Federal Subcontractor Who Failed to Follow FAR Regulations Finds That “Fair” and “Just” are Not Synonymous
April 22, 2019 —
Garret Murai - California Construction Law BlogInscribed over the doors of the U.S. Supreme Court are the words “Equal Justice Under Law.” It’s a reminder that judicial decisions should be just. That doesn’t necessarily mean fair.
In Aspic Engineering and Construction Company v. ECC Centcom Constructors, LLC, U.S. Court of Appeals for the 9th Circuit, Case No. 17-16510 (January 28, 2019), the 9th Circuit overturned an arbitration decision in favor of a local Afghani subcontractor seeking termination costs after it was terminated for convenience by a U.S.-based general contractor. This, despite the arbitrator’s finding that the subcontract was “clearly drafted to give every advantage to” the general contractor, that the local Afghani subcontractor’s “experience with government contracting [was] not nearly as extensive as that of” the general contractor, and “that the normal business practices and customs of subcontractors in Afghanistan were more ‘primitive’ than those of U.S. subcontractors experienced with U.S. Government work.”
Aspic Engineering and Construction
Local Afghani subcontractor Aspic Engineering and Construction Company was awarded two subcontracts by ECC Centcom Constructors the general contractor on two projects in Afghanistan overseen by the United States Army Corps of Engineers. The first subcontract involved construction of various buildings in the Badghis province of Afghanistan . The second subcontract involved the construction various buildings Sheberghan province of Afghanistan . Both subcontracts included clauses from the Federal Acquisition Regulation (FAR), which were incorporated by reference, and included flow-down provisions obligating Aspic to ECC in the same manner that ECC was obligated to the U.S. government.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
Bert L. Howe & Associates to Join All-Star Panel at West Coast Casualty Seminar
March 26, 2014 —
Beverley BevenFlorez-CDJ STAFFDon MacGregor of Bert L. Howe & Associates, a consulting firm, will join fellow panelists Hon. Peter Lichtman (ret), Hon. Nancy Wieben Stock (ret), Peter S. Curry, Brian Kahn, Esq., and Paul R. Kiesel, Esq in a break-out discussion entitled “Working Smarter with Technology” at this year’s West Coast Casualty Construction Defect Seminar being held May 15th-16th at the world-famous Disneyland Hotel in Anaheim, California.
West Coast Casualty's Construction Defect Seminar is the largest seminar of its kind worldwide focusing on all of the elements of the prosecution, defense, coverage and technologies of construction defect claims and litigation from a national perspective.
With offices in California, Nevada, Colorado, Florida and Texas (Houston & San Antonio), Bert L. Howe & Associates provides construction consulting and expert witness services to insurance professionals and lawyers specializing in construction defect litigation, construction risk analysis, and property claims arising from construction-related activities.
Download an Invitation and Register... Read the court decisionRead the full story...Reprinted courtesy of
The Anatomy of a Construction Dispute Stage 3- The Last Straw
January 28, 2015 —
Christopher G. Hill – Construction Law MusingsOver the past two weeks here at Construction Law Musings, I’ve discussed the first two stages of a typical construction dispute (if such a thing exists): the claim, and how to bring heat short of litigation/arbitration. As promised, this week I’ll be discussing the next step or “last straw” in a construction dispute, namely, arbitration or litigation to enforce all of those rights that you preserved in the first two stages.
Construction litigation is expensive, time consuming, and, quite frankly, a pain in the neck. Because of this fact, I almost always recommend that my construction clients exhaust all of the non-litigation methods (including mediation of course) of resolving their disputes prior to “going nuclear” and filing suit. Unfortunately, even the most diligent attempts at less formal resolution means can be unfruitful and more formal means become necessary.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
New Nafta Could Settle Canada-U.S. Lumber War, Resolute CEO Says
February 02, 2017 —
Jen Skerritt - BloombergA renegotiation of Nafta could be used to settle a lumber dispute that’s been simmering between Canada and the U.S. for decades and threatens to make housing unaffordable for thousands of Americans, according to the world’s largest newsprint maker.
