The Importance of Preliminary Notices on Private Works Projects
September 03, 2019 —
William L. Porter - Porter Law GroupTime and time again I receive calls from subcontractors and suppliers who find themselves faced with a customer who is either unwilling or unable to pay for labor or materials supplied for a private works project. As an attorney, the first question I usually ask is “did you serve a Preliminary Notice?” The second question I usually ask is “did you serve the Notice within twenty (20) days after first furnishing labor, service, equipment or materials to the job site?” The answers to these questions will often determine the ability to collect on the claim.
The excuses for failing to serve the Preliminary Notice range from “for the last ten years the customer has always paid on time” to “I didn’t want to imply the contractor was not going to pay me” to “it is too much trouble to do on every job” or, simply, “I forgot”. Contractors and suppliers are well advised that any subcontractor or supplier who fails to properly and timely serve a Preliminary Notice is depriving itself of the most powerful tool available for compelling payment of construction related debt on a private works project. For all but the smallest contracts failure to serve the Preliminary Notice is also a violation of contractors’ license law and constitutes grounds for discipline by the Contractor State License Board, up to and including suspension of the contractor’s license.
Most of these rules are found in California Civil Code Section 8200-8216. The requirements of these sections are far too numerous to itemize here. Suffice it to say every contractor, subcontractor and construction material supplier to private construction projects should be familiar with these sections of the California Civil Code. They set forth most of the rules which relate to Preliminary Notices on private construction projects. Some of the most important features are as follows:
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
“Good Faith” May Not Be Good Enough: California Supreme Court to Decide When General Contractors Can Withhold Retention
March 22, 2018 —
Erinn Contreras and Joy O. Siu – Construction & Infrastructure Law BlogIt is industry standard in California for owners of a construction project to make monthly payments to a contractor for work it has completed, less a certain percentage that is withheld as a guarantee of future satisfactory performance. This withholding is called a retention. Contractors generally pass these withholdings on to their subcontractors via a retention clause in the subcontract. Under such clause, if a subcontractor fails to complete its work or correct deficiencies in its work, the owner and the general contractor may use the retention to bring the subcontractor’s work into conformance with the requirements of the contract.
When and how retention payments must be released are governed by, among other statutes, Civil Code section 8800
et seq. Specifically, Civil Code section 8814, subdivision (a), states that a direct contractor must pay each subcontractor its share of a retention payment within ten days after the general contractor receives all or part of a retention payment. Failure to make payments in accordance with Section 8814 can subject an owner or a contractor to a (1) two percent penalty per a month on the amount wrongfully withheld, and (2) claim for attorney’s fees for any litigation required to collect the wrongfully withheld retention payments. (Civ. Code, § 8818.)
Reprinted courtesy of
Erinn Contreras, Sheppard, Mullin, Richter & Hampton LLP and
Joy Siu, Sheppard, Mullin, Richter & Hampton LLP
Ms. Contreras may be contacted at econtreras@sheppardmullin.com
Ms. Siu may be contacted at jsiu@sheppardmullin.com
Read the court decisionRead the full story...Reprinted courtesy of
Lakewood Introduced City Ordinance to Battle Colorado’s CD Law
September 24, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Denver Post, the Lakewood City Council “introduced an ordinance that would make it more difficult for homeowners associations to sue developers for construction defects and give builders more opportunity to fix problems before litigation begins.” A hearing and final vote is scheduled for October 13th.
"If there are defects, we want to get them fixed rather than dragging this through the courts for years," Lakewood Mayor Bob Murphy told The Denver Post. Murphy believes the ordinance will bring “more diverse housing options to Lakewood, especially around stations along the Regional Transportation District’s West Rail Line.” Lakewood’s City Planner Travis Parker also declared that the defects law is to blame for the lack of condos in the area.
However, some believe that “Lakewood is overstepping its bounds as a home-rule city,” according to The Denver Post. "What they're trying to do is use an ordinance to circumvent state law in order to make it impossible for homeowners to seek redress against builders for defects," Molly Foley-Healy an attorney who serves as legislative liaison for the Community Associations Institute's Legislative Action Committee told the Post. “Mayor Murphy needs to incentivize quality construction in Lakewood instead.”
