Effective Allocation of Damages for Federal Contract Claims
October 25, 2021 —
Dirk D. Haire, Joseph L. Cohen & Jane Han - ConsensusDocsFederal construction contracts law generally recognizes four basic methods for pricing damages: (1) Actual Cost Method (ACM); (2) Total Cost Method (TCM); (3) Modified Total Cost Method (MTCM); and (4) Jury Verdict Recovery Method (JVRM). In practice, it is difficult to obtain significant recoveries on TCM and JVRM claims, and only marginally easier on MTCM claims. That is because the courts and boards that hear federal government contracts cases have developed a clear preference for the ACM. Despite this preference, many contractors do not have systems in place to maximize their opportunity to recover damages under the ACM. This article introduces various strategies for tracking and allocating damages during project performance in a manner that will support an ACM analysis if a federal construction claim is litigated.
Background: Four Basic Methods for Pricing Damages
The four methods for pricing damages are described, below:
1. Actual Cost Method
The actual cost method claims damages based on records of “actual costs” that were documented during the performance of the contract. All additional costs must be separately recorded from the costs incurred in the normal course of contract performance. Because contractors provide the court or board with documented underlying expenses under the actual cost method, courts and boards prefer this method. However, the actual cost method may not always be feasible where a contractor is confronted with drastic changes early and often in a project.
Reprinted courtesy of
Dirk D. Haire, Fox Rothschild LLP,
Joseph L. Cohen, Fox Rothschild LLP and
Jane Han, Fox Rothschild LLP
Mr. Haire may be contacted at dhaire@foxrothschild.com
Mr. Cohen may be contacted at jlcohen@foxrothschild.com
Read the court decisionRead the full story...Reprinted courtesy of
World’s Biggest Crane Lifts Huge Steel Ring at U.K. Nuclear Site
January 25, 2021 —
Rachel Morison - BloombergThe world’s largest crane hoisted the first of three massive steel rings that will encase one of the reactors at Electricite de France SA’s nuclear construction site in the U.K., a key milestone in getting the project completed on time.
Operators of the 250-meter (820-foot) tall crane, affectionately known as “Big Carl,” lifted the ring that weighs as much as a jumbo jet overnight to take advantage of windless conditions.
Hinkley Point C is the U.K.’s first new nuclear power plant in more than two decades. Once up and running the reactor will generate electricity for six million homes by 2025.
It’s the largest and most advanced infrastructure project in the country and, when finished, will contain 3 million tons of concrete and 50,000 tons of structural steel, enough to build a railway line between London and Rome.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Morison, Bloomberg
New Case Law Alert: Licensed General Contractors Cannot Sue Owners to Recover Funds for Work Performed by An Unlicensed Subcontractor
May 30, 2022 —
Michele A. Ellison & Samantha R. Riggen - Gibbs GidenThe opinion in Kim v. TWA Construction, Inc. (2022 Cal. App. LEXIS 412) issued by the Court of Appeal of California Sixth Appellate District, on May 13, 2022, makes it clear that a properly licensed general contractor cannot bring an action for compensation from an owner for work performed by an unlicensed subcontractor.
California licensing law has long made explicit that an unlicensed contractor cannot bring or maintain any action to collect or recover compensation for work that contractor performed unless they were duly licensed at all times during the performance of that work. This new ruling extends the scope of this restriction to licensed contractors who hired unlicensed subcontractors.
The Underlying Dispute
The case involved a dispute between property owners and their former general contractor and its principal (collectively “TWA”). The property owners hired TWA to construct a home, and during the early stages of the project, TWA hired an unlicensed subcontractor to perform tree trimming services and to remove a large eucalyptus tree. The subcontractor partially removed the eucalyptus tree, but was stopped by a neighbor, and it was discovered that the tree was partly located on the neighbor’s property. The neighbor brought suit against the property owners, and eventually TWA, for the damage. The property owners subsequently filed a cross-complaint against TWA, and TWA in turn filed a cross-complaint against the property owners.
Reprinted courtesy of
Michele A. Ellison, Gibbs Giden and
Samantha R. Riggen, Gibbs Giden
Ms. Ellison may be contacted at mellison@gibbsgiden.com
Ms. Riggen may be contacted at sriggen@gibbsgiden.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Beware: Design-Build Firms Must Review Washington’s Licensing Requirements
October 16, 2018 —
John Krawczyk - Ahlers Cressman & Sleight PLLCDesign-build contracting is a method of project delivery where the contractor provides both architectural/design and building services to the owner. Yet rarely do firms perform both design and building work in equal measure. Rather, in many instances, firms perform the vast majority of their work on the building side while advertising and providing design services for smaller projects using in-house architects.
Regardless of the volume of design-build contracting a firm performs, any firms practicing this method of project delivery must be aware of Washington State’s registration requirement under RCW 18.08.420(1), and specifically the condition that a “designated architect” must serve as a partner, manager or director of the firm’s governing structure.
