovation. The company had 250 employees and now has room to expand to 500 employees.
But 2014 could be even better. Apple is about to begin construction of its new campus, which is expected to cost the company $5 billion.
Read the court decisionRead the full story...Reprinted courtesy of