Labor Development Impacting Developers, Contractors, and Landowners
June 25, 2019 —
John Bolesta & Keahn Morris - Sheppard Mullin Construction & Infrastructure Law BlogIt is unlawful for unions to secondarily picket construction sites or to coercively enmesh neutral parties in the disputes that a union may have with another employer. This area of the law is governed by the National Labor Relations Act (“NLRA”), the federal law that regulates union-management relations and the National Labor Relations Board (“NLRB”), the federal administrative agency that is tasked with enforcing the NLRA. But NLRB decisions issued during the Obama administration have allowed a union to secondarily demonstrate at job sites and to publicize their beefs over the use of non-union contractors there, provided the union does not actually “picket” the site. In those decisions, the NLRB narrowed its definition of unlawful “picketing,” thereby, limiting the scope of unlawful activity prohibited by law. Included in such permissible nonpicketing secondary activity is the use of stationary banners or signs and the use of inflatable effigies, typically blow-up rats or cats, designed to capture the public’s attention at an offending employer’s job site or facilities.
A recently released NLRB advice memo, however, signals the likely reversal of those earlier decisions and that contractors and owners may now be able to stop such harassing union job site tactics simply by filing a secondary boycott unfair labor practice change with the NLRB. The 18 page memo, dated December 20, 2018 (and released to the public on May 14, 2019), directs the NLRB’s Region 13 to issue a complaint against the Electrician’s Union in a dispute coming out of Chicago where the union erected a large, inflatable effigy, a cat clutching a construction worker by the neck, and posted a large stationary banner proclaiming its dispute to be with the job’s general contractor over the use of a non-union electrical sub at the job site’s entrance. Though not an official Board decision, the memo suggests the NLRB General Counsel’s (GC) belief that the earlier Obama era decisions may have been wrongly decided and should be reconsidered by the NLRB on the theories that the Union’s nonpicketing conduct was tantamount to unlawful secondary picketing, that it constituted “signal” picketing that unlawfully induced or encouraged the employees of others to cease working with the subs or that it constituted unlawful coercion.
Reprinted courtesy of
John Bolesta, Sheppard Mullin and
Keahn Morris, Sheppard Mullin
Mr. Bolesta may be contacted at jbolesta@sheppardmullin.com
Mr. Morris may be contacted at kmorris@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Nonparty Discovery in California Arbitration: How to Get What You Want
January 08, 2019 —
Leilani L. Jones - Payne & FearsOpting for arbitration requires attorneys to balance efficiency and procedural protections. The implications of arbitration are something clients certainly have to carefully consider both when drafting arbitration provisions, and after initiating a demand. While arbitration can in many respects streamline the civil discovery process, one of the largest roadblocks for cases in California arbitrations is “streamlining” discovery from nonparties. This article explores the challenges presented by third party discovery in arbitration, and proposes strategies for obtaining such discovery efficiently and expeditiously.
Read the court decisionRead the full story...Reprinted courtesy of
Leilani L. Jones, Payne & FearsMs. Jones may be contacted at
llj@paynefears.com
Mich. AG Says Straits of Mackinac Tunnel Deal Unconstitutional
June 03, 2019 —
Jeff Yoders - Engineering News-RecordMichigan Attorney General Dana Nessel (D) has declared unconstitutional a late-2018 law that would create an authority to oversee construction of a key tunnel. The tunnel would house an oil-and-gas pipeline under the Straits of Mackinac.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Yoders, ENRMr. Yoders may be contacted at
yodersj@enr.com
Construction Defect Lawsuit Came too Late in Minnesota
June 28, 2013 —
CDJ STAFFThe Minnesota Court of Appeals has upheld a summary judgment in a construction defect case, Lee v. Gorham. Minnesota law requires that contractors warranty that the home will be free of major construction defects during the first ten years, but claims must “be brought within two years of the discovery of the breach.” The Lees received a home inspection report in 2009 that identified a variety of defects, including “several possible structural defects.” The court noted that the report stated, “Contact your builder in writing of the findings, and discuss your options with an attorney.”
