Wendel Rosen’s Construction Practice Group Receives First Tier Ranking
January 28, 2015 —
Garret Murai – California Construction Law BlogWe try to limit our narcissism here at Wendel Rosen but every once in a while we toot our own horn. Lawyers are, after all, a rather sad, competitive, yet insecure bunch (i.e., we eat this stuff up).
We’re proud to announce that Wendel Rosen’s Construction Practice Group has received a first tier ranking in U.S. News & World Reports’ Best Law Firms for 2015. This is the second year the Construction Practice Group has received a first tier ranking. Yay us!
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Deadline for Hurricane Ian Disaster Recovery Applications Announced
October 17, 2022 —
Lewis BrisboisWashington, D.C. (October 11, 2022) - On Friday, October 7, 2022, the Florida Division of Emergency Management (FDEM) announced that applications for the Federal Emergency Management Agency’s (FEMA) Public Assistance Grant Program are due by October 29, 2022.
FEMA provides disaster recovery assistance to eligible individuals, families, governments, and private non-profit entities. However, the process for recovering costs is complicated, and FEMA has broad discretion to determine whether applicants and their expenses are eligible. All too often, failure to understand FEMA regulations or submit sufficient documentation results in FEMA denying applicants’ claims, leaving individuals, local governments, and non-profits to bear the full cost of recovery.
While ensuring successful recovery through the FEMA grant program can be challenging, clients can increase their likelihood of success when preparing the initial application and documentation by enlisting experienced legal counsel who understand the FEMA process and regulations.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Courthouse Reporter Series: Nebraska Court of Appeals Vacates Arbitration Award for Misconduct
November 18, 2024 —
Brendan J. Witry - The Dispute ResolverVacating an arbitration award is often seen as an uphill battle. Indeed, the U.S. Supreme Court has stated that “courts may only vacate an arbitrator’s decision ‘only in very unusual circumstances.’” Oxford Health Plans, LLC v. Sutter, 569 U.S. 564, 568 (2013). The Federal Arbitration Act provides limited grounds to seek the vacatur of an arbitration award. In Lund-Ross Constructors v. Duke of Omaga, LLC, ___ N.W.3d ___, 33 Neb.App.73, the Nebraska Court of Appeals found that an arbitrator’s conduct warranted the partial vacatur of the award, which granted relief to a subcontractor who filed a counterclaim after the arbitration hearing had closed.
Lund-Ross contracted with Duke of Omaha to build an apartment complex in Omaha. Lund-Ross, in turn, sub-contracted with A Raymond Plumbing. Following completion of the building, Owner withheld payment from Lund-Ross, who in turn, withheld payment from Raymond. Both Lund-Ross and Raymond filed mechanics liens and initiated suits; Raymond’s suit ultimately was dismissed for want of prosecution. Lund-Ross proceeded to arbitration with Owner, naming Raymond as a respondent. Raymond did not participate in the arbitration as a claimant at the time of the hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com
Another Reason to Always Respond (or Hensel Phelps Wins One!)
September 16, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, Hensel Phelps Construction Co. is best known as the company that got whipsawed between indemnity rules and the lack of a statute of limitations for state agencies. However a recent case out of the Federal District Court for the Eastern District of Virginia gave them a win and illustrates, once again, that failing to appear or respond is never a good option.
In Hensel Phelps Construction Co. v. Perdomo Industrial LLC, the Alexandria, VA federal court looked at an arbitration award entered for Hensel Phelps and against Perdomo under the Federal Arbitration Act. The facts of the case showed that Perdomo “double dipped” into the deep end of refusal or failure to respond. First of all, the contract required arbitration and any award was enforceable in any state or federal court having jurisdiction. Based upon this language, Hensel Phelps filed a demand for arbitration with the American Arbitration Association against Perdomo and its surety, AAA sent notice to both Perdomo and Surety, and. . . neither responded or appeared at what was ultimately 8 days of hearings. After hearing Hensel Phelp’s evidence and the total lack of defenses from Perdomo and Surety, the panel issued an award in favor of Hensel Phelps, finding Perdomo LLC in default and holding Perdomo LLC and Allied World jointly and severally liable in the amount of $2,958,209.71 and Perdomo LLC individually liable in the amount of $7,917,666.30 plus interest.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Standard For Evaluating Delay – Directly from An Armed Services Board Of Contract Appeal’s Opinion
October 04, 2021 —
David Adelstein - Florida Construction Legal UpdatesSometimes, it is much better to hear it from the horse’s mouth. That is the case here. The Armed Services Board of Contract Appeal’s (ASBCA) opinion in Appeals of -GSC Construction, Inc., ASBCA No. 59402, 2020 WL 8148687 (ASBCA November 4, 2020) includes an informative discussion of a contractor’s burden when it encounters excusable delay and, of importance, the standard for evaluating delay. It’s a long discussion but one that parties in construction need to know, appreciate, and understand. EVERY WORD IN THIS DISCUSSION MATTERS.
