Flow-Down Clauses Can Drown Your Project
August 26, 2015 —
Craig Martin – Construction Contractor AdvisorFlow-Down or pass-through clauses obligate downstream contractors to certain provisions contained in the up up-stream contractor contracts, such as the contract between the general contractor and the owner. These clauses are contained in every major form subcontract and they can expand the scope of your potential liability. This blog will look at typical language of a flow-down clause, what it means and how you can deal with them.
Typical Flow-Down Clause
A simple flow down clause might provide:
“The Subcontractor agrees to be bound to the Contractor by the terms of the prime contract and to assume to the Contractor all the obligations and responsibilities that the Contractor by those documents assumes to the Owner, except to the extent that the provisions contained therein are by the terms or by law applicable only to the Contractor.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Women Make Slow Entry into Building Trades
December 04, 2013 —
CDJ STAFFIn the next seven years, about 200,000 carpenters will be added to workforce, but few of those are likely to be women. Sylas Demello, an electrical apprentice noted that it isn’t “made clear for women in high school to say, ‘hey, this is an option for you.’”
Tiffany Bluemle is trying to do something about that. She runs Vermont Works for Women, which trains women for jobs in which there are few women, including the building trades. She notes that “seventy-five percent of owners say they face labor shortages.”
Amy Judd is now one of those owners. Fifteen years ago, failing to find a teaching job, she started working as a carpenter. “It had never occurred to me that I would want to be a carpenter,” she said. Her firm employs eight people, half of whom are women.
Read the court decisionRead the full story...Reprinted courtesy of
Athletic Trainers Help Workers Get Back to the Jobsite and Stay Healthy After Injury
August 12, 2024 —
Bryan Lockhart - Construction ExecutiveThere are a number of factors on an active jobsite that can lead to workplace injuries. Heavy machinery, fast-moving equipment, material handling, loud noises and more can create safety hazards and make it easy to lose focus or become distracted. Additionally, the movements workers have to do in their roles—such as lifting or pushing objects or crouching low to the ground for extended periods—can add strain to the body if not done correctly.
The goal is always to minimize the risk of injury, and yet, incidents still occur. According to 2020 Bureau of Labor Statistics data, slips, trips and falls are the most common injuries, accounting for 18% of non-fatal work injuries resulting in days away from work. When workers are injured, it can lead to downtime, lost productivity on the site and workers’ compensation claims.
Employers and site leaders can take various approaches to help workers return to the jobsite safely and effectively and keep them healthy once they return. Introducing an onsite clinic and athletic trainers can help prevent injuries, improve worker health, get people back to work effectively and keep them healthy in the long run. Here are three ways athletic trainers help workers get back to the job and improve their overall health.
Reprinted courtesy of
Bryan Lockhart, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ninth Circuit Resolves Federal-State Court Split Regarding Whether 'Latent' Defects Discovered After Duration of Warranty Period are Actionable under California's Lemon Law Statute
December 17, 2015 —
Laura C. Williams & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Daniel v. Ford Motor Company (filed 12/02/15), the Ninth Circuit resolved a federal and state court split on the issue of whether consumers can sustain a breach of implied warranty claim under California’s Song Beverly Consumer Warranty Act (aka the “lemon law” statute) for “latent” defects discovered after the warranty period has expired. Answering this question in the affirmative, the Ninth Circuit followed the holding in the California state appellate decision of Mexia v. Rinker Boat Co. 95 Cal.Rptr.3d 285 (2009), which definitively determined there is nothing in California’s lemon law that requires a consumer to discover a latent defect during the duration of the warranty.
The underlying class action lawsuit was brought in federal district court by purchasers of Ford Focus vehicles. The plaintiffs alleged Ford was aware of, but failed to disclose, a rear suspension defect in the Focus that resulted in premature tire wear which can cause decreased vehicle control, catastrophic tire failure and drifting on wet or snowy roads. The plaintiffs alleged a number of claims including violations of California’s Song Beverly Consumer Warranty Act and Magnuson Moss Warranty Act. Ford successfully moved for summary judgment on all claims prompting an appeal.
Reprinted courtesy of
Laura C. Williams, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Ms. Williams may be contacted at lwilliams@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Industrialized Construction News 7/2022
August 15, 2022 —
Aarni Heiskanen - AEC BusinessThe
AEC Business newsletter’s Industrialized Construction edition in July featured the following news stories:
The Pros and Cons of Offsite Construction – A French Research Study
The study is titled The current use of industrialized construction techniques in France: Benefits, limits and future expectations. The authors are Emna Attouri, Zoubeir Lafhaj, Laure Ducoulombierb and Bruno Linéatte.
Read more
Rise of the machines? For Construction, Not Yet
Matthew Thibault’s article examines the opportunities and challenges of construction robotics. Robots can improve safety and productivity, but the ROI is still unclear to many contractors.
Read more Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
NAHB Examines Single-Family Detached Concentration Statistics
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFIn the National Association of Builders’ (NAHB) publication Eye on Housing, the NAHB examined “the share of homeowners living in single-family detached housing” statistics as reported in the 2012 American Community Survey (ACS).
Wausau, Wisconsin had the highest share of homeowners living in single-family detached housing within a metropolitan area. Interestingly, NAHB found that “[w]ith the exception of Modesto, CA, all of the metropolitan areas in the top ten [were] located in the Midwest.”
The New York-White Plains-Wayne (New York) division had the lowest share of homeowners living in single-detached housing.
Read the court decisionRead the full story...Reprinted courtesy of
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
The Privilege Is All Mine: California Appellate Court Finds Law Firm Holds Attorney Work Product Privilege Applicable to Documents Created by Formerly Employed Attorney
June 29, 2017 —
David W. Evans & Stephen J. Squillario – Haight Brown & Bonesteel LLPIn Tucker Ellis LLP v. Superior Court (A148956 – Filed 6/21/2017), the First Appellate District held that (1) the holder of the attorney work product privilege is the employer law firm rather than the former employee attorney who created the privileged documents while a firm employee, and (2) as a result, the firm did not owe a duty to obtain the former attorney’s permission before disclosing the subject documents to third parties.
In Tucker Ellis LLP, the attorney, while still employed by Tucker Ellis, exchanged a series of e-mails with a consultant retained by the firm to assist in asbestos litigation for a client. The firm also entered into an agreement with the consultant to summarize scientific studies on the causes of mesothelioma in a published review article. After the attorney departed the firm, Tucker Ellis was served with a subpoena in connection with a matter pending in Kentucky for the production of communications with the consultant regarding the article. In response, Tucker Ellis, in relevant part, produced the work product e-mails authored by the former attorney. The e-mails eventually ended up on the Internet and reached over 50 asbestos plaintiffs’ attorneys, resulting in the attorney’s termination from his new firm. After Tucker Ellis ignored the attorney’s “claw-back” letter, he filed suit against the firm for negligence, among other causes of action. The trial court granted the former attorney’s motion for summary adjudication on the issue of duty, reasoning that the firm owed the attorney a legal duty to prevent the disclosure of the work product. Tucker Ellis filed a petition for a writ of mandate with the Court of Appeal challenging the trial court’s decision on the duty issue.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of