“Genuine” Issue of “Material” Fact and Summary Judgments
December 18, 2022 —
David Adelstein - Florida Construction Legal UpdatesThis is short article on summary judgments. A motion for summary judgment, as you may already know, is a procedural vehicle to try to dispose of issues or claims in a lawsuit, either partially or fully. The objective is that the moving party claims that there is no genuine issue of material fact and that they are entitled to a judgment (partially or finally) as a matter of law. See Florida Rule of Civil Procedure 1.510. In May of 2021, Florida adopted the federal summary judgment standard which theoretically means trial courts should grant more summary judgments, not less, based on the more rigorous standard.
There have been many articles that discuss Florida’s new summary judgment standard including how the standard used to be versus how it is supposed to be now that it is modeled after the federal standard. That isn’t the point of this posting. (Here is an article published in the Florida Bar Journal that provides a primer on summary judgments in case you are interested.)
The point of this posting is to understand the words “genuine” and “material” as underlined above when moving for or defending against a summary judgment. These words have important meaning in the context of motions for summary judgment. In other words, what is a genuine issue of material fact? This is a question that should not be overlooked because these are the facts you want to focus on and frame your arguments on when moving for or defending against a summary judgment. Notably, these are also the facts you want to introduce and emphasize at trial.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Hawaii Appellate Court Finds Duty to Defend Group Builders Case
May 10, 2013 —
Tred EyerlyOn May 19, 2010, the Hawaii Intermediate Court of Appeals determined construction defect claims did not constitute an occurrence under a CGL policy.Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010) ("Group Builders I"). The appeal in Group Builders I, however, only addressed the duty to indemnify. The ICA has now issued a second decision (unpublished), holding that there is was duty to defend Group Builders on the construction defect claims under Hawaii law, based upon the policy language and the allegations in the underlying complaint. Group Builders, Inc. v. Admiral Ins. Co., 2013 Haw.App. LEXIS 207 (Haw. Ct. App. April 15, 2013).
The underlying suit involved allegations by Hilton Hotels Corp. that Group Builders, a subcontractor working on an addition to the hotel, was responsible for mold found after completion of the project. Hilton alleged that the "design, construction, installation, and/or selection of the . . . building exterior wall finish . . . did not provide an adequate air and/or moisture barriers." The counts alleged against Group Builders included breach of contract and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyMr. Eyerly can be contacted at
te@hawaiilawyer.com
Home Buyer Disclosures, What’s Required and What Isn’t
February 05, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Sandy Gadow of the Washington Post, while all states require a property disclosure statement, “the extent of what must be revealed can vary from state to state, county to county and even city to city.” Gadow stated that while, “Federal law requires certain disclosures, such as the existence of asbestos or lead-based paint in the home or other known health or safety risks. But the enforcement of other disclosures (such as reporting certain environmental conditions pertinent to the area, or the existence of Megan’s Law offenders) will be determined by local ordinance or law.”
Gadow recommends home buyers go to their state’s Department of Real Estate to discover the Seller Disclosure requirements.
Read the court decisionRead the full story...Reprinted courtesy of
The Regulations on the Trump Administration's Chopping Block
August 02, 2017 —
Pam Radtke Russell - Engineering News-RecordThe Trump administration's next big step toward repealing the controversial Waters of the U.S. (WOTUS) rule is official, with a proposal to rescind the Obama-era regulation appearing in the Federal Register on July 27, setting off a relatively short comment period that will end Aug. 28.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMr. Russell may be contacted at
Russellp@bnpmedia.com
The Right to Repair Act (Civ.C §895 et seq.) Applies and is the Exclusive Remedy for a Homeowner Alleging Construction Defects
February 07, 2018 —
Craig Wallace – Smith Currie McMillin Albany LLC v. Superior Court (01.18.18) ____ Cal.4th _____ (2018 WL 456728)
The California Supreme Court confirmed that the Right to Repair Act (CA Civil Code § 895, et seq. and often referred to by its legislative nomenclature as “SB800”) applies broadly to any action by a residential owner seeking recovery of damages for construction defects, regardless of whether such defects caused property damages or only economic losses. This includes the right in the Act of the builder to attempt repairs prior to the owner filing a lawsuit.