The Lees contacted the contractor, Gorham Builders. After initial silence, Gorham told the Lees that problems would “have to be ‘turned over to [the] insurance company.’” Rodney noted in his testimony that he had two choices, to either sue Gorham or hire an outside contractor. Mr. Lee had concluded that the legal costs were likely to be equal to the cost of the contractor.
In June, 2011, the Lees changed their mind about bringing a suit. Gorham sought and received a summary judgment dismissing the case on the grounds that too much time had passed since the Lees learned of the construction defect. The Lees appealed.
The appeals court upheld the summary judgment. The Lees claimed that the 2009 home inspection did not alert them of a “major construction defect,” but the court concluded that the language of the report fit within the Minnesota statutory definition of a “major construction defect.”
Nor was the appeals court convinced that at any time did Gorham provide “assurances that it would cure the defects to the home.” Within the same month as the May 2009 inspection, Gorham had made it clear that any problems were an issue for the insurance company. Thus, the appeals court concluded that the Lee’s equitable-estoppel argument was without merit.
The Lees also brought to appeal the new argument that they did not realize they were dealing with “major construction defects” until they received a subsequent home inspection in 2011. The court noted that the second report does not detail “new defects or structural issues not identified in the 2009 inspection report.” In addition to being “without merit,” the court noted that this claim was not made in the district court and so the appeals court “need not consider this issue on appeal.”
Read the court decisionRead the full story...Reprinted courtesy of
Crossrail Audit Blames Busted Budget and Schedule on Mismanagement
August 13, 2019 —
Peter Reina - Engineering News-RecordIn a new report on London’s Crossrail, the U.K. National Audit Office says the beleaguered transportation project is around two years late and nearly 20% over budget because of poor management. The NAO, charged by Parliament with monitoring public spending, pointed to ill-conceived “aspirational” plans that proved to be unfit for the technologically challenging and vast program when things went wrong.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Reina, ENR
Measure of Damages for a Chattel Including Loss of Use
November 16, 2020 —
David Adelstein - Florida Construction Legal UpdatesIn a non-construction case, but an interesting case nonetheless, the Second District Court of Appeals talks about the measure of damages when dealing with chattel (property) including loss of use damages. Chattel, you say? While certainly not a word used in everyday language, a chattel is “an item of tangible movable or immovable property except real estate and things (such as buildings) connected with real property.” Equipment, machinery, personal items, furniture, etc. can be considered chattel.
With respect to the measure of damages for a chattel:
“Where a person is entitled to a judgment for harm to chattels not amounting to a total destruction in value,” the plaintiff may make an election out of two theories of recovery in addition to compensation for the loss of use. Badillo v. Hill, 570 So. 2d 1067, 1068 (Fla. 5th DCA 1990) (quoting Restatement of Torts § 928 (Am. Law Inst. 1939)). In addition to compensation for the loss of use, the plaintiff may elect either “the difference between the value of the chattel before the harm and the value after the harm” or “the reasonable cost of repairs or restoration where feasible, with due allowance for any difference between the original value and the value after repairs.” Id. (quoting Restatement of Torts § 928).
Sack v. WSW Rental of Sarasota, LLC, 45 Fla.L.Weekly D2306a (Fla. 2d DCA 2020).
Sack is a good example of a case dealing with the measure of damages with a chattel, here, an aircraft, including loss of use damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Common Law Indemnity Claim Affirmed on Justifiable Beliefs
June 30, 2016 —
Rick Erickson – Snell & Wilmer Real Estate Litigation BlogYesterday, the Arizona Court of Appeals issued an interesting opinion in Hatch Development v. Solomon. Hatch illustrated two key points in real estate and construction litigation: (1) a contractor’s indemnity does not always require an expressly written obligation; and (2) when facts are undisputed that a contractor is solely at fault for a construction defect, a property owner can be indemnified after paying a neighboring property owner for damages caused by the contractor’s defective work.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr. Erickson may be contacted at
rerickson@swlaw.com