Construction projects get delayed and with a delay comes money because time is money. Many claims are predicated on delay. These can be an owner assessing liquidated damages due to a delayed job or a contractor seeking its costs for delay. Either way, the standard for evaluating delay and the burdens imposed on a party cannot be understated and, certainly, cannot be overlooked. For this reason, here is the discussion on evaluating delay directly from the horse’s mouth in the Appeal of-GSC Construction, Inc.:
The critical path is the longest path in the schedule on which any delay or disruption would cause a day-for-day delay to the project itself; those activities must be performed as they are scheduled and timely in order for the project to finish on time. Wilner v. United States, 23 Cl. Ct. 241, 245 (1991). In Yates-Desbuild Joint Venture, CBCA No. 3350 et al., 17-1 BCA ¶ 36,870, our sister board compiled an excellent and very helpful synopsis of the standards for evaluating delay claims, which I adopt nearly verbatim among the discussion that follows.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homeowners Must Comply with Arbitration over Construction Defects
January 06, 2012 —
CDJ STAFFThe California Court of Appeals has upheld a decision by the Superior Court of Kern County that homeowners must comply with arbitration procedures in their construction defect claim. The California Court of Appeals ruled on December 14 in the case of Baeza v. Superior Court of Kern County, denying the plaintiff’s petition that the trial court vacate its order.
The plaintiffs in the case are homeowners in various developments built by Castle & Cook. The homes were sold with a contract that provided for “nonadversarial prelitigation procedures, including mediation, and judicial reference.” The homeowners made defect claims and argued that Castle & Cooke failed to comply with statutory disclosure requirements and that some of the contracts violate related statutes.
The appeals court found that there was no ground for appeal of the lower court’s order to continue with prelitigation procedures. The court noted that the plaintiffs could not seek a review of the mediation until a judgment was issued, but that then the issue would be moot. The court felt that there were issues presented that needed clarification, and so they reviewed this case. This was cleared for publication.
The court considered the intent of the legislature in passing the Right to Repair Act, noting that “under the statutory scheme, the builder has the option of contracting for an alternative nonadversarial prelitigation procedure,” as established in Chapter 4. The court noted that Chapter 4 “contains no specifics regarding what provisions the alternative nonadversarial contractual provisions may or must include.”
The plaintiffs contended that the builder was in violation of the standards set out in Section 912, however the court responded that these sections set out one set of procedures, but they concluded that “if the Legislature had intended the section 912 disclosure provisions…it could have made the requirements applicable to all builders by locating them in a section outside Chapter 4.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Firm Leadership – New Co-Chairs for the Construction Law Practice Group
July 02, 2024 —
Haight Brown & Bonesteel LLPPartners Yvette Davis and Beth Obra-White have been named co-chairs for the firm’s Construction Law Practice Group. Yvette, Beth and other diverse leaders within the firm play an integral role in the firm’s Diversity, Equity & Inclusion initiatives.
Congratulations to Yvette & Beth for their new roles as practice group leaders!
Reprinted courtesy of
Haight Brown & Bonesteel LLP
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
The Woodland Hills Office Secures a Total Defense Award on Behalf of their High-End Custom Home Builder Client!
June 04, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Daniel Crespo and Associate Theresa Mallen secured a total defense award in arbitration. Our client is a high-end custom home builder with a decades-long flawless record of museum quality construction. Our client was accused of performing substandard construction and the homeowners asserted a multiple million-dollar cost of repair. We took a zero-liability position and argued that the alleged defects were not defects at all but were rather mere reflections of an incomplete project. In sum, our client was forced to terminate the contract and cease construction due to the homeowners’ failure to make progress payments as they became due. The arbitration endured 16 days of testimony scattered over the course of 7 months.
Ultimately, the arbitrator ruled that there were no construction defects at the project and that the homeowners “shall take nothing.” The arbitrator also ruled in favor of our client on its affirmative claim for monies owed by the homeowners’ breach of contract plus interest. A total victory for our client.