90 and 150: Two Numbers You Must Know
July 22, 2019 —
Christopher G. Hill - Construction Law MusingsMechanic’s liens are a big topic here at Construction Law Musings. I’ve discussed everything from the picky nature of this powerful payment tool to the changes that are upcoming on July 1, 2019. Given the strict way that the form and timing of a Virginia mechanic’s lien is so critical, I thought a quick reminder was in order.
Two numbers that are critical to the timing and content of any mechanic’s lien are 90 and 150, both found in Va. Code 43-4. 90 days is the time from the last date of work (not invoicing), or last date of the last month in which work was done given proper circumstances.
The 90 days prescibes the time during which a contractor can properly record a valid lien. This is a hard deadline and is 90 days, not three months. Miss this deadline and no matter what the type of payment that has not been made (something discussed below), the contractor will lose its lien rights. This is the easier of the two numbers to both understand and apply. Count 90 days from last non-corrective or warranty work and that is your hard out for filing.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Firm Claims Construction Defects in Hawaiian Homes
December 04, 2013 —
CDJ STAFFThe Los Angeles law firm Girardi Keese has filed a lawsuit representing 10,000 homeowners in Hawaii. The class action suit claims that construction defects have left the homes unable to withstand the island’s winds. Graham B. LippSmith, who represents the homeowners said that “we’re seeing some homes where the straps have cracked all the way through, so there’s nothing holding the frame to the foundation.” Mr. LippSmith said that the developer should have used anchor bolts instead of hurricane straps, but “that would have cost more money.”
Mr. LippSmith says that his goal is to get the homes fixed. “It doesn’t do any good to give someone $50,000 and tell them go have their home fixed when what the community needs is to be made safe for the residents.”
Read the court decisionRead the full story...Reprinted courtesy of
Kahana Feld Receives 2024 OCCDL Top Legal Organizations for DEI Award
September 30, 2024 —
Linda Carter - Kahana FeldIRVINE, CA – Sep. 12, 2024 – Kahana Feld is pleased to announce that the firm received the 2024 Top Legal Organizations for DEI Award from the Orange County Coalition for Diversity in the Law (OCCDL). The firm will be recognized at an awards gala at The Westin South Coast Plaza on October 3.
Each year, the OCCDL recognizes individuals and organizations who have advanced diversity, equity, and inclusion in the Orange County legal community, whether through their excellence in the law or their direct efforts to promote DEI. Kahana Feld was recognized for programs such as its DEI book club and its regular webinars on topics like implicit bias. The firm supports various DEI organizations and initiatives in the Orange County area, including the Orange County Asian American Bar Association, the Orange County Women Lawyers Association, and the Jewish Federation of Orange County.
The OCCDL is a collaborative effort of professionals from leading Orange County law firms and other community partners promoting the advancement of diverse attorneys in Orange County. The OCCDL partners with local schools and organizations to increase community involvement and provides education focused on diversity to students and attorneys.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Caltrans Hiring of Inexperienced Chinese Builder for Bay Bridge Expansion Questioned
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFThe construction of the new eastern span of San Francisco’s bay bridge has been criticized for the $6.5 billion cost, welding crack violations, and alleged cover ups by Caltrans. The Sacramento Bee reported that the company Shanghai Zhenhua Port Machinery Co. Ltd. (ZPMC) “had never built a bridge.” In fact, ZPMC “was a manufacturer of giant cranes for container ports.”
How then did ZPMC manage to obtain the contract? The Sacramento Bee stated that the company “had established a reputation as fast and cost-effective, offering savings of about $250 million compared to the competing bidder.” The project was already “years behind schedule and billions of dollars over budget by political squabbles and construction delays” and there were some fears that the “old bridge might not survive a major quake.”
Caltrans was told by an outside expert that ZPMC was a “high risk,” however, the company received a “contingent pass.” Sacramento Bee reported that an audit showed “ZPMC didn’t have enough qualified welders or inspectors…and routinely welded in the rain, a basic error that often causes defects.” Regardless, Caltrans signed off on the project.
“In August 2007, Caltrans auditors approved ZPMC outright, although the firm still lacked adequate quality control, even for ‘fracture critical’ materials,” the Sacramento Bee reported.
During the California Senate committee hearing in January, Doug Coe, a senior Caltrans engineer, said “’The race for time’ created overwhelming pressure to keep moving as planned….But there’s no excuse for building something defective like that because we are in a race for time.”
Read the court decisionRead the full story...Reprinted courtesy of
Feds, County Seek Delay in Houston $7B Road Widening Over Community Impact
March 15, 2021 —
Mary B. Powers - Engineering News-RecordThe Federal Highway Administration has asked Texas to delay issuing requests for proposals and pause ongoing contracting on a $7-billion, three-phased highway expansion project in metropolitan Houston as it evaluates complaints that up to 1,000 homes and multifamily buildings and 350 businesses would be condemned to build the project.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Williams v. Athletic Field: Hugely Important Lien Case Argued Before Supreme Court
June 17, 2011 —
Douglas Reiser, Builders Council BlogWell, it finally made it. The most important Washington lien case of recent memory was argued in front of the Washington Supreme Court on Tuesday, June 14, 2011. So, what should we all expect?
As I was reading through my RSS feeds this afternoon ? I was stopped dead in my tracks. Williams v . Athletic Field, the Division II case that has been a frequent topic here on Builders Counsel, has finally been argued before the Supreme Court. All of you who have been anxiously awaiting this day, you can check out the Supreme Court submissions by following this link.
The Williams case has been the center of attention for construction lawyers and construction organizations over the past year. Some have called for complete lien law reform, others have tried to patch a hole in the law. Now, we can expect a ruling from the highest court in the state. That ruling will have a major impact on whether the Legislature feels compelled to change lien law.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Contract Provisions That Help Manage Risk on Long-Term Projects
June 29, 2020 —
Jason Lambert - Construction ExecutiveFew things can dampen the thrill and promise of a newly closed construction deal than the realization that it could quickly become a losing proposition for the contractor depending on economic and other conditions. In an era of instant information, constantly adjusting markets and political extremes, projects that start under one set of assumptions or conditions can occur or conclude under much different ones. While no one has a crystal ball, there are contractual provisions that can provide clear guidance in the face of many “what ifs” that can arise in construction.
One of the chief concerns a contractor should have in a project lasting more than a few months is what impact price increases will have on the profitability of the job. On a true cost-plus project, this may be of little concern, but on any project with a limitation on costs or a guaranteed maximum price, contractors should insist on a procedure to revisit the limitation or price if certain conditions change.
This can be as simple as allowing the contractor to receive an upward adjustment in the price if costs increase by more than a certain percentage. It can be as complicated as requiring multiple new bids and disclosures to the property owner, architect or project manager and allowing approval of new suppliers or subcontractors to limit cost increases to the cheapest increase. The protection—and certainty—to the contractor though, comes from having a process in the contract to address cost increases, whether it is simple or complex.
Reprinted courtesy of
Jason Lambert, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lambert may be contacted at
Jason.lambert@dinsmore.com
Best Lawyers® Recognizes 49 White and Williams Attorneys
September 16, 2024 —
White and Williams LLPThirty-eight White and Williams lawyers were recognized in Best Lawyers in America® 2025. Inclusion in Best Lawyers® is based entirely on peer-review. The methodology is designed to capture, as accurately as possible, the consensus opinion of leading lawyers about the professional abilities of their colleagues within the same geographical area and legal practice area. Best Lawyers® employs a sophisticated, conscientious, rational, and transparent survey process designed to elicit meaningful and substantive evaluations of quality legal services.
In addition, eleven lawyers were recognized as Best Lawyers: Ones to Watch® in America. This recognition is given to attorneys who are earlier in their careers for outstanding professional excellence in private practice in the United States.
The firm is also pleased to announce Best Lawyers® has recognized three attorneys as "Lawyer of the Year” including: Chuck Eppolito, Litigation - Health Care, Philadelphia, who focuses his practice on medical malpractice defense as well as other insurance-related defense; William D. Kennedy, Litigation – Insurance, Philadelphia, who focuses his practice on complex claims of injury and damage arising in both the professional and general liability contexts; and, Michael O. Kassak, Litigation – Insurance, Cherry Hill, who focuses his practice on large complex commercial matters including insurance coverage and healthcare disputes.
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP