Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Death of Subcontractor’s Unjust Enrichment Claim Against Project Owner
April 12, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a previous article, I discussed a subcontractor’s
unjust enrichment claim against a project’s owner and the death of this equitable claim if the owner fully paid the general contractor or paid the general contractor for the subcontractor’s work. This can be best summarized from a very short 1995 opinion out of the Fourth District Court of Appeal: “Unjust enrichment is equitable in nature and cannot exist where payment has been made for the benefit conferred. [Owner] paid [General Contractor] the full amount of its contract for the construction project. Accordingly, there can be no unjust enrichment claim to support [Subcontractor’s] claim.” Gene B. Glick Co., Inc. v. Sunshine Ready Concrete Co., Inc., 651 So.2d 90 (Fla. 4th DCA 1995).
Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.
Mr. Adelstein may be contacted at dma@kirwinnorris.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Scary Movie: Theatre Developer Axed By Court of Appeal In Prevailing Wage Determination Challenge
July 19, 2017 —
Steven M. Cvitanovic & Omar Parra - Haight Brown & Bonesteel LLPThe First Appellate District of the California Court of Appeal recently held that the construction of a movie theater, which was performed in furtherance of a city’s redevelopment agenda, constitutes a “public work” within the meaning of California’s prevailing wage law. Cinema West, LLC v. Christine Baker, No. A144265, (Cal. Ct. App. June 30, 2017).
Like many California cities, the City of Hesperia (the “City”) endeavored to revitalize its downtown. In furtherance of this goal, the City acquired vacant property in its downtown with the hope of turning it into a new city hall, a public library, and “complimentary retail, restaurant, and entertainment establishments.” After completing construction of the civic buildings, the City entered into discussions with Cinema West, LLC (“Cinema West”) for the construction of a “state-of-the-art cinema experience.”
Under the agreement with the City, Cinema West agreed to purchase the property from the City at fair market value, obtain financing for the construction costs, and build and maintain the movie theater. The City, on the other hand, agreed to provide Cinema West with an interest-bearing loan forgivable over ten years, and to construct an adjacent parking lot “for use by Cinema West... as a parking lot for the movie theater.” The City, moreover, agreed to issue Cinema West a one-time payment as consideration for the operating covenant.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Omar Parra, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Mr. Parra may be contacted at oparra@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado General Assembly Sets Forth Prerequisites for an Insurance Company to Use Failure to Cooperate as a Defense to a Claim for First Party Insurance Benefits
August 10, 2020 —
Christine Kroupa, John Palmeri & Katelyn Werner - Gordon & ReesDespite first party insurance policies generally requiring cooperation from an insured in the investigation of a claim, insurers can no longer rely on the failure to cooperate as a defense in a claim for first party insurance benefits in Colorado unless certain conditions are met.
The Bill:
On July 2, 2020, Colorado Governor Jared S. Polis signed House Bill 20-1290 which addresses the ability of an insurer to use a failure to cooperate defense in an action where the insured has made a claim for benefits under an insurance policy. This bill bars an insurer from raising the failure to cooperate unless the following conditions are met:
- The insurer submitted a written request to the insured or the insured’s representative for the information (via electronic means if consent was given by insured or insured’s representative, or via certified mail);
- The information is not available to the insurer without the assistance of the insured;
- The written request provides the insured 60 days to respond;
- The written request is for information a reasonable person would determine the insurer needs to adjust the claim filed by the insured or to prevent fraud; and
- The insurer gives the insured an opportunity to cure, which must:
- Provide written notice to the insured of the alleged failure to cooperate, describing with particularity the alleged failure within 60 days after the alleged failure; and
- Allow the insured 60 days after receipt of the written notice to cure the alleged failure to cooperate.
Reprinted courtesy of Gordon & Rees attorneys
Christine Kroupa,
John Palmeri and
Katelyn Werner
Ms. Kroupa may be contacted at ckroupa@grsm.com
Mr. Palmeri may be contacted at jpalmeri@grsm.com
Ms. Werner may be contacted at kwerner@grsm.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Federal Court Enforces “Limits” and “Most We Will Pay” Clauses in Additional Insured Endorsement
September 13, 2021 —
Craig Rokuson - Traub Lieberman Insurance Law BlogIn the recent case of Zurich Am. Ins. Co. v. XL Ins. Am., Inc., 20-CV-4614 (LJL), 2021 WL 3617218 (S.D.N.Y. Aug. 16, 2021), the United States District Court for the Southern District of New York—in deciding a motion for consideration—had occasion to review the 2013 ISO changes to the additional insured endorsement, and held that coverage under a policy providing additional insured coverage was limited to the $1,000,000 required by contract, and not the $2,500,000 limit to the policy.
In Zurich, Zurich and its named insured D.A. Collins sought the full limits of the primary policy issued by XL to the D.A. Collins’ subcontractor, HBI, which are $2,5000 per occurrence and in the aggregate, for an underlying personal injury lawsuit. XL also issued an excess policy in the amount of $5,000,000 to HBI.
The contract between D.A. Collins and HBI required HBI to obtain commercial liability coverage “in an amount of $1,000,000 per occurrence and $2,000,000 in the aggregate. It further provides that the “required limits for the umbrella excess coverage shall be sufficient to provide a total of $5,000,000 per occurrence/aggregate.”
Read the court decisionRead the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Panthers Withdraw City, County Deal Over Abandoned Facility
September 19, 2022 —
The Associated Press (Jeffrey Collins) - BloombergColumbia, S.C. (AP) -- Carolina Panthers owner David Tepper’s real estate company wants to revoke a bankruptcy settlement it negotiated with the city and county where its abandoned South Carolina practice facility was supposed to be built because it says the governments are making exorbitant and unreasonable demands.
GT Real Estate Holdings had offered $21 million to York County. It suggested giving the proceeds from selling part of its site in Rock Hill so the city would get at least $20 million.
But the county and city have filed separate lawsuits and court papers. York County said it is entitled to more than $80 million in part to get back money from a special penny sales tax that was supposed to expand a road but Tepper’s company used for the proposed practice facility.
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
Several Lewis Brisbois Partners Recognized by Sacramento Magazine in List of Top Lawyers
October 03, 2022 —
Lewis BrisboisSacramento, Calif. (September 2, 2022) - Sacramento Magazine has recognized several partners from Lewis Brisbois' Sacramento office on its List of Top Lawyers of 2022. The list is developed through a peer nomination process, with nominees then evaluated on the basis of survey results, the legitimacy of their licenses, and their standing with the State Bar of California. Qualifying attorneys who then receive the highest number of votes from their peers are included in the list, which is organized by area of practice.
Congratulations to:
- Managing Partner John S. Poulos, recognized for Construction Law and Construction Litigation.
- Partner Paul R. Baleria, recognized for Medical Malpractice.
- Partner Scott E. Bartel, recognized for Securities & Corporate Finance and Securities Litigation.
- Partner Greg L. Johnson, recognized for Banking & Financial Services.
- Partner Eric J. Stiff, recognized for Mergers & Acquisitions.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois