After Restoring Power in North Carolina, Contractor Faces Many Claims
August 10, 2017 —
Jim Parsons - Engineering News-RecordHaving successfully helped to restore power to two North Carolina barrier islands, PCL Civil Constructors now faces the fallout from a July 27 construction incident that forced a week-long evacuation of 60,000 visitors, putting a potential multimillion-dollar dent in the region’s tourism-dependent economy.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Subcontractor Not Liable for Defending Contractor in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe California Court of Appeals has ruled on January 9, 2012 in Hensel Phelps Construction Company v. Urata & Sons Cement, upholding the judgment of the lower court.
Hensel Phelps was the general contractor for a high-rise in Sacramento. They were sued by the owners of the building after problems were discovered in the concrete slabs of the building’s parking garage. Instead of welded steel wire mesh, the slabs had been constructed with fiber mesh. Hensel Phelps filed a cross-complaint against Urata Cement, the subcontractor that had performed the cement work. Urata refused to defend Hensel Phelps. The owners’ case was subsequently dismissed due to the statute of limitations.
Although the original case was over, Hensel Phelps continued in their claims against Urata. “Urata argued that a handwritten interlineation required Hensel Phelps to prove Urata was at fault for the injury alleged in the building owners’ complaint before Urata was obliged to defend Hensel Phelps in that action.”
The lower court concluded that Urata would have been obligated to defend Hensel Phelps if the owners’ lawsuit had alleged that the damage was due to the subcontractor’s work or if evidence at trial established this. The lower court found neither of these true. Instead, the use of the fiber mesh was a design issue and “that decision was outside the scope of the subcontractor’s work.”
During the trial, Hensel Phelps conceded that Urata was not at fault. The appeals court could find no reading of the contract that would cause Urata to be obligated to defend Hensel Phelps, calling Hensel Phelps’s reading of the contact as “grammatically infeasible.”
Judges Nicholson, Raye, and Butz upheld the decision of the lower court and awarded costs on appeal to Urata.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams Celebrates Chambers 2024 Rankings
June 21, 2024 —
White and Williams LLPWhite and Williams practice groups and attorneys have been ranked in this year's Chambers USA 2024 Guide. Among the rankings, the firm has been recognized in the areas of Insurance and Real Estate: Finance in Pennsylvania, and Construction in Maryland.
Chambers recognized Tim Davis, Managing Partner of the Firm, and Nancy Frantz, Chair of the Real Estate Finance Group, both of whom were recognized for Real Estate: Finance. Chambers also ranked Steven Coury, Managing Partner of the Stamford, CT Office, for Real Estate, as well as Randy Maniloff, Partner, and Patricia Santelle, Chair Emeritus/Former Managing Partner and Chair of the Executive Committee, for Insurance. David Marion, Senior Counsel and Chambers’ Senior Statespeople (22-years ranked) was recognized for Litigation: General Commercial. Partner David Gilliss, Managing Partner of the Maryland office, was recognized for Construction and Amy Vulpio, Co-Chair of the Financial Restructuring and Bankruptcy Practice, was recognized for Bankruptcy/Restructuring.
In one review of Tim Davis, a client described, "He's been around a long time; he's seen it all and has an instinctive feel for getting to the right outcome." Davis has been listed for the past four years and was described by Chambers as, “experienced in representing clients, including insurance companies, banks and investments funds, in a wide variety of real estate finance transactions.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Liquidated Damages Clause Not Enforced
October 02, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA liquidated-damages clause was not enforced in a recent case before the Georgia Court of Appeals. The clause did not contain standard provisions that would normally allow a trial court to enforce the clause as written. As a result, the trial court looked beyond the contract to determine whether the City satisfied the requirements for enforcement of the liquidated-damages clause. Below are the relevant excerpts.
City of Brookhaven v. Multiplex, LLC, A23A0843, 2023 WL 4779591 (Ga. Ct. App. July 27, 2023)
Here, the Contract provides for “Liquidated Damages at the rate of $1,000.00 per calendar day” in the last paragraph of the Scope of Work addendum. The Contract lacks, however, any language indicating that the liquidated damages were not intended to be a penalty. See Fuqua Const. Co. v. Pillar Dev., Inc., 293 Ga. App. 462, 466, 667 S.E.2d 633 (2008) (rejecting use of parol evidence where the parties “explicitly agreed” in “unambiguous contract language” that the liquidated damages were not a penalty). Absent such language, the court can look to parol evidence in the record to determine the effect the provision was intended to have. See J.P. Carey Enterprises, 361 Ga. App. at 391-392 (1) (b), 864 S.E.2d 588 (looking to “extrinsic evidence” such as emails, documents, and deposition testimony to determine whether the damages provision at issue was a penalty); see also Gwinnett Clinic, Ltd. v. Boaten, 340 Ga. App. 598, 602-603, 798 S.E.2d 110 (2017) (“Shah’s testimony also suggested that one purpose of the liquidated damages provision was to deter employees from breaching the agreement”).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Can I Record a Lis Pendens in Arizona if the Lawsuit is filed Another Jurisdiction?
