An Oregon School District Files Suit Against Robinson Construction Co.
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Tigard-Tualatin School District in Tigard, Oregon filed a lawsuit against Robinson Construction for water damage to the Alberta Rider Elementary school, built in 2005, according to The Oregonian. The school district “is seeking $1.4 million in damages.”
According to the suit, as quoted by The Oregonian, the school district “holds Robinson responsible for faulty construction of the school’s panel siding, windows, doors, exterior walls and more.”
Repairs began in December of 2011, reported The Oregonian, and the cost so far is more than one million: “The district had to replace parts of the ‘exterior wall cladding system’ and remove and reinstall ‘storefront windows and window/door assemblies to ensure watertight performance,’ in addition to other alterations, the lawsuit reads.”
Read the court decisionRead the full story...Reprinted courtesy of
You're Doing Construction in Russia, Now What?
May 16, 2022 —
Anazette Ray & Michael Vardaro - Zetlin & De Chiara LLPIn recent weeks, there has been a long list of companies, from all industries spanning from construction/engineering to fashion and hospitality, that have announced that they are completely severing ties with Russia, while a host of others have announced a temporary halt. See Jeffrey A. Sonnenfeld, Over 400 Companies Have Withdrawn from Russia – But Some Remain, Yale School of Management (Updated Mar. 21, 2022), https://som.yale.edu/story/2022/over-400-companies-have-withdrawn-russia-some-remain?utm_campaign=mb. For those developers, EPC contractors, and design professionals (engineers and architects) who have construction projects in Russia, the question is, “How should we proceed?”
The U.S. initially stated that it was not issuing a total embargo on business dealings and trade relations with Russia in response to the nation’s invasion of Ukraine. Instead, the U.S., along with many other Western nations, issued targeted sanctions. See Francesco Giumelli, Understanding Targeted U.N. Sanctions: An Empirical Analysis, International Affairs, 91(6), 1351-1368 (explaining the difference between embargoes and targeted sanctions). However, after evidence of war crimes by Russia emerged, President Biden issued an Executive Order prohibiting U.S. individuals, whether in the states or abroad, from new investments in Russia and prohibiting U.S. individuals from transactions with Russian state-owned entities. See April 6, 2022, Presidential Actions, https://www.whitehouse.gov/briefing-room/presidential-actions/2022/04/06/prohibiting-new-investment-in-and-certain-services-to-the-russian-federation-in-response-to-continued-russian-federation-aggression/. This new Executive Order is said to not affect existing contracts in Russia, but instead prohibits new ones.
Reprinted courtesy of
Anazette Ray, Zetlin & De Chiara LLP and
Michael Vardaro, Zetlin & De Chiara LLP
Ms. Ray may be contacted at aray@zdlaw.com
Mr. Vardaro may be contacted at mvardaro@zdlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Litigation Roundup: “Based on New Information …”
August 01, 2023 —
Daniel Lund III - LexologyBased on new information … your arbitration award is thrown out!
So said the United States Eleventh Circuit Court of Appeals, affirming a district court’s vacatur of the award based upon the award having been procured by fraud.
The lower court ruled as it did notwithstanding the fact that the action seeking to have the arbitration award vacated was filed and served beyond the three months allowed by the Federal Arbitration Act, 9 U.S.C. 12.
The party attacking arbitration award alleged that during the course of the arbitration hearing, a witness whose testimony was been handled remotely by videoconference was being inappropriately aided: the witness was being instructed remotely – by texting – by the corporate representative for his company, who was entitled to sit in on all portions of the arbitration hearing.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Are COVID-19 Claims Covered by Builders Risk Insurance Policies?
May 04, 2020 —
Jason M. Adams, Gibbs Giden Locher Turner Senet & Wittbrodt LLP and Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.If you are an attorney, insurance broker, or other professional representing developers and contractors, then your clients have likely reached out with concerns about losses related to COVID-19. One common question is whether there is potential coverage under builders risk insurance policies.
The short answer is: It depends. As with most questions pertaining to insurance coverage, the answers depend on the specific policy language and underlying facts required to trigger coverage. Builders risk policies are even more fact specific due to the lack of uniformity of base policy forms and endorsements between insurance carriers.
The first step in any analysis is to gather facts and carefully document any impending and potential damages or delays. The facts are crucial because the coverage analysis may vary depending on the specific reason the project was shut down. For example, the analysis would be different if the project was shut down as a result of an express government order, such as those in Northern California and Washington, versus the project shutting down as a result of workers testing positive for COVID-19. Properly analyzing builders risk coverage involves a granular account of the facts and damages, and can require a great deal of hair splitting with respect to specific policy language.