Read the court decisionRead the full story...Reprinted courtesy of
Jen Skerritt, BloombergMs. Skerritt may be followed on Twitter @jenskerritt
Big Data Meets Big Green: Data Centers and Carbon Removal Compete for Zero-Emission Energy
October 15, 2024 —
Robert A. James, Sidney L. Fowler & Ashleigh Myers - Gravel2Gavel Construction & Real Estate Law BlogArtificial intelligence, data centers, carbon removal and zero-emission power may sound like a winning line (plus the Free Space) on a 2024 Buzzword Bingo card. But the concepts have come into dramatic real-world tension as private and public actors seek to accommodate the digital and environmental imperatives for green energy.
After years of fairly stable demand, punctuated by declines during the pandemic and economic slumps, electricity demand is projected to double by 2050. A principal cause is the rapid expansion in the power needed to energize and cool servers amid explosive growth in the number and size of data centers, crypto miners, and other point sources of computation. Data centers were 3% of U.S. demand and are projected to be up to 9% or more by 2030; AI will drive a 160% surge in data center demand by 2030. A commentator notes, “We haven’t seen [growth like] this in a generation.”
Reprinted courtesy of
Robert A. James, Pillsbury,
Sidney L. Fowler, Pillsbury and
Ashleigh Myers, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Mr. Fowler may be contacted at sidney.fowler@pillsburylaw.com
Ms. Myers may be contacted at ashleigh.myers@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Boyfriend Pleads Guilty in Las Vegas Construction Defect Scam Suicide
November 07, 2012 —
CDJ STAFFOne of the odder twists of the Las Vegas construction defect scandal was the charge that Nancy Quon’s boyfriend helped her in an initial suicide attempt. Quon, implicated by not charged in the case of taking control of homeowner boards in order to profit from construction defect settlements. William Webb was alleged to have bought the drug GBH in order to allow Quon, his girlfriend, to commit suicide. Ms. Quon later overdosed on a combination of alcohol and prescription drugs.
In addition to pleading guilty to the drug charges, Webb also made a plea bargain with prosecutors in which he did not admit guilt in an insurance fraud charge, but acknowledged that prosecutors would likely be successful at obtaining a conviction. Webb will be sentenced February 7 and is expected to receive a sentence of six years imprisonment.
Read the court decisionRead the full story...Reprinted courtesy of
Is The Enforceability Of A No-Damage-For-Delay Provision Inappropriate For Summary Judgment
February 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesIs the enforceability of a no-damage-for-delay provision inappropriate for resolution on a summary judgment? The recent decision in U.S. f/u/b/o Kingston Environmental Services, Inc. v. David Boland, Inc., 2019 WL 6178676 (D. Hawaii 2019), dealing with Florida law, suggests that it is inappropriate for a summary judgment resolution, particularly when there is a right to a jury trial.
In this case, a prime contractor was hired on a federal construction project in Hawaii. The prime contractor hired a subcontractor and the subcontractor sued the prime contractor and its surety under the Miller Act. Of interest, the subcontractor was seeking to recover for the costs it incurred due to construction delays. The prime contractor moved for summary judgment as to the no-damage-for-delay provision in the subcontract. The no-damages-for-delay provision read as follows (and it is a well-written no-damage-for-delay provision):
The Subcontractor expressly agrees that the Contractor shall not be liable to the Subcontractor for any damages or additional costs, whether foreseeable or unforeseeable, resulting in whole or in part from a delay, hindrance, suspension, or acceleration of the commencement or execution of the Work, caused in whole or in part by the acts or omissions, whether negligent or not, of the Contractor including other subcontractors or material suppliers to the Project, its agents, employees, or third parties acting on behalf of the Contractor. The Subcontractor’s sole remedy for any such delay, hindrance, suspension, or acceleration shall be a noncompensable time extension.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court of Appeals Discusses Implied Duty of Good Faith and Fair Dealing in Public Works Contracting
August 17, 2017 —
Lindsay K. Taft - Ahlers & Cressman PLLCThe implied duty of good faith and fair dealing is implied in every contract, including construction contracts. Generally speaking, this implied duty requires parties cooperate with one another so that they each obtain the full benefit of their contracted bargain. Recently, the Court of Appeals (Division II) in Nova Contracting, Inc. v. City of Olympia discussed this duty’s application to a public works contract.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay K. Taft, Ahlers & Cressman PLLCMs. Taft may be contacted at
ltaft@ac-lawyers.com