September 26, 2022 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogRecent research I did on a case led me to the conclusion that Arizona law recognizes foreign litigation (i.e., a lawsuit filed outside of Arizona) as a justification for the recording of a lis pendens against real property located within Arizona. See
TWE Retirement Fund Trust v. Ream, 198 Ariz. 268 (Ct. App. 2000). Apparently, there’s some debate about whether foreign litigation can support a local lis pendens. See
Boca Petroco, Inc. v. Petroleum Realty II, 285 Ga. 487 (Ga. 2009). As noted in the TWE case, Arizona’s lis pendens statute
(A.R.S. 12-1191) does not discriminate between local or foreign “actions.” As such, if litigation is pending anywhere that affects Arizona real property, a lis pendens can (and probably should) be filed.
Reprinted courtesy of
Ben Reeves, Snell & Wilmer
Mr. Reeves may be contacted at breeves@swlaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Stick to Your Guns on Price and Pricing with Construction Contracts
December 20, 2021 —
Christopher G. Hill - Construction Law MusingsIn recent posts here at Construction Law Musings, I have discussed the need for clarity of contract, trusting your gut, and assuring that your contract has the necessities. All of these bits of advice (along with my usual advice of working with an experienced construction attorney) are true with regard to commercial construction contracts and apply ten fold in a residential construction (read working for a single/family owner on their house). With a residential project, you, as a construction contractor, are likely to be dealing with the difficult combination of an owner with little or no experience relating to how a construction project is supposed to work and an owner that is emotionally invested in the project because it is their home.
Because of the above, and the fact that your project is likely the biggest single investment that the owner has made outside of possibly a prior house, the residential owner will likely be looking over your shoulder and may very well attempt to negotiate down some of the costs that they perceive as the project moves forward. In short, the average person 1. does not know how much the project truly costs the contractor, and 2. feels that because they hold the cash, they can and should have some control over the individual costs of the construction thus making those costs, and by extension, their contract, negotiable right up until the end.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Three Key Takeaways from Recent Hotel Website ADA Litigation
April 26, 2021 —
Shane Singh & Grace Mehta - Lewis BrisboisDespite the COVID-19 pandemic and its chill on the hospitality industry, ADA-related digital lawsuits increased by approximately 23% in 2020. Many of these lawsuits are filed against hotels. The complaints allege that a hotel’s online reservation system failed to provide enough detail for individuals with disabilities to decide if the hotel meets their accessibility needs.
These plaintiffs will often claim that it is insufficient to describe an aspect of a hotel or room as “accessible” because the term is an opinion or conclusion. Plaintiffs argue that a hotel’s reservation system must report specific information, such as the dimensions of space under accessible desks and sinks, the slopes of surfaces, doorway clearance, and numerous other technical requirements under the ADA.
Many hotels are fighting back, arguing that the detail provided is sufficient and in compliance with the ADA. So far this year, in February 2021, two judges in the U.S. District Court for the Central District of California, Judge Percy Anderson and Judge Cormac Carney, agreed with the defendants, dismissing three cases with prejudice.
Reprinted courtesy of
Shane Singh, Lewis Brisbois and
Grace Mehta, Lewis Brisbois
Mr. Singh may be contacted at Shane.Singh@lewisbrisbois.com
Ms. Mehta may be contacted at Grace.Mehta@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Overtime! – When the Statute of Limitations Isn’t Game Over For Your Claim
August 07, 2022 —
Bradley E. Sands, Jones Walker LLP - ConsensusDocsStatutes of limitations establish the period of time within which a claimant must bring an action after it accrues. An action can be filing a lawsuit and, in some instances, filing a demand for arbitration. But a multi-year construction project could be longer than the applicable statute of limitations. For example, under Delaware or North Carolina law, the statute of limitations for a breach of contract is only three years.1 So a claim for breach of a construction contract that occurred (i.e. accrued) at the beginning of a four-year project under Delaware or North Carolina law may expire before the project is completed.
Generally, a claim accrues at the time of the breach (however, it is important to note that this is not always the case and claim accrual could be the subject of an entirely different article). During the course of a multi-year construction project, proposed change orders or claims for additional compensation can sit, unanswered or unpursued, for months. Or, the parties may informally agree as part of regular project communications to put off dealing with a claim head-on until the end of the project. On certain projects, slow-walking a claim is understandable, as a contractor may be hesitant to sue an owner in the middle of a multi-year project and risk upsetting an otherwise good working relationship. But a delay in formally asserting a put-off claim after it accrues could result in the claim falling subject to a statute of limitations defense.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley E. Sands, Jones Walker LLP (ConsensusDocs)Mr. Sands may be contacted at