Regardless of the strength of the insured’s facts and damages, or the breadth of its policy language, the policyholder still likely faces an uphill battle in finding coverage for COVID-19 related claims. The unfortunate reality of most builders risk policies is that they are property policies that require some evidence of physical loss or damage to trigger coverage. Whether or not COVID-19 claims constitute property damage will be the subject of great debate and litigation over the coming months and years. The outcome will likely depend on how the insured’s jurisdiction ultimately rules on the litany of COVID-19 cases that have already been filed – specifically, how broadly each court interprets the meaning of “physical loss or damage.”
Although these key issues have yet to be clearly defined by the courts, some policies are better than others and there are specific variables that could affect the likelihood of coverage. For example, some of the more policyholder-friendly insurance programs may contain coverage extensions for delay in completion, business interruption, loss of rental income, or civil authority that may not be tied to the property damage requirement, and which would tend to support coverage for COVID-19 claims.
Even if the insured crosses the initial threshold and can demonstrate a covered claim, the following common endorsements and exclusions may require additional analysis depending on the facts.
- Virus or Pandemic Exclusions: Virus or pandemic exclusions are not as common on builders risk policies as they may be on other forms of coverage. However, they do exist and, if present, result in a significant barrier to coverage. As with the policy itself, every endorsement is different and should be analyzed in terms of the express language contained in the endorsement and the facts.
- Abandonment or Cessation of Work: Most builders risk policies include provisions that preclude coverage in the event of the abandonment of the project or a lengthy cessation of work. As a result, the insured should take steps to articulate to the carrier that the project has not been abandoned, and that there exists an intent to return as soon as possible. The insured should also maintain a record of ongoing project oversight and protection efforts taken during the period when construction operations are suspended.
- Security and Safety Requirements: Many builders risk policies contain provisions requiring the insured to maintain protective safeguards and security protocols throughout the pendency of the project. Safety fencing, lighting and security guards are common examples. The policy should be analyzed to ensure that the policyholder can meet any such requirements during a COVID-19 related shutdown. For example, can the insured continue to staff a security guard? If not, arrangements will likely need to be made with the carrier depending on the language of the policy.
- Insurable Limits: Builders risk policies are typically underwritten based upon the total completed value of the structure, including materials and labor. The insured will need to analyze the policy to consider whether increased material or labor costs as a result of COVID-19 will alter the terms of coverage, trigger any escalation clauses, or result in an increase in premium due. If increased cost projections become apparent, the insured should report these changes to the carrier immediately.
- Extensions of Coverage: The insurance industry was facing a hard market even before the COVID-19 pandemic, which resulted in higher premiums and limited coverage options. The COVID-19 pandemic has only exacerbated these issues and it may be difficult to obtain coverage extensions on projects that have been shut down. The insured should work with its risk management team (risk manager, insurance broker and lawyer) to engage the carriers to negotiate any necessary coverage extensions resulting from COVID-19 related project delays.
To summarize, builders risk coverage for COVID-19 claims is far from certain, but not impossible. Insureds should provide notice of a claim to all potentially applicable carriers in order to preserve their rights. The insured should also report increased construction cost and articulate its intent to return to the project to preserve their escalation clause and avoid arguments that they have abandoned the project. The insured should continue to document its claims and damages, and be ready to substantiate its claims and push back on any coverage denial. Throughout the entirety of this process, the insured should work with its risk management team to get out in front of any extensions it may need to complete the project. In a climate where insurance carriers are receiving an insurmountable number of claims, the insured should be prepared to fight for coverage and not simply throw up its hands in the face of a denial. Given the intense social, legislative and executive pressure to cover COVID-19 claims, there may be a tendency for the courts to find coverage in gray areas, particularly if the insured was fortunate enough to have purchased one of the broader coverage forms referenced above.
About the Authors
Jason M. Adams, Esq. (jadams@gibbsgiden.com) is a partner at Gibbs Giden representing construction professionals in the areas of Construction Law, Insurance Law and Risk Management and Business/Civil Litigation. Adams is also a licensed property and casualty insurance broker and certified Construction Risk & Insurance Specialist (CRIS). Jason represents developers, contractors, public entities, investors, lenders, REITs, design professionals, and other construction professionals at all stages of the construction process. Jason is a published author and sought-after speaker at seminars across the country regarding high level construction risk management and insurance topics. Gibbs Giden is nationally and locally recognized by U. S. News and Best Lawyers as among the “Best Law Firms” in both Construction Law and Construction Litigation. Chambers USA Directory of Leading Lawyers has consistently recognized Gibbs Giden as among California’s elite construction law firms.