Read the court decisionRead the full story...Reprinted courtesy of
John Krawczyk, Ahlers Cressman & Sleight PLLCMr. Krawczyk may be contacted at
john.krawczyk@acslawyers.com
Revisiting Statutory Offers to Compromise
August 28, 2023 —
Kathryne Baldwin - Wilke FleuryThe fourth appellate district published an opinion earlier this year in Smalley v. Subaru of America, Inc. (2022) 87 Cal.App.5th 450 that serves as an excellent refresher on requirements of the “998 Offer,” or a statutory offer to compromise pursuant to Code of Civil Procedure (“CCP”) §998.
In Smalley, set in the context of a Lemon Law action, Defendant Subaru made a 998 Offer for $35,001.00, together with attorneys’ fees and costs totaling either $10,000.00 or costs and reasonably incurred attorneys’ fees, in an amount to be determined by the Court. (Smalley, supra, 87 Cal.App.5th at 454.) Plaintiff objected that the offer was not reasonable and the case proceeded to trial. At trial, a jury found in favor of Plaintiff and awarded him a total judgment award of $27,555.74 – far short of the $35,001.00 offer. The trial court found Plaintiff had failed to beat the 998 at trial and that Subaru’s earlier 998 offer was reasonable. Plaintiff appealed the post-judgment order awarding Plaintiff pre-offer costs and Defendant post-offer costs on the grounds that the 998 was not reasonable in that it did not specify whether Plaintiff would be deemed the prevailing party for purposes of a motion for attorneys’ fees. The fourth district affirmed the trial court’s order and engaged in a helpful review of 998 requirements.
Read the court decisionRead the full story...Reprinted courtesy of
Kathryne Baldwin, Wilke FleuryMs. Baldwin may be contacted at
kbaldwin@wilkefleury.com
Congratulations 2024 DE, MA, MD, NJ, NY, and PA Super Lawyers and Rising Stars
June 17, 2024 —
White and Williams LLPWhite and Williams congratulates the fifteen attorneys nominated as Super Lawyers and ten attorneys named Rising Stars across our Delaware, Massachusetts, Maryland, New Jersey, New York and Philadelphia offices. Lawyers are selected through a process that takes into consideration peer recognition and professional achievement. The lawyers named to this year’s list represent a multitude of practices throughout the firm.
Super Lawyers 2024
Attorney |
Super Lawyers Denoted Practice Area (s)
| |
David B. Chaffin |
Business Litigation |
Robert G. Devine |
Personal Injury, Employment Litigation, Products Liability |
David D. Gilliss |
Surety, Construction Litigation, Administrative Law |
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Mass Timber Reduces Construction’s Carbon Footprint, But Introduces New Risk Scenarios
March 04, 2024 —
Michael Bruch & Franck Fumat - Allianz CommercialMass timber has the potential to be a critical building component for the cities of the near future given the need for the construction sector to reduce its reliance on concrete and steel to lower its Co2 emissions. However, as this market grows and mass timber buildings evolve to greater heights, the construction risk landscape will also be transformed, bringing risk management challenges for companies, according to the new Emerging Risk Trend Talk
report from Allianz Commercial.
“The emergence of mass timber as a sustainable construction alternative represents a significant opportunity for the building sector to reduce its carbon footprint while also satisfying a demand for a material that is more cost-efficient but as durable as steel and concrete,” says Michael Bruch, Global Head of Risk Advisory Services at Allianz Commercial. “However, in any industry, deployment of new materials or processes can result in new risk scenarios, potential defects, or unexpected safety consequences, as well as bringing benefits, and mass timber is no different. Given this market’s expected future growth, companies should do all they can to develop a greater understanding of their exposures including fire, water damage, repetitive loss scenarios and even termite infestation, and ensure they have robust loss prevention measures in place to combat these.”
The need for mass timber
The building and construction sector is among the largest contributors to Co2 emissions, accounting for over 34% of energy demand and around 37% of energy and process related Co2 emissions in
2021 [1]. Given emissions reduction is essential to meet climate change commitments around the world, the need for more sustainable solutions in the built environment has become increasingly important, driven by growing investor and consumer concerns, and legislation, regulation and reporting requirements evolving quickly in many jurisdictions around the world.
Read the court decisionRead the full story...Reprinted courtesy of
Allianz Commercial
Code Changes Pave Way for CLT in Tall Buildings and Spark Flammability Debate
May 13, 2019 —
Sam Barnes - Construction ExecutiveAlthough nothing new, the debate over which is better as a building material—wood or concrete—intensified in December following the preliminary approval of new codes for cross-laminated timber and mass timber in tall structures.
The discussion among industry professionals has been less about CLT’s structural capabilities and more about its perceived flammability, with either side offering decidedly different perspectives. Comparatively new to the United States, CLT and mass timber products are constructed of several layers of pressed lumber board stacked in alternating directions.
In December, the International Code Council released the unofficial voting results on several code change proposals, including passage of the entire package of 14 tall mass timber codes. The proposals were presented by the ICC’s Ad Hoc Committee on Tall Wood Buildings, comprised mostly of engineers, architects, building and fire code officials, fire service, materials and testing lab representatives.
Reprinted courtesy of
Sam Barnes, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of