Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Spain Risks €10.6 Billion Flood Damage Bill, Sanchez Says
November 25, 2024 —
Rodrigo Orihuela, Macarena Munoz Montijano & Jorge Zuloaga - BloombergSpanish Prime Minister Pedro Sanchez announced the first financial package for victims of the storms that killed more than 200 people in the country’s eastern region of Valencia.
Spain will earmark as much as €10.6 billion ($11.5 billion) for its first relief package and more will be announced in the future, Sanchez said in a press conference Tuesday in Madrid. The package includes direct aid for households, self-employed workers and firms; state-backed credit guarantees for companies and residents; and funds for city governments to pay for repairs and reconstruction.
Reprinted courtesy of
Rodrigo Orihuela, Bloomberg,
Macarena Munoz Montijano, Bloomberg and
Jorge Zuloaga, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Ambiguity Kills in Construction Contracting
February 15, 2018 —
Christopher G. Hill – Construction Law MusingsWell, I’m back and hope to have a more consistent publishing schedule moving forward. I appreciate the continued readership through what has been a busy time for
my solo construction practice over the last couple of months. Now, back to our program. . .
Here at Construction Law Musings, I have often beaten the drum of
a solid contract that leaves as little as possible to chance or the dreaded “grey areas” where we construction lawyers like to make money. An example of the issues that can arise from ambiguity can be found in a case from 2017 in the
Western District of Virginia, W.C. English, Inc. v. Rummel, Klepper & Kahl, LLP et al
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill – The Law Officeof Christopher G. Hill, PC
OSHA Advisory Committee, Assemble!
February 06, 2023 —
Rachel E. Pelovitz - Construction ExecutiveThe Occupational Safety and Health Administration (OSHA) has sourced new members for its Advisory Committee on Construction Safety and Health, which was established by the Construction Safety Act to provide “advice and assistance in construction standards and policy matters” to the assistant secretary of labor for occupational safety and health. The committee consists of 15 members, one appointed by the secretary of labor, to represent the interests of employers, employees, state safety and health agencies, in addition to the public.
Reprinted courtesy of
Rachel E. Pelovitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Ms. Pelovitz may be contacted at pelovitz@abc.org
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court of Wisconsin Applies Pro Rata Allocation Based on Policy Limits to Co-Insurance Dispute
February 18, 2019 —
Brian Margolies - TLSS Insurance Law BlogIn its recent decision in Steadfast Insurance Company v. Greenwich Insurance Company, 2019 WL 323702 (Wis. Jan. 25, 2019), the Supreme Court of Wisconsin addressed the issue of contribution rights as among co-insurers.
Steadfast and Greenwich issued pollution liability policies to different entities that performed sewer-related services for the Milwaukee Metropolitan Sewerage District (MMSD) at different times. MMSD sought coverage under both policies in connection with underlying claims involving pollution-related loss. Both insurers agreed that MMSD qualified as an additional insured under their respective policies, but Greenwich took the position that its coverage was excess over the coverage afforded under the Steadfast policy, at least for defense purposes, and that as such, it had no defense obligation.
Read the court decisionRead the full story...Reprinted courtesy of
Brian Margolies, Traub LiebermanMr. Margolies may be contacted at
bmargolies@tlsslaw.com
Out of Eastern Europe, a Window Into the Post-Pandemic Office
September 28, 2020 —
Andra Timu & Irina Vilcu - BloombergSpecial quarantine rooms. Floor-to-ceiling walls in bathroom stalls. Touchless entrances that take your temperature. This is what telecommunications company Ericsson’s office building in Bucharest looks like after coronavirus. The space has become the pilot for a 100-prong coronavirus standard that a real estate investor in Eastern Europe is pitching as a new global “immune” building standard.
Liviu Tudor, president of the Brussels-based European Property Federation, hopes the standard will convince more employees to go back to work. He’s gathered a team of experts in construction, health care and engineering, such as such as Adrian Streinu-Cercel, the head of Bucharest's biggest infectious diseases hospital, to develop three tiers of “immune” building certifications that he says are intended to make indoor spaces “pandemic proof.”
Read the court decisionRead the full story...Reprinted courtesy of
Andra Timu & Irina Vilcu, Bloomberg
County Elects Not to Sue Over Construction Defect Claims
June 18, 2014 —
Beverley BevenFlorez-CDJ STAFFEven though repairs are expected to cost four million, the New Hanover County Board of Commissioners announced that they will not be pursuing litigation against Clancy and Theys Construction Company for their alleged construction defects of their work on the W. Allen Cobb Judicial Annex in North Carolina, according to Star News Online.
“The board stated that taxpayer money would be better spent on the repairs than on a lengthy court case,” reported Star News Online. “But as a result of the faulty work, the board removed the company from its list of prequalified bidders and stated that it would not be eligible to work on other county construction projects.”
Read the court decisionRead the full story...Reprinted courtesy of
California Courts Call a “Time Out” During COVID-19 –New Emergency Court Rules on Civil Litigation
May 04, 2020 —
Tara C. Dudum - Newmeyer Dillion“We are at this point truly with no guidance in history, law, or precedent. To say that there is no playbook is a gross understatement of the situation.”
-Chief Justice and Chair of the California Judicial Council, Tani G. Cantil-Sakauye
Seeking to sustain essential court services while balancing weighty considerations, including litigants’ due process rights, access to justice, and stringent health and safety orders, the California Judicial Council has adopted Emergency Rules in response to the ongoing coronavirus pandemic (COVID-19).
While many of the Emergency Rules focus on criminal and juvenile dependency matters, this update highlights the Emergency Rules immediately impacting civil litigation in California state courts. The following Emergency Rules remain in effect until 90 days after the Governor lifts the state of emergency or the rule is amended or repealed by the Judicial Council:
Tolling of Statutes of Limitation in Civil Actions
Effective April 6, 2020, the statutes of limitation (the time period in which to bring a claim) for all civil causes of action is tolled until such time as the rule is no longer in effect. The impact of this rule is that it provides plaintiffs with more time to bring claims and extends the time period that defendants may face legal action for alleged violations of the law.
Read the court decisionRead the full story...Reprinted courtesy of
Tara C. Dudum, Newmeyer DillionMs. Dudum may be contacted at
tara.dudum@ndlf.com