Read the court decisionRead the full story...Reprinted courtesy of
Power & Energy - Emerging Insurance Coverage Cases of Interest
November 30, 2020 —
David G. Jordan & Tiffany Casanova - Saxe Doernberger & Vita, P.C.The Power & Energy sector faces a multitude of risks that impact output and profitability, requiring sound risk management and robust insurance programs. As of recent, like most industries, there have been significant challenges facing the industry in light of COVID-19. These issues, including decreased product demand as well as supply- side issues, have been well documented. However, other issues continue to impact Power & Energy providers, with significant insurance coverage implications that are worthy of note. Below is a summary of three open cases of interest, where declaratory relief has been sought by energy providers’ insurance carriers, seeking an avoidance of coverage.
1. Fracking Dispute and “Intentional Acts”
In the Texas case of The James River Insurance Co. v. Clearpoint Chemicals LLC et al., No. 4:20-cv-0076 (N.D.Tex), James River Insurance Company (“James River”) is asking a federal district court to declare that it does not owe defense or indemnity to its insured for acts it defines as both intentional and/or malicious acts.
Reprinted courtesy of
David G. Jordan, Saxe Doernberger & Vita, P.C. and
Tiffany Casanova, Saxe Doernberger & Vita, P.C.
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Ms. Casanova may be contacted at TCasanova@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
No Duty to Indemnify Where No Duty to Defend
February 08, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Montana Supreme Court held that because there was no duty to defend the insureds' intentional acts, the insurer had no duty to defend. Farmers Ins. Exch. v. Wessel, 2020 Mont. LEXIS 2617 (Mont. Dec. 22, 2020).
The insureds' property was accessed by Turk Road. Turk Road was also used by the neighbors to access their land. The insureds asked for permission to snowmobile across the neighbors' property. Permission was denied because the property was in a conservation easement which prohibited motorised used. The insureds' thereafter retaliated by not allowing the neighbors to use Turk Road. The neighbors then purchased an easement from another landowners to construct a new driveway which did not traverse the insureds' property. The insureds built snow berms and gates, felled trees, and created other obstacles to prevent the neighbors from using the new driveway. Physical threats were also made by the insureds.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Intellectual Property And Employment Law Best Practices: Are You Covering Your Bases In Protecting Construction-Related Trade Secrets?
November 15, 2021 —
Colin Holley - ConsensusDocsThere are four main types of intellectual property (IP) – patents, copyrights, trademarks and trade secrets. Many companies have IP rights of all four types. Very different steps are required to protect different types of IP. Your company should work with an experienced IP attorney to develop and continuously update a comprehensive IP protection plan. And for the reasons discussed below, it is important for your company’s IP protection plan to be closely coordinated with employment and contracting practices.
Patents are rights that may be granted to protect uniquely-original and usable inventions for a prescribed period of years, the length of which depends on the patent type. To register a patent, an application must be filed with the United States Patent and Trademark Office (USPTO), which will decide whether the invention is patentable. A registration gives the owner the ability to prevent others from using or selling the invention without permission. Registered patents may be challenged in court on several grounds, but mounting a successful challenge is a very expensive proposition. A patent registration is thus a highly valued asset and is key to preventing others from using or copying your invention, unless you have a foolproof way to keep your invention secret and out of the hands of competitors. On the other hand, if it is possible to keep the invention secret for enough time to gain a commercial advantage over competitors and the enforceability of the patent is questionable, registering a patent may be a mistake because the invention must be publicly disclosed in excruciating detail, for all competitors to see.
Read the court decisionRead the full story...Reprinted courtesy of
Colin Holley, Watt, Tieder, Hoffar, & Fitzgerald, LLPMr. Holley may be contacted at
cholley@watttieder.com
Big League Dreams a Nightmare for Town
April 03, 2013 —
CDJ STAFFThe town of Gilbert, Arizona had their own big dreams for Big League Dreams Gilbert, which the town was convinced would bring in financial benefits. Now the amateur sports complex is plagued by defects and failing infrastructure. The town was wondering how to create sufficient recreation facilities when Big League Dreams made a proposal that would bring tax revenue from a new stadium complex.
Ten years later, Gilbert says it’s not getting enough of the revenue from the parks. The proposal, created by Big League Dreams, estimated an economic benefit of $40 million over 30 years with a construction cost of $22.7 million. Instead, construction ran to $42.7 million and over the last two years the town has received only $250,570.
Then there are the construction defects. The structure was warranteed for only one year. That warrantee long over, the complex has problems with various concrete surfaces and has generated injury claims. The town did not inspect the park after Big League Dreams started operating it. They later found out that some parts did not conform to code, with 39 problem areas referenced in a report. Some of these included safety issues like missing handrails.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of