Cheryl L. Kozdrey, Esq. (clk@sdvlaw.com) is an associate at Saxe Doernberger & Vita, P.C., a national insurance coverage law firm dedicated exclusively to policyholder representation and advocacy. Cheryl advises insurance brokers, risk managers, and construction industry professionals regarding optimal risk transfer strategies and insurance solutions, including key considerations for Builder’s Risk, Commercial General Liability, D&O, and Commercial Property policies. She assists clients with initial policy reviews, as well as renewals and modification(s) of existing policies to ensure coverage needs are satisfied. Cheryl also represents policyholders throughout the claims process, and in coverage dispute litigation against insurance carriers. She is currently working on some of the largest construction defect cases in the country. Cheryl is a published author and is admitted to practice in the State of California and all federal district courts within the State.
Read the court decisionRead the full story...Reprinted courtesy of
Assignment Endorsement Requiring Consent of All Insureds, Additional Insureds and Mortgagees Struck Down in Florida
January 24, 2018 —
Tred Eyerly – Insurance Law HawaiiSecurity First Insurance Company's endorsement restricting the ability of policyholders to assign post-loss benefits was struck down by the Florida District Court of Appeal. Security First Ins. Co. v. Florida Office of Ins. Regulation, 2017 Fla. App. LEXIS 18083 (Fla. Ct. App. Dec. 1, 2017).
Read the court decisionRead the full story...Reprinted courtesy of
Tred Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Colorado’s Three-Bill Approach to Alleged Construction Defect Issues
May 01, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the Denver Post, two Colorado construction defect bills have “made their way out of the Senate Affairs Committee Wednesday, with a third reportedly on its way.”
The two bills that have made it out of committee are SB 219 and SB 216: “SB 219 would require the Colorado Division of Housing to prepare a study to present to legislators before March 15, 2015, on why there isn't more affordable housing construction in the state,” the Denver Post reported. “SB 216 directs the Colorado Division of Housing to design a program to rebate a portion of the insurance premiums builders pay as a way to boost their willingness to build more projects.”
However, a third bill would require “homeowners to pursue arbitration or mediation before litigation.”
All three bills are sponsored by Sen. Jessie Ulibarri, D-Commerce City.
Read the court decisionRead the full story...Reprinted courtesy of
The Leaning Tower of San Francisco
January 24, 2018 —
Dave Suggs - CDJ STAFFThe Millennium Tower located at 301 Mission Street in San Francisco, California opened in 2009 and is fifty-eight stories high. It is comprised of expensive apartments with price tags in the millions. “Yet for all its curb appeal, the building has, quite literally one fundamental problem: it’s sinking into mud and tilting towards its neighbors” reports John Wetheim of CBS News in the
60 Minutes segment about the condition of the tower “San Francisco’s Leaning Tower of Lawsuits.”
In the Tower’s basement along columns that protrude from the foundation of the building there are stress gauges lining the walls illustrating cracks with slow growth which is cause for concern. The tower is tilting a total of 14 inches toward the northwest and has sunk 17 inches so far. Petar Marinkovic, an engineer for the European Space Agency estimates that the tower is sinking 1.5 to 2 inches per year.
Jerry Cauthen, a local engineer, weighs in on what he believes is the cause of the sinking and leaning; it was built from concrete instead of steel. “Concrete is often cheaper. And it’s just as good, but it is a lot heavier. And so you got to design your foundation and your sub-surface to support that higher weight.” A local geotechnical engineer, Larry Karp agrees stating that the foundation of a building of this size and weight should be on solid rock (bedrock). The Millennium Tower is sitting on layers debris from the 1906 earthquake, a gold rush landfill, as well as clay, mud, and sand.
There over 20 parties involved in the Millennium Tower lawsuits so far. Solutions to “fix” the tower’s issues range from removing 20 stories from the top of the building to perpetually freezing the ground beneath the building. There are also ongoing mediation talks to determine the feasibility of drilling down to bedrock under a building where a thousand residents are still upstairs.
Read the court decisionRead the full story...Reprinted courtesy of
Competent, Substantial Evidence Carries Day in Bench Trial
February 26, 2024 —
David Adelstein - Florida Construction Legal UpdatesA number of construction disputes, if tried, are tried through a bench trial meaning the judge is serving in the role of the jury in the construction trial. In a bench trial, two points are important. First, “the factual findings of the judge are entitled to the weight of a jury verdict.” Q.G.S. Development, Inc. v. National Lining Systems, Inc., 2024 WL 357984 (Fla. 3d DCA 2024) (internal quotation and citation omitted). Second, “[t]he appellate court is only authorized to reverse if such findings are not supported by competent, substantial evidence.” Id. These two points need to be appreciated when participating in any construction dispute that will be resolved through a bench trial.
A recent construction dispute highlights these two points. In Q.G.S. Development, a contractor was hired to refurbish a golf course which included constructing a lake. The contractor was going to construct the lake, prepare the subgrade, perform dewatering, and it hired a subcontractor to install a reservoir liner at the bottom of the lake.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com