Background
Homeowners sued builder for construction defects. Included in their causes of action was a cause of action for violation of the Right To Repair Act. The Act requires that before filing litigation, a homeowner must give the builder notice and engage in a nonadversarial prelitigation process which gives the builder a right to repair the defects. The builder asked the court to stay the homeowners’ action so the prelitigaiton process could be undertaken. Rather than give the builder the repair right, the homeowners dismissed the particular cause of action from their case, leaving only other so-called common law and warranty causes of action. The common law claims sought recovery for property damage caused by the defects. The builder nonetheless asked to the Court to stay the action so it could exercise its right to repair.
The trial court, relying on
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, denied builder’s request to stay the action. The
Liberty Mutual Court concluded that certain common law construction defect claims fell outside the purview of the Act. Builder appealed. The Court of Appeal disagreed with
Liberty Mutual, so did not follow it, granted the builder’s request for a stay, and directed that the homeowners afford the builder the right to repair the claimed defects as provided under the Act.
The California Supreme Court affirmed, disapproving
Liberty Mutual and the subsequent cases relying on it.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Wallace, Smith CurrieMr. Wallace may be contacted at
swwallace@smithcurrie.com
Building a Case: Document Management for Construction Litigation
October 07, 2019 —
Robert A. Gallagher, Jane Fox Lehman, & Michael I. Frankel, Pepper Hamilton LLP - ConsensusDocsSuccess in construction litigation often turns less on counsel’s ability to craft legal arguments and more on counsel’s ability to gather, master and present the often complex set of facts underlying the case. In construction matters, most of the key facts are found in documents: contract documents, drawings, plans and specifications, schedules, submittals, progress reports, daily logs, change orders, invoices and payment records. Nowadays, these documents will almost certainly be created, exchanged and stored electronically; many will never exist in hard copy. As such, timely collection, organization and analysis of electronically stored information (ESI) is crucially important in construction litigation.
The construction industry has always involved a large quantity of records. Today, the majority of those records exist only as ESI: Design professionals use computer-aided design (CAD) software to create construction plans. Construction managers use Primavera or similar software to create schedules and workflows. Estimators use job cost control programs. Innovative firms capture digital photos of the project, from mobilization through the punch process.
Because ESI is created and exchanged at a higher rate than hard-copy documents, ESI has facilitated a dramatic increase in the volume of records associated with construction projects. Further compounding the increase is the proliferation of mobile devices. With a smartphone in every pocket, ESI creation has moved out of the home office and the site trailer and onto the site itself. As the volume of ESI expands, so too does the time and expense associated with storing, processing, reviewing and producing these records. This article will cover strategies for balancing time and expense with the requirements of the rules and the needs of the case.
Reprinted courtesy of Pepper Hamilton LLP attorneys
Robert A. Gallagher,
Jane Fox Lehman and
Michael I. Frankel
Mr. Gallagher may be contacted at gallagherr@pepperlaw.com
Ms. Lehman may be contacted at lehmanj@pepperlaw.com
Mr. Frankel may be contacted at frankelm@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Flood Sublimits Do Not Apply to Loss Caused by Named Windstorm
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe New Jersey Superior Court considered whether recovery for storm surge was limited by the policy's sublimit for loss caused by flood. Public Serv. Enter. Group, Inc. v. Ace Am. Ins. Co., 2015 N. J. Super. Unpub. LEXIS 620 (N.J. Super. Ct. Law Div. March 23, 2015).
Storm surge from Superstorm Sandy inundated and damaged Public Service Enterprise Group, Inc.'s (PSEG) property, including eight large generating stations. PSEG had coverage of $1 billion under policies with defendant carriers. There was no sublimit in the policies for "named windstorms," other than named windstorms in Florida. A $250 million sublimit appeared in the policies for losses caused by "flood."
The carriers paid only a portion of PSEG's claim. The total damages exceeded $500 million.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Thanks for the Super Lawyers Nod for 2019!
May 20, 2019 —
Christopher G. Hill - Construction Law MusingsIt is with humility and a sense of accomplishment that I announce that I have been selected for the third straight year to the Virginia Super Lawyers in the Construction Litigation category for 2019. Add this to my recent election to the Virginia Legal Elite in Construction and I’ve had a pretty good year. As always, I am thrilled to be included on these peer elected lists.
So without further ado, thank you to my peers and those on the panel at Virginia Super Lawyers for the great honor. I feel quite proud to be part of the 5% of Virginia attorneys that made this list for 2019.
The full lists of Virginia Super Lawyers will appear in the May edition of Richmond Magazine. Please check it out.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com